Question













Crosshill Companys total overhead costs at various levels of activity are presented below. Month pril May Machine Hours 19,0
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1 Maintenance cost in July $93,260 Working notes: Total $62,400 per unit Utilities (variable) $1.60 $62,400/39,000 July total

Add a comment
Know the answer?
Add Answer to:
Crosshill Company's total overhead costs at various levels of activity are presented below. Month pril May...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Crosshill Company's total overhead costs at various levels of activity are presented below. chine Total Month...

    Crosshill Company's total overhead costs at various levels of activity are presented below. chine Total Month April May 19.000 39.000 59.000 69.000 $191, 360 164.560 $236.200 July Assume that the overhead cost above consists of utilities, supervisory salaties, and maintenance The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows: DELL) Super Scries te $ nes $2.500 43.000 59.06 16. The company wants to break down the maintenance cost into ts variable and feed...

  • Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May...

    Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May Machine- Hours 49,000 39,000 59,000 69,000 Total Overhead Cost $210,730 $186,030 $ 235, 430 $260,130 June July Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 50, 700 70,000 65,330 Total overhead cost $ 186,030 The...

  • Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May...

    Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $204,360 $180,060 $228,660 $252,960 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 54,600 60,000 65,460 Total overhead cost $ 180,060 The company wants to...

  • Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May...

    Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 54,000 44,000 64,000 74,000 Total Overhead Cost $213,580 $189,380 $237,780 $261,980 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 57,200 68,000 64,180 Total overhead cost $ 189,380 The company wants to...

  • Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May...

    Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 45,000 35,000 55,000 65,000 Total Overhead Cost $175,050 $ 151,550 $198,550 $ 222,050 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000-machine-hour level of activity in May is as follows: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 42,000 55,000 54,550 Total overhead cost $ 151,550 The company wants...

  • Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...

    Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 54,000    $188,180        May 44,000    $163,980        June 64,000    $212,380        July 74,000    $236,580   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 52,800     Supervisory salaries (fixed) 44,000   Maintenance (mixed) 67,180   Total overhead cost $ 163,980 The...

  • Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...

    Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 54,000    $188,180        May 44,000    $163,980        June 64,000    $212,380        July 74,000    $236,580   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 52,800     Supervisory salaries (fixed) 44,000   Maintenance (mixed) 67,180   Total overhead cost $ 163,980 The...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $223,100 $196,100 $250, 100 $277,100 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 63,000 65,000 68,100 $ 196,100 Nova Company's management wants to...

  • Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month...

    Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month April May June July Cost Hours 49,000190,590 39,000 $165,490 59,000215, 690 69,000 240,790 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 50,700 49,000 65,790 $165,490 Nova Company's management wants to break down the maintenance...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May Tune July Machine Hours 49,000 39,000 59,000 69,000 Total Overhead Cost $ 183,110 $ 158,210 $ 208,010 $ 232,910 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 54,600 45,000 58,610 $ 158,210 Nova Company's...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT