Question 8
Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system to calculate its cost of goods manufactured. The company’s policy is to price its job at cost plus 30% markup. On January 1, 2020, there was only one job in process, with the following costs:
Overhead rate = $27000 / $18000 = 150% of Direct Labor cost
Total Overhead applied = ($132400+45900+26000) x 150% = $306450
Job No. 200 | |
Cost of Completed Job | |
Direct Material | $ 164,100 |
Direct Labor | $ 150,400 |
Overhead applied | $ 225,600 |
Total Cost | $ 540,100 |
Job No. 300 | |
Cost of Completed Job | |
Direct Material | $ 45,900 |
Direct Labor | $ 45,900 |
Overhead applied | $ 68,850 |
Total Cost | $ 160,650 |
Job No. 400 | |
Cost of Work in process | |
Direct Material | $ 35,500 |
Direct Labor | $ 26,000 |
Overhead applied | $ 39,000 |
Total Cost | $ 100,500 |
Overhead incurred | $ 274,540 |
Manufacturing Overhead applied | $ 306,450 |
Overapplied Overhead | $ (31,910) |
Schedule of Cost of Goods Sold | |
Finished Goods Inventory, Beginning | $ 85,400 |
Cost of Goods Manufactured | $ 700,750 |
Cost of Goods Available for sale | $ 786,150 |
Less : Finished Goods Inventory, Ending | $ 160,650 |
Unadjusted Cost of goods sold | $ 625,500 |
Less : Overapplied Overhead | $ (31,910) |
Adjusted Cost of goods sold | $ 593,590 |
Selling Price of Job 200 = $540100 x 130% = $702,130
Ending Balances
Direct Material = $45900+377000-(150400+45900+35500) =
$191100
Work in process = $100500
If you have any query, kindly comment with your query and please mark thumbs up.
Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system...
Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system to calculate its cost of goods manufactured. The company's policy is to price its job at cost plus 30% markup. On January 1, 2020, there was only one job in process, with the following costs: Job 200 $13,600 Direct materials Direct labour Applied overhead Total 18,000 27,000 $58,600 The following balances were taken from the company's general ledger as of January 1, 2020: Direct...
Need correct answers with workings to this question asap! I've given all the information below with a drop-down list, and please follow whatever is given, this all the information I have! Question 8) Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system to calculate its cost of goods manufactured. The company's policy is to price its job at cost plus 30% markup. On January 1, 2020, there was only one job in process,...
Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,000, and manufacturing overhead $20,000. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...
Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,200, and manufacturing overhead $20,200. As of January 1, Job No. 49 had been completed at a cost of $120,200 and was part of finished goods inventory. There...
Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were worked on during November and December. Job 105 was completed on December 10; the other two jobs were still in production on December 31, the end of the company’s operating year. Data from the job cost sheets of the three jobs follow: Job Cost Sheet Job 105 Job 106 Job 107 November costs incurred: Direct materials $ 20,500 $ 13,300 $ 0...
Lott company uses a Problem 2-1A (Video) Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $22,000, direct labor $13,200, and manufacturing overhead $17,600. As of January 1, Job 49 had been completed at a cost of $99,000 and was part of...
Ravsten Company uses a job-order costing system. On January 1, the beginning of the current year, the company's inventory balances were as follows: Raw materials Work in process Finished goods $16,500 $10,200 $30, 100 The company applies overhead cost to jobs on the basis of machine-hours. For the current year, the company estimated that it would work 36.100 machine-hours and incur $155.230 in manufacturing overhead cost. The following transactions were recorded for the year: a. Raw materials were purchased on...
Question 9 For the year ended December 31, 2020, the job cost sheets of DeVoe Company contained the following data: Help System Announcements Question 9 For the year ended December 31, 2020, the job cost sheets of Devoe Company contained the following data: Job Direct Direct Manufacturing Total Number Explanation Materials Labour Overhead Costs 7610 Balance 1/1 $25,400 $24,500 $29,100 $79,000 Current year's costs 30,200 35,100 43,400 108,700 7641 Balance 1/1 11,200 18.900 21,600 51,700 Current year's costs 43,300 48,400...
Exercise 5.34 Whispering Company uses a job costing system. Overhead is allocated based on 120% of direct labour cost. Last month's transactions in the work-in-process account are shown here: Work in Process $51,900 171,300 To finished goods 108,000 145,600 Beginning balance Direct materials Direct labour Factory overhead $408,900 Only one job, +850, was still in process at the end of the month. Job 850 was charged with $8,700 in overhead for the month. What is the ending balance in the...
Skysong Company uses a job costing system. Overhead is allocated based on 120% of direct labour cost. Last month's transactions in the work-in-process account are shown here: Work in Process $46,100 162,500 To finished goods 113,300 151,700 Beginning balance Direct materials Direct labour Factory overhead $446,400 Only one job, #850, was still in process at the end of the month. Job 850 was charged with $9,600 in overhead for the month. What is the ending balance in the WIP account?...