Question

Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 153,000 s 654,088 $ 4.20 Required 1. Compute the plantwide predetermined overhead rate 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct labor cost Machine-hours used 340 240 34 Compute the total manufacturing cost assigned to Job 400 3. If Job 400 includes 50 units, what is the unit product cost for this job? 41f Moody uses a markup percentage of 130% of its total manufacturing cost, then what selling price per unit would it have established for Job 400?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1) Predetermined overhead rate
Formula:
Estimated manufacturing overhead/estimated machine hours
Variable manufacturing overhead cost per machine hour 4.20
Fixed manufacturing overhead cost per mh (654000/153000) 4.27
predetermined overhead rate 8.47 per MH
2) Total manufacturing cost
$
Direct materials requistioned 340
Direct labor cost 240
Overhead applied (8.47*34) 288
Total manufacturing cost 868
3) unit product cost of the job
868/50
17
4) Selling price 17*130%
22
answer to question 2 , 3 and 4 have been changed to whole numbers
Add a comment
Know the answer?
Add Answer to:
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 153,000 Fixed manufacturing overhead cost $ 659,000 Variable manufacturing overhead cost per machine-hour $ 4.90 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 153,000 Fixed manufacturing overhead cost $ 652,000 Variable manufacturing overhead cost per machine-hour $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 154,000 Fixed manufacturing overhead cost $ 652,000 Variable manufacturing overhead cost per machine-hour $ 4.20 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 150,000 $ 652,000 $ 4.20 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: ots Machine-hours required to support estimated production 152, eee Fixed manufacturing overhead cost $659,800 Variable manufacturing overhead cost per machine-hour $ 4.30 - eBook Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job!...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 153,000 $ 658,000 4.30 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: $ 380 $ 220...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 157,000 Fixed manufacturing overhead cost $ 658,000 Variable manufacturing overhead cost per machine-hour $ 4.60 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 153,000 $ 654,000 $ 4.20 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 158,000 Fixed manufacturing overhead cost $ 651,000 Variable manufacturing overhead cost per machine-hour $ 4.30 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...

  • Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....

    Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 151,000 $ 650,000 $ 4.10 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT