The mall building job was started and completed during the month. Direct materials used totaled $33,000;...

The mall building job was started and completed during the month. Direct materials used totaled $33,000; Direct labor costs were $42,000; manufacturing overhead applied was $21,000. Job 101 was for a total of 3,000 units.

-What is the total cost that should have been recorded on a job cost card for mall building job?

-What is the cost per unit for mall building job?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Solution:
CALCULTION OF TOTAL COST AND COST PER UNIT
Particulars Amount
Direct Materials $                  33,000
Direct Labor $                  42,000
Manufacturing overhead $                  21,000
Total Cost $                  96,000
Divide By "/" By  
No of Units Produced                         3,000 Units
Cost Per Unit $                    32.00
Answer =
Total Cost = $ 96,000
Cost Per Unit = $ 32.00
Add a comment
Know the answer?
Add Answer to:
The mall building job was started and completed during the month. Direct materials used totaled $33,000;...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • When Job 117 was completed, direct materials totaled $17,199; direct labor, $25,184; and factory overhead, $19,042....

    When Job 117 was completed, direct materials totaled $17,199; direct labor, $25,184; and factory overhead, $19,042. A total of 1,575 units were produced at a per-unit cost of a.$42,383 b.$61,425 c.$39 d.$1,575

  • When Job 117 was completed, direct materials totaled $42,754; direct labor, $54,414; and factory overhead, $32,390....

    When Job 117 was completed, direct materials totaled $42,754; direct labor, $54,414; and factory overhead, $32,390. A total of 3,926 units were produced at a per-unit cost of On: 533 Ob 53,926 Oc. $129,558 Od 597,166 Smith Company reports the following information: $68,250 Cost of goods manufactured Direct materials used Direct labor incurred Work in process inventory, January 1 27,000 25,000 11,000 Factory overhead is 75% of the cost of direct labor. Work in process inventory on December 31 is...

  • Calculator When Job 117 was completed, direct materials totaled $13,328; direct labor, $20,222; and factory overhead,...

    Calculator When Job 117 was completed, direct materials totaled $13,328; direct labor, $20,222; and factory overhead, $12,410. A total of 1,915 units were produced at a per-unit cost of Oa. $1,915 Ob $45.960 Oc. $33,550 Od $24 Direct labor and direct materials are Oa. period costs and expensed when incurred Ob. product costs and expensed when incurred Oc: period costs and expensed when the goods are sold Od product costs and expensed when the goods are sold

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead 4,900 Date 7,000 Beg. bal. Jan. 1 8 6,000 7,000 12 10,000 8,500 25 2,500 27 4,000 3,400 16,800 15,500 21,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($53,300 = 2,000) $15,500 21,000 16,800 $53,300 $26.65 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • Fact Pattern:Hamilton Company uses job-order costing. Manufacturing overhead is applied to production at a predetermined rate...

    Fact Pattern:Hamilton Company uses job-order costing. Manufacturing overhead is applied to production at a predetermined rate of 150% of direct labor cost. Any over- or underapplied overhead is closed to the cost of goods sold account at the end of each month. Additional information is available as follows: Job 101 was the only job in process at January 31, with accumulated costs as follows: Direct materials $4,000 Direct labor 2,000 Applied manufacturing overhead 3,000 Total manufacturing costs $9,000 Jobs 102,...

  • Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan....

    Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 1 7,000 4,900 5,700 7,000 10,000 8,500 2,200 4,000 21,000 3,400 16,800 14,900 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($52,700 = 2,000) $14,900 21,000 16,800 $52,700 $26.35 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work in Process Inventory on January 1 if this was the...

  • Job 243 was recently completed. The following data have been recorded on its job cost sheet:...

    Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor vage rate Machine-hours Number of units completed $50,370 420 labor-hours $ 10 per labor-hour 501 machine-hours 3,000 units 4 The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine- hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer...

  • Tyler Tooling Company uses a job order cost system with overhead applied to products on the...

    Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $234,840 and total machine hours at 61,800. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job:     Job 101 Job 102 Job 103 Total Direct materials used $...

  • 5. Tyler Tooling Company uses a job order cost system with overhead applied to products on...

    5. Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $201,600 and total machine hours at 63,000. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job: Job 101 Job 102 Job 103 Total Direct materials used...

  • Tyler Tooling Company uses a job order cost system with overhead applied to products on the...

    Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $213,520 and total machine hours at 62,800. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job:     Job 101 Job 102 Job 103 Total Direct materials used $...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT