Assume Nortel Networks contracted to provide a customer with
Internet infrastructure for $2,650,000. The project began in 2021
and was completed in 2022. Data relating to the contract are
summarized below:
2021 | 2022 | |||||
Costs incurred during the year | $ | 352,000 | $ | 2,025,000 | ||
Estimated costs to complete as of 12/31 | 1,408,000 | 0 | ||||
Billings during the year | 470,000 | 1,750,000 | ||||
Cash collections during the year | 405,000 | 1,815,000 | ||||
Required:
1. Compute the amount of revenue and gross profit or loss to be
recognized in 2021 and 2022 assuming Nortel recognizes revenue over
time according to the percentage of completion.
2. Compute the amount of revenue and gross profit or loss to be
recognized in 2021 and 2022 assuming this project does not qualify
for revenue recognition over time.
3. Prepare a partial balance sheet to show how the information
related to this contract would be presented at the end of 2021
assuming Nortel recognizes revenue over time according to
percentage of completion.
4. Prepare a partial balance sheet to show how the information
related to this contract would be presented at the end of 2021
assuming this project does not qualify for revenue recognition over
time.
1.
2.
Revenue | Gross Profit (Loss) | |
2021 | 0 | 0 |
2022 | 2650000 | 273000 |
Since the project does not qualify for revenue recognition over time, the entire revenue of $2650000 and gross profit $2650000 - $2377000 = $273000 will be recognized on completion of the project in 2022.
3.
Nortel Networks | |
Balance Sheet (Partial) | |
At December 31, 2021 | |
Current assets: | |
Accounts receivable | 65000 |
Costs and profits in excess of billings | 60000 |
Current liabilities: | |
Working:
Accounts receivable = $470000 - $405000 = $65000
Costs and profits in excess of billings = $352000 + $178000 - $470000 = $60000
4.
Nortel Networks | |
Balance Sheet (Partial) | |
At December 31, 2021 | |
Current assets: | |
Accounts receivable | 65000 |
Current liabilities: | |
Billings in excess of costs | 118000 |
Working:
Accounts receivable = $470000 - $405000 = $65000
Billings in excess of costs = $470000 - $352000 = $118000
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,650,000. The project began...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,650,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 352,000 1,408,000 470,000 405,000 2022 $2,025,000 0 1,750,000 1,815,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,720,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405.000 300,000 1.670.000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2.250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,720,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405,000 300,000 1,670,000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,910,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 376,000 $ 2,265,000 Estimated costs to complete as of 12/31 1,504,000 0 Billings during the year 535,000 1,810,000 Cash collections during the year 500,000 1,845,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 356,000 $ 2,135,000 Estimated costs to complete as of 12/31 1,424,000 0 Billings during the year 475,000 1,760,000 Cash collections during the year 415,000 1,820,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,300,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 324,000 $ 1,800,000 Estimated costs to complete as of 12/31 1,296,000 0 Billings during the year 410,000 1,680,000 Cash collections during the year 310,000 1,780,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,450,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 336,000 $ 1,870,000 Estimated costs to complete as of 12/31 1,344,000 0 Billings during the year 446,000 1,710,000 Cash collections during the year 361,000 1,795,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,960,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $2,300,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 380,000 1,520,000 540,000 510,000 1, 820,000 1,850,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,250,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 320,000 1,280,000 405,000 300,000 2022 $1,720,000 0 1,670,000 1,775,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021...
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,350,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 $1,830,000 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 328,000 1,312,000 436,000 341,000 1,690,000 1,785,000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and...