1
Answer is $102090
Supervisor salaries =$49000
Variable cost per Machine hr =$50700/39000=$1.30 per Mh
Utilities variable =69000*$1.30 per Mh=$89700
Maintenance Cost =240790-49000-89700=$102090
2
3
$240790=$67600+69000*2.51
4
67600+44000*2.51=$178040
Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month...
Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month April May June July Hours Cost 55,000 205,600 45,000179,600 65,000 75,000 ş 231,600 ş 257,600 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 45,000 machine-hour level of activity is Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $67,500 49,000 63,100 $179,600 Nova Company's management wants to break down the...
Nova Company's total overhead cost at various levels of activity are presented below. Month April MAY June July Machine- Hours 51.000 41.000 61,000 71,000 Total Overhead Cost $ 181,310 $ 158,210 $ 204, 410 $227,510 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 49,200 51,000 58,010 $158,210 Nova Company's management...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 46,000 36,000 56,000 66,000 Total Overhead Cost $ 186,020 $ 161,820 $ 210,220 $ 234, 420 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 43, 200 60,000 58,620 $ 161,...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 51,000 41,000 61,000 71,000 Total Overhead Cost $ 208, 040 $ 182,640 $ 233, 440 $ 258, 840 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 53,300 63,000 66,340 $182,640...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 45,000 35,000 55,000 65,000 Total Overhead Cost $ 192,900 $ 166,900 $ 218,900 $ 244,900 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 49,000 60,000 57,900 $ 166,900 Nova Company's...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 53,000 43,000 63,000 73,000 Total Overhead Cost $ 215, 940 $ 189, 140 $ 242,740 $ 269,540 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 43,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 64,500 55,000 69,640 $189, 140...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 50,000 40,000 60,000 70,000 Total Overhead Cost $ 187,300 $ 161,500 $ 213,100 $ 238,900 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 40,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 56,000 45,000 60,500 $161,500 Nova Company's management...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 54,000 44,000 64,000 74,000 Total Overhead Cost $ 196,260 $ 171,860 $ 220,660 $ 245,060 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 57,200 45,000 69,660 $171,860 Nova Company's management...
Nova Company's total overhead cost at various levels of activity are presented below: Month April May Tune July Machine Hours 49,000 39,000 59,000 69,000 Total Overhead Cost $ 183,110 $ 158,210 $ 208,010 $ 232,910 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 54,600 45,000 58,610 $ 158,210 Nova Company's...
Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Hours 45,000 35,000 55,000 65,000 Month Cost S 185,650 $ 160,350 $ 210,950 $ 236,250 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000 machine-hour level of activity is: $ 45,500 54,000 60,850 $160,350 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost Nova Company's management...