Answer: $445,500
Explanation:
i. (Actual quantity x Standard price) - (Standard quantity x Standard price) = $6,750
(Actual quantity x Standard price) - Standard material cost = $6,750
(Actual quantity x Standard price) = $6,750 + Standard material cost
(Actual quantity x Standard price) = $6,750 + $450,000
(Actual quantity x Standard price) = $456,750
.
ii. (Actual quantity x Actual price) - (Actual quantity x Standard price) = -$11,250
Actual Total direct material cost - (Actual quantity x Standard price) = -$11,250
Actual Total direct material cost - $456,750 = -$11,250
Actual Total direct material cost = -$11,250 + $456,750
Actual Total direct material cost = $445,500
provide an answer and explanation 5 Sanchez Company's output for the current period was assigned a...
Sanchez Company's output for the current period was assigned a $415,000 standard direct labor cost. The direct labor variances included a $10,375 unfavorable direct labor rate variance and a $4,150 favorable direct labor efficiency variance. What is the actual total direct labor cost for the current period? Multiple Choice $425,375. $429,525. $421,225. $408,775 $400,475
QS 8-10 Materials cost variances LO P2 Juan Company's output for the current period was assigned a $160,000 standard direct materials cost. The direct materlals variances included a $14,000 favorable price variance and a $2700 favorable quantity variance. What is the actual total direct materials cost for the current period? Actual total direct materials cost
Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The company actually used 4,600 pounds that cost $6.10 per pound to produce 2,000 units. What is the direct materials quantity variance? Multiple Choice 0 $3,050 unfavorable. 0 $460 unfavorable. 0 $3,460 unfavorable. 0 $3,000 unfavorable. 0 $410 unfavorable. Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The company actually used 4,600 pounds that cost $6.10 per pound...
QS 23-12 Labor cost variances LO P2 Frontera Company's output for the current period results in a $29,000 unfavorable direct labor rate variance and a $14,000 unfavorable direct labor efficiency variance. Production for the current period was assigned a $370,000 standard direct labor cost What is the actual total direct labor cost for the current period? Actual total direct labor cost
QS 8-12 Labor cost variances LO P2 Frontera Company's output for the current period results in a $27,000 unfavorable direct labor rate variance and a $12,000 unfavorable direct labor efficiency variance Production for the current period was assigned a $440,000 standard direct labor cost. What is the actual total direct labor cost for the current period? Actual total direct labor cost
3073 1 Frontera Company's output for the current period results in a $23,000 unfavorable direct labor rate variance and a $11,000 unfavorable direct labor efficiency variance. Production for the current period was assigned a $410,000 standard direct labor cost. What is the actual total direct labor cost for the current period? Actual total direct labor cost 11 of 24 < Prey Next >
PLease answer all queations ASAP! wil rate 1. Georgia, Inc. has collected the following data on one of its products. The actual cost of the direct materials used is: Direct materials standard (3 lbs @ $2/lb) $6 per finished unit Total direct materials cost variance—unfavorable $14,250 Actual direct materials used 100,000 lbs. Actual finished units produced 25,000 units Multiple Choice $135,750. $164,250. $150,000. $182,000. $100,000. 2. Use the following data to find the total direct labor cost variance if the...
Cavern Company's output for the current period results in a $5,250 unfavorable direct material price variance. The actual price per pound is $56 50 and the standard price per pound is $55.00 How many pounds of material are used in the current period? 5,393 5,110 3,500 3,750 4,000. Levelor Company's flexible budget shows $10,710 of overhead at 75% of capacity, which was the operating level achieved during May However, the company applied overhead to production during May at a rate...
QS 8-9 Materials cost variances LO P2 For the current period, Kayenta Company's manufacturing operations yield a $4,000 unfavorable price variance on its direct materials usage. The actual price per pound of material is $86, the standard price is $85.50 per pound. How many pounds of material were used in the current period? Actual pounds used pounds
Hart Company made 3,220 bookshelves using 22,220 board feet of wood costing $293,304. The company's direct materials standards for one bookshelf are 8 board feet of wood at $13.10 per board foot. AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP = Standard Price (1) Compute the direct materials price and quantity variances and classify each as favorable or unfavorable . (2) Hart applies management by exception by investigating direct materials variances of more than 5%...