Please answer 3 - 5 thank you!3. In his neighborhood, a businessman would be setting up a repair shop. At a cash price of P 2.8 Million, he would be gettin - 5 thank you!

0 0
Add a comment Improve this question Transcribed image text
Answer #1

EUAC for Plant 1 = 2 billion + 2 milion(A/P, 8%, 15) + 3 million (A/P, 8%, 15)

(A/P, 8%, 15) = 0.1168 (using factor table for 8% and 15 years)

EUAC = 2 billion + 2 million *0.1168 + 3 * 0.1168 = 2 billion + 233600 + 350400 = 2,000,584,000

Pcost of plant after 15 years = 1.5 billion(P/A, *%, 15) = 12839250000

EUAC for plant 2 = 1.25 billion + 12839250000(A/P, 8%, 15) + 1.5 million (A/P, 8%, 15) + 3 million (A/P, 8%, 15)

(P/A, 8%, 15) = 8.5595 (from factor table)

EUAC = 1.25 billion + 1,499,624,400 + 175200 + 350400 = 3,000,150,000

SInce, Option 1 has lower EUAC, It is better option than option 2.

Add a comment
Know the answer?
Add Answer to:
Please answer 3 - 5 thank you! - 5 thank you! 3. In his neighborhood, a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Government has two (2) plans to deal with their water supply problem. Option 1 is to...

    Government has two (2) plans to deal with their water supply problem. Option 1 is to build a complete water pumping plant costing P 2 Billion, which would meet all needs during the 1st 30 years. Annual maintenance costs are estimated to be at P 2 Million for the 1st 15 years and P 3 Million for the succeeding 15 years. Option 2 is to build a partial water pumping plant at a cost of P 1.25 Billion, which would...

  • In his neighborhood, a businessman would be setting up a repair shop. At a cash price...

    In his neighborhood, a businessman would be setting up a repair shop. At a cash price of P 2.8 Million, he would be getting a complete set of tools and equipment from a vendor. If by installment, he would need to pay today P 280,000 and the balance is payable at the end of each quarter for 5 years. The interest is at 18% cpd. qtr. Determine the following: a) the quarterly payment; b) If he chooses to pay at...

  • Given the new found interest in nuclear power plants due to potential carbon taxes, you consider starting a company to build a nuclear power plant. Before you can build the plant, you need to gather p...

    Given the new found interest in nuclear power plants due to potential carbon taxes, you consider starting a company to build a nuclear power plant. Before you can build the plant, you need to gather permits, fight lawsuits and so forth. That will cost $800 million today and take 5 years to resolve with a 35% probability of success. If you build the plant, you must pay $9 billion the day you start building the plant, which is immediately after...

  • (6) A municipal water authority is considering the installation of a new water system. Two options...

    (6) A municipal water authority is considering the installation of a new water system. Two options are being considered. The first option is a steel pipeline with an installation cost of $225 million. Annual maintenance and pumping costs begin at $15 million and increase by $1.0 million per year. The second option is a gravity fed concrete canal with an installation cost of $400 million. Annual maintenance costs begin at $0.5 million and increase by $0.4 million per year. If...

  • use x= SR8000 include cash flow diagram H2.3 = A large refinery and petrochemical complex is...

    use x= SR8000 include cash flow diagram H2.3 = A large refinery and petrochemical complex is planning to manufacture caustic soda, which will use 10,000 gallons of feed water per day. Two types of feed-water storage installation are being considered to serve over 40 years of useful life: III Option 1: Build a 20,000-gallon tank on a tower. The cost of installing the tank and tower is estimated to be $164,000. The salvage value is estimated to be negligible. II...

  • please help on problems 1 and 2. thank you. Exercise 1 The City of lowa City...

    please help on problems 1 and 2. thank you. Exercise 1 The City of lowa City is considering two options to replace broken concrete at the Pedestrian mall, between Clinton and Linn Streets. One of the options implies spending $120,000 using "Grade-A' concrete that has a life of 15 years, with an annual maintenance cost of $5,000. The other option implies using "Grade Super-X" plasticised concrete that has a life of 25 years with no need for annual maintenance. What...

  • please solve without spreadsheet 2) A proposed civic center is estimated to cost $10,000,000 and have...

    please solve without spreadsheet 2) A proposed civic center is estimated to cost $10,000,000 and have a life of 45 years. The maintenance costs are estimated to be: Paint & normal repairs: $20,000/yr (billed and paid at the end of first year and each succeeding year) and increase 10%/year over the 45 year life. Replace air conditioner, floor tiles, seat upholstery every 15 year: the cost 15 years from now is estimated at $2,000,000 and the cost is expected to...

  • Please Show all work and formulas! Problem 4 You have just won a lottery of $1...

    Please Show all work and formulas! Problem 4 You have just won a lottery of $1 million and you can choose among the following three payout options.  The effective annual interest rate (EAR) is 5%. Option A: $200,000 right now and $100,000 every two years, starting 2 years from now and ending 16 years from now. Option B: $100,000 a year at the end of the next 10 years, with the first payment one year from today. Option C: Twenty annual...

  • 5-31 Teléfono Mexico is expanding its facilities to serve a new manufacturing plant. The new plant...

    5-31 Teléfono Mexico is expanding its facilities to serve a new manufacturing plant. The new plant will require 2000 telephone lines this year, and another 2000 lines after expansion in 10 years. The plant will operate for 30 years. Option 1 Provide one cable now with capacity to serve 4000 lines. The cable will cost $20,000 and annual maintenance costs will be $1500. Option 2 Provide a cable with capacity to serve 2000 lines now and a second cable to...

  • will rate and like thanks! Had trouble. can you please show work! PART 2 -COMPARING TWO...

    will rate and like thanks! Had trouble. can you please show work! PART 2 -COMPARING TWO ALTERNATIVES The city of Bernoulliville is currently facing a water crisis and will need reservoir. The city has hired you as a construction e and select the most affordable option to bring water into the city. Assume as hired you as a construction expert to evaluate the cost of two alternative proje er crisis and will need to pipe water from a nearby to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT