Question 18: A. Service Level = 0.8, Stockout Probability = 0.2
Selling Price (P) = $3
Cost Price (C) = $1
Salvaging Value (S) = $0.5
Cost of Understocking (Cu) = P - C = $2
Cost of Overstocking (Co) = C - S = 1 - 0.5 = $0.5
Optimum Service Level = Cu/(Cu + Co) = 2/2.5 = 0.8
Stockout Probability = 1 - 0.8 = 0.2
Question 19:E. BCE , 12
Path BCE is a path with maximum duration of completion.
So Critical Path : BCE
Project Completion Duration :12
Need help on whether the answers are right. if not, please provide the right ones. Thanks!...
need help with 18-22 marketing questions
med with francesca Je on the COUCO col grocery This Me span and no CHAPTER 35 Maring Crowng Customer and Engagement Company Caso Chick-Fil-A: Getting Better before Getting Bigger dong the food . Wh e n It Right way, Burger King and Taco Berge mong top of the C hos en bom a south Asocer lo Check Asminis to have a povinu once on who come in contact with Chick corted Chick SA Athough...