A manufacturing process on the critical path of a project is
expected to get easier as we go along and the project manager wants
to plan accurately for when he expects the task to be
complete.
How many cycles are anticipated before a new operator reaches a
standard production time of 50 minutes if the first unit required
101 minutes and the learning curve rate is 0.77?
Tn = T1 * nb
T1 = 101 minutes
b = log (r) / log 2
b = −0.37707
Tn = 50
So,
50 = 101 * n−0.37707
Solving, we get
n=6.453573
So, we can anticipate atleast 7 cycles before a new operator reaches the given condition.
PLEASE LEAVE A LIKE. IT REALLY HELPS ME A LOT. THANK YOU!!!
A manufacturing process on the critical path of a project is expected to get easier as...
NO EXPLANATION NEEDED, JUST ANSWER. A senior manager is in the process of selecting a project manager for a new initiative that is very important for the company’s future. What is the key factor in choosing a project manager? The project manager should be the most technically competent person on the team The PM works well with various levels of management The project manager should be the functional manager of the most people on the team The project manager must...
Case Study: Acme Manufacturing Company Steve Arnold is a production manager at Acme Manufacturing Company in New Jersey. When Steve drove into the parking lot at the plant on Tuesday morning at 8:35, he was already 35 minutes late for work. Steve had overslept that morning because the night before he had stayed up late to finish the monthly production report for his department. He parked his car and entered the rear of the plant building. Passing through the shipping...
Consider the proposal. Should SCF accept or reject ACL’s request? If you were the project manager, which option would you select? What risks are involved with your choice and with ACL’s request? Shell Case Fabricators BACKGROUND Shell Case Fabricators (SCF) designs and builds shell casings that enclose electronic products such as calculators, cell phones, modems. Typically the cases are plastic or plastic compounds. SCF has six different production lines that cover different types of product. For example, the largest high...
24. Project Evaluation This is a comprehensive project evaluation problem bringing together much of what you have learned in this and previous chapters. Suppose you have been hired as a financial consultant to Defense Electronics, Inc. (DEI), a large, publicly traded firm that is the market share leader in radar detection systems (RDS). The company is looking at setting up a manufacturing plant overseas to produce a new line of RDSs. This will be a 5-year project. The company bought...
Doesn’t Time Fly! It was 7.30 on a Tuesday morning, when John Edwards, general manager of the Jenkins Company’s main factory, turned on to the M3 to drive to his office in Basingstoke. The journey took about twenty minutes and gave John an opportunity to reflect on the problems of the plant without interruptions. The Jenkins Company ran three printing plants and had nationwide clients for its high-quality colour work. There were about 350 employees, almost half of whom were...
Hi, Kindly assist with my project management assignment below using the attached case study Question 1 Update the project charter for the remainder of the project in response to Adams’ memo (lines 241 through 246). Question 2 Prepare a plan for the remainder of the project in response to Adams’ memo (lines 241 through 246). Your answers to the above will be assessed in terms of the level of communication displayed, the insights and inferences drawn, and your ability to...
Susan Thomas is the vice president for human resources at National Products, a manufacturing company with 500 employees. The company has an opening for a general manager in one of its product divisions, and the president asked Susan to review the backgrounds of three department managers who are interested in being promoted to this position. She is expected either to recommend one of the three internal candidates or to begin recruitment of external candidates. The internal candidates are Charley Adams,...
How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...
Problem 12-24 Project Evaluation Suppose you have been hired as a financial consultant to Defense Electronics, Inc. (DEI), a large, publicly traded firm that is the market share leader in radar detection systems (RDSs). The company is looking at setting up a manufacturing plant overseas to produce a new line of RDSs. This will be a five-year project. The company bought some land three years ago for $4.8 million in anticipation of using it as a toxic dump site for...
Review the course project scenario Top Shelf was found in 1990 by Tie Woodward. Within five years, Top Shelf had established a solid presence in the global shoe business with production facilities in Asia and sales throughout the world By 2000, Top Shelf had a share of 45 percent of the global market in shoe sales. In 2001, Top Shelf made the Fortune 500 list of privately held companies and Tie was awarded the coveted International Business Award. However, Tie...