Job 200 | Job 300 | Job 400 | Total | |||
Beginning WIP | ||||||
direct materials | 13,600 | 13,600 | ||||
direct labor | 18,000 | 18,000 | ||||
overhead applied | 27,000 | 27,000 | ||||
total beginning wip | 58,600 | 58,600 | ||||
cost added | ||||||
direct materials | 150,900 | 45,400 | 35,100 | 231,400 | ||
direct labor | 132,100 | 45,400 | 25,700 | 203,200 | ||
overhead applied | 198150 | 68100 | 38550 | 304800 | ||
total cost added | 481,150 | 158,900 | 99,350 | 739,400 | ||
total cost of job | 539,750 | 158,900 | 99,350 | 798,000 | ||
1) | overhead rate = | 150% | (27000/18000) | |||
total overhead applied = | 304800 | answer | ||||
2) | Job No.200 | |||||
cost of completed job | ||||||
Direct materials | 164,500 | |||||
Direct labor | 150,100 | |||||
Manufacturing overhead | 225,150 | |||||
Total cost | 539,750 | |||||
Job 300 | ||||||
cost of completed job | ||||||
Direct materials | 45,400 | |||||
Direct labor | 45,400 | |||||
Manufacturing overhead | 68100 | |||||
Total cost | 158,900 | |||||
Job 400 | ||||||
cost of completed job | ||||||
Direct materials | 35,100 | |||||
Direct labor | 25,700 | |||||
Manufacturing overhead | 38550 | |||||
Total cost | 99,350 | |||||
3) | Manufacturing overhead applied: | |||||
overhead incurred during the month | 275690 | |||||
Manufacturing overhead applied: | 304800 | |||||
overapplied | overhead | 29110 | ||||
4) | Statement of cost of goods sold | |||||
Beginning finished goods | 85,000 | |||||
Cost of goods manufactured | 698,650 | |||||
cost of goods available for sale | 783,650 | |||||
less finished goods ,Ending | 158,900 | |||||
unadjusted cost of goods sold | 624,750 | |||||
less overapplied overhead | 29110 | |||||
adjusted cost of goods sold | 595,640 | |||||
5) | Selling price of job 200 | 701675 | ||||
6) | Direct materials | 191,000 | ||||
Work in process | 99,350 | |||||
Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system...
Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system to calculate its cost of goods manufactured. The company’s policy is to price its job at cost plus 30% markup. On January 1, 2020, there was only one job in process, with the following costs: Questions Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system to calculate its cost of goods manufactured. The company's policy is to price its...
Need correct answers with workings to this question asap! I've given all the information below with a drop-down list, and please follow whatever is given, this all the information I have! Question 8) Question 8 Red Fire Inc. produces fire trucks. The company uses a normal job-order costing system to calculate its cost of goods manufactured. The company's policy is to price its job at cost plus 30% markup. On January 1, 2020, there was only one job in process,...
Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,000, and manufacturing overhead $20,000. As of January 1, Job No. 49 had been completed at a cost of $120,000 and was part of finished goods inventory. There...
Question 5 Bertrand Manufacturing uses a job-order cost system and applies overhead to production on the basis of direct labour costs. On January 1, 2020, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $30,000, direct labour $15,200, and manufacturing overhead $20,200. As of January 1, Job No. 49 had been completed at a cost of $120,200 and was part of finished goods inventory. There...
Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were worked on during November and December. Job 105 was completed on December 10; the other two jobs were still in production on December 31, the end of the company’s operating year. Data from the job cost sheets of the three jobs follow: Job Cost Sheet Job 105 Job 106 Job 107 November costs incurred: Direct materials $ 20,500 $ 13,300 $ 0...
Ravsten Company uses a job-order costing system. On January 1, the beginning of the current year, the company's inventory balances were as follows: Raw materials Work in process Finished goods $16,500 $10,200 $30, 100 The company applies overhead cost to jobs on the basis of machine-hours. For the current year, the company estimated that it would work 36.100 machine-hours and incur $155.230 in manufacturing overhead cost. The following transactions were recorded for the year: a. Raw materials were purchased on...
Question 9 For the year ended December 31, 2020, the job cost sheets of DeVoe Company contained the following data: Help System Announcements Question 9 For the year ended December 31, 2020, the job cost sheets of Devoe Company contained the following data: Job Direct Direct Manufacturing Total Number Explanation Materials Labour Overhead Costs 7610 Balance 1/1 $25,400 $24,500 $29,100 $79,000 Current year's costs 30,200 35,100 43,400 108,700 7641 Balance 1/1 11,200 18.900 21,600 51,700 Current year's costs 43,300 48,400...
Lott company uses a Problem 2-1A (Video) Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $22,000, direct labor $13,200, and manufacturing overhead $17,600. As of January 1, Job 49 had been completed at a cost of $99,000 and was part of...
Question 9 For the year ended December 31, 2020, the job cost sheets of DeVoe Company contained the following data: Direct Materials Direct Labour Total Costs Job Number Explanation 7640 Balance 1/1 Current year's costs Balance 1/1 $25,100 30,500 11,800 43,600 48,300 7641 Manufacturing Overhead $28,900 43,900 22,100 57,900 66,800 $24,900 35,400 18,800 48,300 55,000 $78,900 109,800 52,700 149,800 170,100 Current year's costs Current year's costs 7642 Other data: 1. Raw materials inventory totalled $15,100 on January 1. During the...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,800, direct labor $13,080, and manufacturing overhead $17,440. As of January 1, Job 49 had been completed at a cost of $98,100 and was part of finished goods inventory. There was a $16,350...