Question

Nova Companys total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hour
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer1

COMPUTATION OF MAINTENANCE OF JULY

Total Overhead Cost $238,900
less: Supervisory salaries $45,000
less: Utilities [($56,000/40,000) * 70,000] $98,000
Maintenance Cost in July $95,900

Answer2

Machine Hours Maintenance Cost
High Level 70,000 $95,900
Low Level 40,000 $60,500
Change 30,000 $35,400
Variable Cost Element 1.18 35,400/30,000
Fixed Cost Element 13,300 95,900-(70,000*1.18)

Y= 13,300 + 1.18X (fixed + variable* variable rate)

Answer3

Variable Cost per Machine hour Fixed cost
Utilities Cost and Supervisory Salaries Cost 1.40 $45,000
Maintenance Cost 1.18 $13,300
Total Overhead Cost 2.58 $58,300

Y= 58,300+2.58X

Answer4

Total overhead cost = $58,300+(45,000*2.58)

=$58,300+$116,100

=$174,400

hope you got the answer, please comment for any clarification

Thankyou and all the best for future

PLEASE UPVOTE...

Add a comment
Know the answer?
Add Answer to:
Nova Company's total overhead cost at various levels of activity are presented below: Month April May...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 45,000 35,000 55,000 65,000 Total Overhead Cost $ 192,900 $ 166,900 $ 218,900 $ 244,900 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 49,000 60,000 57,900 $ 166,900 Nova Company's...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 54,000 44,000 64,000 74,000 Total Overhead Cost $ 196,260 $ 171,860 $ 220,660 $ 245,060 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 57,200 45,000 69,660 $171,860 Nova Company's management...

  • Nova Company's total overhead cost at various levels of activity are presented below. Month April MAY...

    Nova Company's total overhead cost at various levels of activity are presented below. Month April MAY June July Machine- Hours 51.000 41.000 61,000 71,000 Total Overhead Cost $ 181,310 $ 158,210 $ 204, 410 $227,510 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 49,200 51,000 58,010 $158,210 Nova Company's management...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 46,000 36,000 56,000 66,000 Total Overhead Cost $ 186,020 $ 161,820 $ 210,220 $ 234, 420 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 43, 200 60,000 58,620 $ 161,...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 51,000 41,000 61,000 71,000 Total Overhead Cost $ 208, 040 $ 182,640 $ 233, 440 $ 258, 840 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 53,300 63,000 66,340 $182,640...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 53,000 43,000 63,000 73,000 Total Overhead Cost $ 215, 940 $ 189, 140 $ 242,740 $ 269,540 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 43,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 64,500 55,000 69,640 $189, 140...

  • Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month...

    Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month April May June July Hours Cost 55,000 205,600 45,000179,600 65,000 75,000 ş 231,600 ş 257,600 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 45,000 machine-hour level of activity is Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $67,500 49,000 63,100 $179,600 Nova Company's management wants to break down the...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May Tune July Machine Hours 49,000 39,000 59,000 69,000 Total Overhead Cost $ 183,110 $ 158,210 $ 208,010 $ 232,910 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 54,600 45,000 58,610 $ 158,210 Nova Company's...

  • Nova Company's total overhead cost at various levels of activity are presented below: Month April May...

    Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $223,100 $196,100 $250, 100 $277,100 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 63,000 65,000 68,100 $ 196,100 Nova Company's management wants to...

  • Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month...

    Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month April May June July Cost Hours 49,000190,590 39,000 $165,490 59,000215, 690 69,000 240,790 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 50,700 49,000 65,790 $165,490 Nova Company's management wants to break down the maintenance...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT