utilties cost is a variable as given, vary with the activity.
supervisor salary is fixed it will be remain unchanged.
maintinance cost is mixed which has both component fixed as well as variable.
Answer to Part1-
utility cost per unit for may = Utilities cost/Machine shours
=70400/44000
= $ 1.6
Maintinance cost of july = Total cost - machine hours of july*$ 1.6 - fixed cost of supervisory salary for july month
= 292380 - 74000*1.6 - 69000
= 292380 - 118400 - 69000
= $ 104980
Answer to Part 2
Using High low method, variable cost per unit = (Highest activity cost - lowest activity cost)/(Highest activity unit - lowest activity units)
variable cost per unit = (104980 - 69880)/(74000-44000)
= 35100/30000
= $ 1.17
Y = 18400 + 1.17*x
where x - no. of activity units
Answer to Part 3
Y = 87400 + 2.77X
Where X- No. of activity units
Answer to Part 4
at 49000 machine hours Total overhead cost = 2.77*49000 + 87400
= 135730 + 87400
= $ 223130
Please check with your answer and let me know.
3: Assignment Seved Help Save & Exit Crosshill Company's total overhead costs at various levels of...
Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May Machine- Hours 49,000 39,000 59,000 69,000 Total Overhead Cost $210,730 $186,030 $ 235, 430 $260,130 June July Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 50, 700 70,000 65,330 Total overhead cost $ 186,030 The...
Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $204,360 $180,060 $228,660 $252,960 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 54,600 60,000 65,460 Total overhead cost $ 180,060 The company wants to...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost April 54,000 $188,180 May 44,000 $163,980 June 64,000 $212,380 July 74,000 $236,580 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows: Utilities (variable) $ 52,800 Supervisory salaries (fixed) 44,000 Maintenance (mixed) 67,180 Total overhead cost $ 163,980 The...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost April 54,000 $188,180 May 44,000 $163,980 June 64,000 $212,380 July 74,000 $236,580 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows: Utilities (variable) $ 52,800 Supervisory salaries (fixed) 44,000 Maintenance (mixed) 67,180 Total overhead cost $ 163,980 The...
Crosshill Company's total overhead costs at various levels of activity are presented below. chine Total Month April May 19.000 39.000 59.000 69.000 $191, 360 164.560 $236.200 July Assume that the overhead cost above consists of utilities, supervisory salaties, and maintenance The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows: DELL) Super Scries te $ nes $2.500 43.000 59.06 16. The company wants to break down the maintenance cost into ts variable and feed...
Crosshill Company's total overhead costs at various levels of activity are presented below. Month pril May Machine Hours 19,000 39,000 59,000 69.000 Total Overhead Cost $191,860 $164,460 $219, 260 $246,660 July Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity in May is as follows: Utilities variable) Supervisory salaries (fixed) Maintenance mixed) 62.400 43.000 59,060 nces Total overhead coat $164.960 The company wants to...
Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 45,000 35,000 55,000 65,000 Total Overhead Cost $175,050 $ 151,550 $198,550 $ 222,050 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000-machine-hour level of activity in May is as follows: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 42,000 55,000 54,550 Total overhead cost $ 151,550 The company wants...
Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 54,000 44,000 64,000 74,000 Total Overhead Cost $213,580 $189,380 $237,780 $261,980 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 57,200 68,000 64,180 Total overhead cost $ 189,380 The company wants to...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $223,100 $196,100 $250, 100 $277,100 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 63,000 65,000 68,100 $ 196,100 Nova Company's management wants to...
Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Hours 45,000 35,000 55,000 65,000 Month Cost S 185,650 $ 160,350 $ 210,950 $ 236,250 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000 machine-hour level of activity is: $ 45,500 54,000 60,850 $160,350 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost Nova Company's management...