Assume Nortel Networks contracted to provide a customer with
Internet infrastructure for $2,450,000. The project began in 2021
and was completed in 2022. Data relating to the contract are
summarized below:
2021 | 2022 | |||||
Costs incurred during the year | $ | 336,000 | $ | 1,870,000 | ||
Estimated costs to complete as of 12/31 | 1,344,000 | 0 | ||||
Billings during the year | 446,000 | 1,710,000 | ||||
Cash collections during the year | 361,000 | 1,795,000 | ||||
Required:
1. Compute the amount of revenue and gross profit or loss to be
recognized in 2021 and 2022 assuming Nortel recognizes revenue over
time according to percentage of completion.
2. Compute the amount of revenue and gross profit or loss to be
recognized in 2021 and 2022 assuming this project does not qualify
for revenue recognition over time.
3. Prepare a partial balance sheet to show how the information
related to this contract would be presented at the end of 2021
assuming Nortel recognizes revenue over time according to
percentage of completion.
4. Prepare a partial balance sheet to show how the information
related to this contract would be presented at the end of 2021
assuming this project does not qualify for revenue recognition over
time.
Answers:
1). The revenue and gross profit or loss to be recognized by Nortel under percentage of completion
Revenue to be recognized in 2021
Determine the percentage of work completed and multiply with the contract price
Percentage of work completed= Cost of work incurred to date/ Estimated total costs of work
Percentage of work completed=$336,000/$1,344,000
Revenue recognized= $336,000/$1,344,000 x $2,450,000=$612,500
Profit/loss= Revenue recognized - costs incurred in the period
Profit/loss=$612,500-$336,000=$276,500, profit
Revenue to be recognized in 2022
Revenue recognized=$2,450,000-$612,500=$1,837,500
Profit/loss= Revenue recognized - costs incurred in the period
Profit/loss=$1,837,500-$1,870,000=-$32,500, loss
2). The revenue and gross profit or loss to be recognized by Nortel where the project does not qualify for revenue recognition over time.
Under this method all of the revenue and profit associated with this project will be recognized only after the project is completed in 2022.This method is called completed contract method.
Revenue and profit or loss to be recognized in 2021= 0
Revenue to be recognized in 2022 (Contract price)= $2,450,000
Costs to the completion of the project=$336,000 + $1,870,000= $2,206,000
Contract price (Revenue) -------------------------$2,450,000
Total contract costs ($336,000 + $1,870,000) ($2,206,000)
Profit--------------------------------------------------$244,000
3). A partial balance sheet for Nortel end of 2021-Percentage of completion
Current Assets
Cash---------------------------$361,000
Construction in progress---$336,000
Accounts Receivable-------$85,000
Liabilities
Accounts Payable------------$336,000
.
4). Partial balance sheet as at end of 2021-Completed contact
Current Assets
Cash---------------------------$361,000
Construction in progress---$336,000
Accounts Receivable-------$85,000
Liabilities
Accounts Payable------------$336,000
.
Journal entries
Recording of costs incurred
Debit, Construction in progress---$336,000
Credit, Accounts Payable-------------------------$336,000
Recording of billings
Debit, Accounts Receivable-------$446,000
Credit, Billings---------------------------------------$446,000
Recording cash collections
Debit, Cash--------------------------$361,000
Credit, Accounts Receivable---------------------$361,000 (reduces accounts receivable balance)
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,720,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405.000 300,000 1.670.000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2.250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,720,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405,000 300,000 1,670,000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,910,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 376,000 $ 2,265,000 Estimated costs to complete as of 12/31 1,504,000 0 Billings during the year 535,000 1,810,000 Cash collections during the year 500,000 1,845,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 356,000 $ 2,135,000 Estimated costs to complete as of 12/31 1,424,000 0 Billings during the year 475,000 1,760,000 Cash collections during the year 415,000 1,820,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,300,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 324,000 $ 1,800,000 Estimated costs to complete as of 12/31 1,296,000 0 Billings during the year 410,000 1,680,000 Cash collections during the year 310,000 1,780,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,650,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 352,000 $ 2,025,000 Estimated costs to complete as of 12/31 1,408,000 0 Billings during the year 470,000 1,750,000 Cash collections during the year 405,000 1,815,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,650,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 352,000 1,408,000 470,000 405,000 2022 $2,025,000 0 1,750,000 1,815,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,960,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $2,300,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 380,000 1,520,000 540,000 510,000 1, 820,000 1,850,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405,000 300,000 2022 $1,720,000 0 1,670,000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,350,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,830,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 328,000 1,312,000 436,000 341,000 1,690,000 1,785,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...