Question

Reed Incorporated uses a job-order costing system and a predetermined overhead rate based on machine hours....

Reed Incorporated uses a job-order costing system and a predetermined overhead rate based on machine hours.

At the beginning of the year, the company estimated that the manufacturing overhead for the year would be $240,000 and machine hours would be 8,000.

The following information pertains to December of the current year:

Job 10 Job 11 Job 12 Total
Work in process, Dec. 1 $16,000 $26,000 $38,000 $80,000
December production activity:
Materials requisitioned $4,000 $4,800 $7,200 $16,000
Direct labor cost 2,400 3,600 4,000 10,000
Machine hours 400 hrs. 700 hrs. 900 hrs. 2,000 hrs.
Labor hours 120 hrs. 180 hrs. 200 hrs. 500 hrs.

Actual manufacturing overhead cost incurred in December was $61,000.

Required:

A. Compute the predetermined overhead application rate.
$

B. Determine the total cost associated with each job.

Job 10 $
Job 11 $
Job 12 $

C. If Jobs 10 and 12 were completed, prepare the journal entry to transfer the cost.

D. If Job 10 was delivered to customers that paid $50,000 in cash, prepare the journal entries.

E. What is the gross margin for Job 10?
$

F. What is the cost assigned to ending work in process?
$

G. Assuming no beginning finished goods balance, what is the cost assigned to ending finished goods?
$

H. How much was overhead over/underapplied?
$  

0 0
Add a comment Improve this question Transcribed image text
Answer #1

A Predetermined overhead rate based on machine hour Total manufacturing overheads $240,000 Machine hours 8,000 $30 per MH B J

Add a comment
Know the answer?
Add Answer to:
Reed Incorporated uses a job-order costing system and a predetermined overhead rate based on machine hours....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Job Costing #3 Burlington Corporation uses a job-order costing system and a predetermined overhead rate based...

    Job Costing #3 Burlington Corporation uses a job-order costing system and a predetermined overhead rate based on machine hours. At the beginning of the year, the company estimated manufacturing overhead for the year would be $3,200,000 and 4,000 machine hours would be used. Labor was estimated at $200/hour. The following information pertains to December of the current year: Job No. Job No. Job No. Job No. 206 207 208 209 Work in process, December 1 $28,000 $30,000 $22,000 $10,000 December...

  • Moody Corporation uses a job-order costing system with a plant wide overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plant wide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production…………100,000 Fixed manufacturing overhead cost……………………………….$650,000 Variable manufacturing overhead cost per machine-hour…………$3.0 Required: 1. Compute the predetermined overhead rate During the year, Job 400 was started and completed. The following information was available with respect to the job: Direct materials requisitioned…………………..$450 Direct labor cost………………………………...$210 Machine-hours used……………………………….40 2. Compute...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour $ 156,000 658,000 4.30 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Predetermined overhead rate Predetermined overhead per MH 2. During the year Job 500 was...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 152,000 S 655,000 $ 4.70 Required: 1. Compute the predetermined overhead rate. (Round your answer to 2 decimal places.) Predetermined overhead rate per MH 2. During the year Job 500 was started and completed. The following information...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour S $ 154,000 654,000 4.90 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Predetermined overhead rate per MH 2. During the year Job 500 was started...

  • 48. Lauren Company uses a job-order costing system and a predetermined overhead rate based on machine...

    48. Lauren Company uses a job-order costing system and a predetermined overhead rate based on machine hours. At the beginning of 2020, Lauren estimated the overhead for the year would be $720,000 and that production would use 90,000 machine hours. The following information relates to the month of August: Job 125 Job 126 Job 127 $10,000 $14,000 $0 $15.000 $20,000 $2.000 Work in process August 1 Direct materials cost Direct labor costs Actual direct labor hours Actual machine hours $24,000...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 154,000 $ 655,000 $ 5.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 157,000 Fixed manufacturing overhead cost $ 652,000 Variable manufacturing overhead cost per machine-hour $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 156,000 Fixed manufacturing overhead cost $ 652,000 Variable manufacturing overhead cost per machine-hour $ 4.80 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 153,000 s 654,088 $ 4.20 Required 1. Compute the plantwide predetermined overhead rate 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT