On average, each unit produced by the Kantor Company takes 0.90 worker hours and 0.02 hours...

On average, each unit produced by the Kantor Company takes 0.90 worker hours and 0.02 hours of machine time. Furthermore, each worker and machine is available 160 hours a month. Use these planning values and the following sales order forecast to estimate

a) The number of worker hours and machine hours needed each month

b) The number of actual workers and machines needed each month (rounded to the nearest whole number)

Month Sales Forecast

October 44,000

November 52,000  

December 68,000

January 69,000

February 58,000

March 46,000


0 0
Add a comment Improve this question Transcribed image text
Answer #1

Given:

Worker hour per unit = 0.90 hours

Machine hour per unit = 0.02 hours

Total worker and machine hours available per month = 160 hours

(a)

One unit requires 0.90 worker hours. In the month of October, 44,000 units are forecasted. So the number of worker hours for 44,000 units will be 44,000*0.90. Similarly, for each month the calculation is done. For machine-hours, we will multiply by 0.02, as for each unit, 0.02 machine hours are required.

Month

Sales Forecast

Worker hours needed

Machine hours needed

October

44,000

44,000*0.90=39,600

44,000*0.02=880

November

52,000

52,000*0.90=46,800

52,000*0.02=1,040

December

68,000

68,000*0.90=61,200

68,000*0.02=1,360

January

69,000

69,000*0.90=62,100

69,000*0.02=1,380

February

58,000

58,000*0.90=52,200

58,000*0.02=1,160

March

46,000

46,000*0.90=41,400

46,000*0.02=920

(b)

The total worker and machine hours available are 160. So we need to divide available working hours by 160 to find out the number of workers and machines required per month.

Month

Sales Forecast

Number of Workers needed

Number of Machines needed

October

44,000

39,600/160=247.5=248

880/160=5.5=6

November

52,000

46,800/160=292.5=293

1,040/160=6.5=7

December

68,000

61,200/160=382.5=383

1,360/160=8.5=9

January

69,000

62,100/160=388.125=389

1,380/160=8.625=9

February

58,000

52,200/160=326.25=327

1,160/160=7.25=8

March

46,000

41,400/160=258.75=259

920/160=5.75=6

Add a comment
Know the answer?
Add Answer to:
On average, each unit produced by the Kantor Company takes 0.90 worker hours and 0.02 hours...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A company is planning the aggregate production capacity required to produce the sales forecast in this table: Sales Forecast (thousands of tons) Resin Ist Quarter 2nd Quarter 3rd Quarter 4th Quar...

    A company is planning the aggregate production capacity required to produce the sales forecast in this table: Sales Forecast (thousands of tons) Resin Ist Quarter 2nd Quarter 3rd Quarter 4th Quarter 9.0 7.0 6.0 10.0 8.0 3.0 12.0 5.0 4.0 14.0 10.0 7.0 Ample machine capacity exists to produce the forecast and each ton of resin re- quires five labor-hours. a. Compute the aggregate demand for resin in each quarter. b. Compute the aggregate number of labor-hours in each quarter...

  • Complete the level production plan, using the following information. The only costs you need to consider...

    Complete the level production plan, using the following information. The only costs you need to consider here are layoff, hiring, and inventory costs. If you complete the plan correctly, your hiring, layoff, and inventory costs should match those given here. E: Click the icon to view the costs table. Click the icon to view the forecasted sales. Fill in the production plan table below (enter your responses rounded to the nearest whole number). Month Forecasted sales Sales in worker hours...

  • P 2 Level : Product Activity based driver Units produced Setups Design changees Machine hours Plant total 90 B0 Uni...

    P 2 Level : Product Activity based driver Units produced Setups Design changees Machine hours Plant total 90 B0 Unit Batch Product 40 Plant 60 180 Total www Units produced 30 Setups 16 Design changes Machine hours 20 15 Activity based costing is used K Overhead allocated to product A 14 Total Cost Total Units 61 C 90 Rate Number units Assigned Overhead Rate D 100 Form Use Good FOR THE PROBLEMS THAT FOLLOW Show computations each 4 pts CASH...

  • Show Formulas Manufacturing Overhead Budget 2020 October November December QUARTER Units Produced Variable Overhead Rate per...

    Show Formulas Manufacturing Overhead Budget 2020 October November December QUARTER Units Produced Variable Overhead Rate per Unit Total Variable Overhead Cost Fixed Overhead TOTAL OVERHEAD COST Noncash Overhead Expenses TOTAL OVERHEAD DISBURSEMENTS Lexie's Wool Sweaters Balance Sheet As of September 30, 2020 ASSETS LIABILITIES & EQUITIES Cash $    150,000.00 Accounts Payable $      14,500.00 Accounts Receivable $      75,000.00 Notes Payable $                  -   Raw Materials Inventory $      28,929.60 Interest Payable $                  -   Finished Goods Inventory $      61,125.00 TOTAL LIABILITIES $      14,500.00 PP&E,...

  • Shoney Video Concepts produces a line of video streaming servers that are linked to personal computers...

    Shoney Video Concepts produces a line of video streaming servers that are linked to personal computers for storing movies. These devices have very fast access and large storage capacity.     Shoney is trying to determine a production plan for the next 12 months. The main criterion for this plan is that the employment level is to be held constant over the period. Shoney is continuing in its R&D efforts to develop new applications and prefers not to cause any adverse feelings...

  • NYY is a winter jacket manufacturer company with manufacturing facilities in the U.S.A. Winter jacket demand...

    NYY is a winter jacket manufacturer company with manufacturing facilities in the U.S.A. Winter jacket demand is seasonal peaking in the winter as the temperatures along the East Coast dipping well below zero. Production of winter jackets requires some certain amount of work and NYY jacket manufacturer has multiple options to handle seasonal demand. The first option is NYY can prefer to increase number of workers by adding workers during the peak season. Second option is NYY can subcontract out...

  • Problem 8-13 Shoney Video Concepts produces a line of video streaming servers that are linked to...

    Problem 8-13 Shoney Video Concepts produces a line of video streaming servers that are linked to personal computers for storing movies. These devices have very fast access and large storage capacity.     Shoney is trying to determine a production plan for the next 12 months. The main criterion for this plan is that the employment level is to be held constant over the period. Shoney is continuing in its R&D efforts to develop new applications and prefers not to cause any...

  • NUMBER OF EMPLOYEES 2013-PRODUCTION 1,000s MONTH January 90 May June September 130 130 100 Octobe...

    Please show how to do a pure chase strategy given this info NUMBER OF EMPLOYEES 2013-PRODUCTION 1,000s MONTH January 90 May June September 130 130 100 October 107 December space was available at the plant, therefore, additional space would have to be rented. In addition, the cost of capital is high because of the company's low credit rating. Taking all of these factors into account, Joan estimated the cost of storing 1,000 pounds of product for one month to be...

  • Andree’s All-American manufactures fashionable tennis wear, needs help planning production for next year. Demand for tennis...

    Andree’s All-American manufactures fashionable tennis wear, needs help planning production for next year. Demand for tennis gear is fairly stable, but has peaks during the summer months. Month Demand Forecast January 500 February 300 March 200 April 1500 May 2500 June 3500 July 4500 August 2500 September 500 October 300 November 300 December 2500 Beginning workforce 9 workers Production per day 9 units per employee Production cost during regular time $50 per unit Subcontracting cost $75 per unit Increasing production...

  • Maria Chavez owns a catering company that serves food and beverages at parties and business functions....

    Maria Chavez owns a catering company that serves food and beverages at parties and business functions. Chavez’s business is seasonal, with a heavy schedule during the summer months and holidays and a lighter schedule at other times. One of the major events Chavez’s customers request is a cocktail party. She offers a standard cocktail party and has estimated the cost per guest as follows: Food and beverages $ 17.00 Labor (0.5 hour @ $11.00 /hr.) 5.50 Overhead (0.5 hour @...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT