1) Predetermine overhead rate = 126000/90000 = 140% of direct material used
2) Direct material used = 24000+137000-14000 = 147000
Applied overhead = 147000*1.4 = 205800
Actual overhead = 210400
Under applied overhead = 210400-205800 = 4600
3) Schedule of cost of goods manufactured
Direct material used | ||
Beginning raw material | 24000 | |
Raw material purchase | 137000 | |
Raw material available for use | 161000 | |
Less; Ending raw material | -14000 | |
Direct material used | 147000 | |
Direct labor | 86000 | |
Manufacturing overhead | 205800 | |
Total manufacturing cost | 438800 | |
Beginning work in process | 47000 | |
Total Cost of work in process | 485800 | |
Less: Ending WIP | -38000 | |
Cost of goods manufactured | 447800 | |
4) Unadjusted cost of goods sold = 74000+447800-56000 = 465800
5) Calculate following
Direct material | 8900 |
Direct labor | 16640 |
Manufacturing overhead (8900*1.4) | 12460 |
Total ending WIP | 38000 |
Required 1-5 please Problem 3-14 (Algo) Schedule of Cost of Goods Manufactured; Overhead Analysis (LO3-3, LO3-4]...
Problem 3-14 Schedule of Cost of Goods Manufactured; Overhead Analysis (LO3-3, LO3-4) Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $118,300 of manufacturing overhead for an estimated allocation base of $91,000 direct material dollars to be used in production. The company has provided the following data...
Problem 3-14 Schedule of Cost of Goods Manufactured; Overhead Analysis [LO3-3, LO3-4] Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $127,400 of manufacturing overhead for an estimated allocation base of $91,000 direct material dollars to be used in production. The company has provided the following data...
Problem 3-14 (Algo) Schedule of Cost of Goods Manufactured; Overhead Analysis (LO3-3, LO3-4) Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $118,300 of manufacturing overhead for an estimated allocation base of $91,000 direct material dollars to be used in production. The company has provided the following...
please show all work and formulas used PROBLEM 3-14 Schedule of Cost of Goods Manufactured; Overhead Analysis LO3-3, LO3-4 Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $800,000 of manufacturing overhead for an estimated allocation base of $500,000 direct material dollars to be Page 14 used...
Problem 3-14 Schedule of Cost of Goods Manufactured; Overhead Analysis [LO3-3, LO3-4] Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $121,800 of manufacturing overhead for an estimated allocation base of $87,000 direct material dollars to be used in production. The company has provided the following data...
Problem 3-14 Schedule of Cost of Goods Manufactured; Overhead Analysis [LO3-3, LO3-4] Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $124,600 of manufacturing overhead for an estimated allocation base of $89,000 direct material dollars to be used in production. The company has provided the following data...
Problem 3-14 Schedule of Cost of Goods Manufactured; Overhead Analysis (LO3-3, LO3-4) Gitano Products operates a job order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $127,400 of manufacturing overhead for an estimated allocation base of $91.000 direct material dollars to be used in production. The company has provided the following...
Problem 3-25 Schedule of Cost of Goods Manufactured; Overhead Analysis [LO3-1, LO3-2, LO3-3, LO3-6, LO3-7] Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $109,200 of manufacturing overhead for an estimated allocation base of $91,000 direct material dollars to be used in production. The company has provided...
i really need help with this question Problem 3-14 Schedule of Cost of Goods Manufactured; Overhead Analysis (LO3-3, LO3-4) Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $123,200 of manufacturing overhead for an estimated allocation base of $88,000 direct material dollars to be used in production....
Accounting Experts please help thumbs up for all correct answers Problem 3-14 Schedule of Cost of Goods Manufactured; Overhead Analysis [LO3-3, LO3-4) Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $123,200 of manufacturing overhead for an estimated allocation base of $88.000 direct material dollars to be...