Management Instructions | ||||||||
Beginning Inventory | 68 | |||||||
Safety Stock | 300 | |||||||
Lot Size | 144 | |||||||
Master Production Schedule | ||||||||
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Demand | 505 | 580 | 575 | 550 | 520 | 480 | 475 | 525 |
Customer Orders | 710 | 660 | 570 | 330 | 100 | 515 | 80 | 40 |
Projected On-Hand Inventory (POHI) (at the end of the period) |
||||||||
Master Production Schedule | ||||||||
Available To Promise (1-period look ahead) Discrete |
||||||||
Available To Promise (1-period look ahead) Cumulative |
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Demand | 505 | 580 | 575 | 550 | 520 | 480 | 475 | 525 |
Customer Orders | 710 | 660 | 570 | 340 | 100 | 515 | 80 | 40 |
Beginning Inventory | 68 | 366 | 426 | 427 | 309 | 365 | 426 | 383 |
Projected on hand inventory(POHI) | 366 | 426 | 427 | 309 | 365 | 426 | 383 | 434 |
Master production schedule | 1008 | 720 | 576 | 432 | 576 | 576 | 432 | 576 |
Available to promise | 366 | 60 | 6 | 92 | 476 | 61 | 352 | 536 |
Available to promise ( Cumulative ) | 366 | 426 | 432 | 524 | 1000 | 1061 | 1413 | 1949 |
Master production schedule is the number of units to be produced inorder to keep the ending inventory above the safety stock level.
Please provide feedback if it was helpful. Feel free to comment if you have any doubts
Management Instructions Beginning Inventory 68 Safety Stock 300 Lot Size 144 Master Production Schedule Period 1...
Can somone show me how to do the 1st problem? Need to find the LS and SS for the fit and the LH and SH for the hole. Fits are all SHAFT BASIS METRIC but the shaft and hole diameters can not be used right out of the table. This is because the 3mm shaft tolerance does not match. You will need to lookup the "Fit" from the table, and then use the LS (Largest Shaft) and SS (Smallest Shaft)...