Question

QUESTION 13 A design engineer wants to construct a sample mean chart for controlling the service life of a halogen headlamp h
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 13= Samples out of control = Sample 2 and Sample 3

Reason= Sample 2 and sample 3 has the data points out of LCL range0

Add a comment
Know the answer?
Add Answer to:
QUESTION 13 A design engineer wants to construct a sample mean chart for controlling the service...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • I need help with my test review question please A design engineer wants to construct a...

    I need help with my test review question please A design engineer wants to construct a sample mean chart for controlling the service life of a halogen headlamp his company produces. He knows from numerous previous samples that this service life is normally distributed with a mean of 500 hours and a standard deviation of 20 hours. On three recent production batches, he tested service life on random samples of four headlamps, with these results: Service life in hours Sample...

  • QUESTION 12 A design engineer wants to construct a sample mean chart for controlling the service...

    QUESTION 12 A design engineer wants to construct a sample mean chart for controlling the service life of a halogen headlamp his company produces. He knows from numerous previous samples that this service life is normally distributed with a mean of 500 hours and a standard deviation of 20 hours. On three recent production batches, he tested service life on random samples of four headlamps, with these results: Service life in hours Sample 1 Sample 2 Sample 3 Sample 4...

  • A design engineer wants to construct a sample mean chart for controlling the service life of...

    A design engineer wants to construct a sample mean chart for controlling the service life of a halogen headlamp his company produces. He knows from numerous previous samples that this service life is normally distributed with a mean of 500 hours and a standard deviation of 20 hours. On three recent production batches, he tested service life on random samples of four headlamps, with these results, If he uses upper and lower control limits of 520 and 480 hours, what...

  • A junior engineer has to build a sample mean chart for the machines making Oreo cookies....

    A junior engineer has to build a sample mean chart for the machines making Oreo cookies. He knows from numerous previous samples that this service life of the cream injectors is normally distributed with a mean of 760 hours and a standard deviation of 41.5 hours. In the last three weeks, he tested the service life on random samples of four production runs with these results: Sample Hours 1 721 765 762 784 2 784 782 764 747 3 764...

  • A junior engineer has to build a sample mean chart for the machines making Oreo cookies....

    A junior engineer has to build a sample mean chart for the machines making Oreo cookies. He knows from numerous previous samples that this service life of the cream injectors is normally distributed with a mean of 760 hours and a standard deviation of 41.5 hours. In the last three weeks, he tested the service life on random samples of four production runs with these results: Sample Hours 1 761 767 781 759 2 788 782 762 755 3 779...

  • Question pertains to the x-chart part Sample Mean Range 16 8 12 13 6 6 4...

    Question pertains to the x-chart part Sample Mean Range 16 8 12 13 6 6 4 15 10 10 11 10 16 13 14 0 14 17 11 12 IU 12 12 11 13 14 12 7 8 13 9 11 14 7 13 15 10 15 Subsequently, samples of size 5 were taken from the process every week for the next 10 weeks. The times were measured and the following results oblained: Sample Mean Range 16 9 17 12...

  • Thanks so much :) Formulas and Tables for Questions 28-31 Setting Mean Chart Limits ( -chart)...

    Thanks so much :) Formulas and Tables for Questions 28-31 Setting Mean Chart Limits ( -chart) Upper controllimit. UCL, = + A,R Lower controllimit, LCL, = 2 - A R Setting Range Chart Limits (R-chart) Upper controllimit, UCLR=DAR Lower controllimit, LCLR=DER where - mean of the sample means, A2, D3, D4-table factors for control charts R-average range of the samples R-average range of the samples Tables Table 3. Factors for Computing Control Chart Limits (3 sigma) SAMPLE SIZE, n MEAN...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT