Question

3. Assume that the time required to pour a concrete floor for a structure (D) has a triangular distribution between 18 and 22
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Page 1 ® Triangular Distribution : f(x) a18 19 c=20 21 b=22 We know that, for triangular distribution xea acxsc f (x) 2x-a) (1/2 x Page-2 2(22 - 2D x (222) (22-18) (22-20) 1/2 0,25x1 P(0321) = 0.125 p (D520) = 1 / 2 x f(x) x base a=18 c=20=X b=22 1 xprob (D =19) Page 3 1 x basex f(x) = 1/2x1 x 22-0) (b-a) ((-a) 2(19-18) 22 10 re 21 = 1/2X1 X (92-18) (*20-18 base PP(D=19) =

Add a comment
Know the answer?
Add Answer to:
3. Assume that the time required to pour a concrete floor for a structure (D) has...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3. Assume that the time required to pour a concrete floor for a structure (D) has...

    3. Assume that the time required to pour a concrete floor for a structure (D) has a triangular distribution between 18 and 22 days with the most required time of 20 days.. Determine the following probabilities: a. (5%)Prob (D > 21) b. (5%) Prob (D = 20) C. (5%) Prob (D = 19)

  • 3- Assume that the time required to pour a concrete floor for a structure (D) has...

    3- Assume that the time required to pour a concrete floor for a structure (D) has a triangular distribution between 18 and 22 days with the most required time of 20 days... Determine the following probabilities: a. (5%)Prob (D > 21) b. (5%) Prob (D = 20) c. (5%) Prob (D = 19)

  • 3. Assume that the time required to pour a concrete floor for a structure (D) has...

    3. Assume that the time required to pour a concrete floor for a structure (D) has a triangular distribution between 18 and 22 days with the most required time of 20 days.. Determine the following probabilities: a. (5%)Prob (D > 21) b. (5%) Prob (D = 20) c. (5%) Prob (D = 19)

  • 3- Assume that the time required to pour a concrete floor for a structure (D) has...

    3- Assume that the time required to pour a concrete floor for a structure (D) has a triangular distribution between 18 and 22 days with the most required time of 20 days.. Determine the following probabilities: a. (5%)Prob (D > 21) b. (5%) Prob (D ≤ 20) c. (5%) Prob (D = 19)

  • 3 4657.3 12. 12. How many cubic yards of concrete are needed to pour a slab...

    3 4657.3 12. 12. How many cubic yards of concrete are needed to pour a slab 60' x 80' × 5" thick? 13. 13. How many gallons of paint are required to paint one side of a block wall of the following dimensions: 6'x 172? The paint being used will cover 200 ft per gallon. 14. 14. Compute the gallons of sealer required to seal a floor 120 x 250. The sealer being used will cover 175 ft per gallon....

  • A floor system (Figure 2) consists of a 3 in. concrete slab supported by continuous T...

    A floor system (Figure 2) consists of a 3 in. concrete slab supported by continuous T beams with a span L=24 ft, and 47 in. on centers distance between beams. Web dimensions, as determined by the negative-moment requirements at the supports are bw=11 in. and d=20 in. Use concrete clear cover of 2 in. Determine the tensile steel of the T-beam that is required at mid-span to resist a factored positive moment of Mu=530 kip-ft if fc’=3,000 psi and fy=60,000...

  • Problem 1 While performing scheduling work on a project you have determined that one activity has...

    Problem 1 While performing scheduling work on a project you have determined that one activity has a great deal of variability. A sample of times (30) the task has been completed is provided the table below. Assume that the task is considered to be "late" if the task duration is two days greater than the mean value (rounded to the nearest whole day), and "early" if the task duration is two days less than the mean value (rounded to the...

  • x 19 20 21 22 23 F(x) 18 10 7 8 5 Let x be the...

    x 19 20 21 22 23 F(x) 18 10 7 8 5 Let x be the ages of students in a class. Given the frequency distribution F(x) above, determine the following probabilities: (a) P(x>20)= (b) P(x≤22)= (c) P(x≥20)=

  • 3.-/5 points BBBasicStat8 7.1.008.MI. The incubation time for a breed of chicks is normally distributed with...

    3.-/5 points BBBasicStat8 7.1.008.MI. The incubation time for a breed of chicks is normally distributed with a mean of 22 days and standard deviation of approximately 1 day. Look at the figure below and answer the following questions. If 1000 eggs are being incubated, how many chicks do we expect will hatch in the following time periods? (Note: In this problem, let us agree to think of a single day or a succession of days as a continuous interval of...

  • Given: Measured compressive strength of concrete as a function of curing time Curing time (days) Compressive...

    Given: Measured compressive strength of concrete as a function of curing time Curing time (days) Compressive strength of concrete (MPa) 17 23 26 28 29 30 14 21 28 (a) Using Excel, prepare a scatter chart with curing time on the horizontal axis and compressive strength on the vertical axis. Show only black markers with no lines and format your chart in the usual way (Times new roman 16 bold axis numbers and Times new roman 18 bold axis titles)....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT