A reactor, which will contain corrosive liquid, has been design. If the reactor is made of mild steel, the initial installed

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Number of years n=4 yrs Installed Cost of first reactor C1=$ 6000 Interest I=4 %=4/100=0.04 Capitalized cost of First reac0.632=1.04^n-1 1.632 =1.04^n Take In on both sides as In X^n=n*In X Ln 1.632/ ln 1.04=n n=12.5 yrs Useful life period of seco

Add a comment
Know the answer?
Add Answer to:
Engineering Economics .... I need to solution this question within less than half hour necessary and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A reactor, which will contain corrosive liquid, has been design. If the reactor is made of...

    A reactor, which will contain corrosive liquid, has been design. If the reactor is made of mild steel, the initial installed cost will be $6000, and the useful life period will be 4 years. Since stainless steel is highly resistant to the corrosive action of the liquids, stainless steel, as the material of construction, has been proposed as an alternative to mild steel. the stainless steel reactor would have an initial installed cost of $16000. The scrape value at the...

  • A reactor, which will contain corrosive liquid, has been design. If the reactor is made of...

    A reactor, which will contain corrosive liquid, has been design. If the reactor is made of mild steel, the initial installed cost will be $6000, and the useful life period will be 4 years. Since stainless steel is highly resistant to the corrosive action of the liquids, stainless steel, as the material of construction, has been proposed as an alternative to mild steel. the stainless steel reactor would have an initial installed cost of $16000. The scrape value at the...

  • Engineering economics I need a solution within half an hour The installation cost of a 20...

    Engineering economics I need a solution within half an hour The installation cost of a 20 m3 (cubic meter) stainless- steel tank in 1975 was $5000. The tank is cylindrical with flat top and bottom, and the diameter is 6 m. If the entire outer surface of the tank is to be covered with 2-in. thickness of Magnesia block, estimated the present total cost for the insulated tank at 1980. The cost for the 2-in. magnesia block was $1.40 per...

  • This question concerns the Engineering economics I needed the solution within half an hour يجب اخذ...

    This question concerns the Engineering economics I needed the solution within half an hour يجب اخذ ثلاث مراتب بعد الفارزة في النواتج. The installation cost of a 20 m3 (cubic meter) stainless-steel tank in 1975 was $5000. The tank is cylindrical with flat top and bottom, and the diameter is 6 m. If the entire outer surface of the tank is to be covered with 2-in. thickness of Magnesia block, estimated the present total cost for the insulated tank at...

  • I need help with question 7.12. I looked at the step-by-step solution for that one but someone posted a comment saying...

    I need help with question 7.12. I looked at the step-by-step solution for that one but someone posted a comment saying that the answer is wrong and no one has commented on what the correct answer should be 201 Problems Determination of ROR 7.7 If a manufacturer of slectronic devices invests S650,000 in equipment for making compact piezo electric accelerometers for general purpose vibra Lion measurement estimate the rate of return from revenue of $225.000 per year for 10 years...

  • I am in desperate need of help with this project. Apparently my answers are all wrong....

    I am in desperate need of help with this project. Apparently my answers are all wrong. 3:02 PM Thu Feb 27 4796% AC 321 Intl - FA19 - Comprehensive Project Insert Draw Formulas Data Review View 8 Q o Calibri (Body) 12 B U Home B ^ A = 1 EE tx ã į 19 2 3 4 All work must be completed using this Excel spreadsheet. All journal extries, financial statements, etc. must be prepared in clean, proper form....

  • I need help with Part 6 (closing journal entries) and Part 7 (post closing trial balance)...

    I need help with Part 6 (closing journal entries) and Part 7 (post closing trial balance) 3:02 PM Thu Feb 27 4796% AC 321 Intl - FA19 - Comprehensive Project Insert Draw Formulas Data Review View 8 Q o Calibri (Body) 12 B U Home B ^ A = 1 EE tx ã į 19 2 3 4 All work must be completed using this Excel spreadsheet. All journal extries, financial statements, etc. must be prepared in clean, proper form....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT