Question

Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system to calculate its cost of goPrepare simple job cost sheets for jobs 200, 300, and 400 for the year ended December 31, 2020. Job No. 200 $ Job No. 300 JobDetermine whether the overhead is over-applied or under-applied. By how much? Manufacturing overhead applied: Overhead incurrCalculate the selling price of Job 200. Selling price of Job 200 $ LINK TO TEXT Calculate the ending balances as of December

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Job 200 Job 300 Job 400 Total
Beginning WIP
direct materials 13,600 13,600
direct labor 18,000 18,000
overhead applied 27,000 27,000
total beginning wip 58,600 58,600
cost added
direct materials 150,900 45,400 35,100 231,400
direct labor 132,100 45,400 25,700 203,200
overhead applied 198150 68100 38550 304800
total cost added 481,150 158,900 99,350 739,400
total cost of job 539,750 158,900 99,350 798,000
1) overhead rate = 150% (27000/18000)
total overhead applied = 304800 answer
2) Job No.200
cost of completed job
Direct materials 164,500
Direct labor 150,100
Manufacturing overhead 225,150
Total cost 539,750
Job 300
cost of completed job
Direct materials 45,400
Direct labor 45,400
Manufacturing overhead 68100
Total cost 158,900
Job 400
cost of completed job
Direct materials 35,100
Direct labor 25,700
Manufacturing overhead 38550
Total cost 99,350
3) Manufacturing overhead applied:
overhead incurred during the month 275690
Manufacturing overhead applied: 304800
overapplied overhead 29110
4) Statement of cost of goods sold
Beginning finished goods 85,000
Cost of goods manufactured 698,650
cost of goods available for sale 783,650
less finished goods ,Ending 158,900
unadjusted cost of goods sold 624,750
less overapplied overhead 29110
adjusted cost of goods sold 595,640
5) Selling price of job 200 701675
6) Direct materials 191,000
Work in process 99,350
Add a comment
Know the answer?
Add Answer to:
Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system...

    Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system to calculate its cost of goods manufactured. The company’s policy is to price its job at cost plus 30% markup. On January 1, 2020, there was only one job in process, with the following costs: Questions Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system to calculate its cost of goods manufactured. The company's policy is to price its...

  • Need correct answers with workings to this question asap! I've given all the information below with...

    Need correct answers with workings to this question asap! I've given all the information below with a drop-down list, and please follow whatever is given, this all the information I have! Question 8) Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system to calculate its cost of goods manufactured. The company's policy is to price its job at cost plus 30% markup. On January 1, 2020, there was only one job in process,...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,000, and manufacturing overhead $20,000. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...

  • Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the...

    Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,200, and manufacturing overhead $20,200. As of January 1, Job No. 49 had been completed at a cost of $120,200 and was part of finished goods inventory. There...

  • Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were...

    Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were worked on during November and December. Job 105 was completed on December 10; the other two jobs were still in production on December 31, the end of the company’s operating year. Data from the job cost sheets of the three jobs follow:    Job Cost Sheet    Job 105 Job 106 Job 107   November costs incurred:      Direct materials $ 20,500 $ 13,300 $ 0...

  • Ravsten Company uses a job-order costing system. On January 1, the beginning of the current year, the company's...

    Ravsten Company uses a job-order costing system. On January 1, the beginning of the current year, the company's inventory balances were as follows: Raw materials Work in process Finished goods $16,500 $10,200 $30, 100 The company applies overhead cost to jobs on the basis of machine-hours. For the current year, the company estimated that it would work 36.100 machine-hours and incur $155.230 in manufacturing overhead cost. The following transactions were recorded for the year: a. Raw materials were purchased on...

  • Question 9 For the year ended December 31, 2020, the job cost sheets of DeVoe Company...

    Question 9 For the year ended December 31, 2020, the job cost sheets of DeVoe Company contained the following data: Help System Announcements Question 9 For the year ended December 31, 2020, the job cost sheets of Devoe Company contained the following data: Job Direct Direct Manufacturing Total Number Explanation Materials Labour Overhead Costs 7610 Balance 1/1 $25,400 $24,500 $29,100 $79,000 Current year's costs 30,200 35,100 43,400 108,700 7641 Balance 1/1 11,200 18.900 21,600 51,700 Current year's costs 43,300 48,400...

  • Lott company uses a Problem 2-1A (Video) Lott Company uses a job order cost system and...

    Lott company uses a Problem 2-1A (Video) Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $22,000, direct labor $13,200, and manufacturing overhead $17,600. As of January 1, Job 49 had been completed at a cost of $99,000 and was part of...

  • Question 9 For the year ended December 31, 2020, the job cost sheets of DeVoe Company...

    Question 9 For the year ended December 31, 2020, the job cost sheets of DeVoe Company contained the following data: Direct Materials Direct Labour Total Costs Job Number Explanation 7640 Balance 1/1 Current year's costs Balance 1/1 $25,100 30,500 11,800 43,600 48,300 7641 Manufacturing Overhead $28,900 43,900 22,100 57,900 66,800 $24,900 35,400 18,800 48,300 55,000 $78,900 109,800 52,700 149,800 170,100 Current year's costs Current year's costs 7642 Other data: 1. Raw materials inventory totalled $15,100 on January 1. During the...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,800, direct labor $13,080, and manufacturing overhead $17,440. As of January 1, Job 49 had been completed at a cost of $98,100 and was part of finished goods inventory. There was a $16,350...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT