Direct materials used in production = $330,000
Direct labor = $415,000
Manufacturing overhead = $220,000
Total manufacturing cost = Direct materials used in production+ Direct labor+ Manufacturing overhead
= 330,000+415,000+220,000
= $965,000
The total manufacturing cost incurred for the month = $965,000
Correct option is B.
Kindly give a positive rating if you are satisfied with this solution and please ask if you have any query.
Thanks
Direct materials used in production totaled $330,000. Direct labor was $415,000 and manufacturing overhead was $220,000....
Cost of direct materials used in production Direct labor Work in process inventory, October 1 Work in process inventory, October 31 Total factory overhead $1,323,600 1,680,000 455,300 378,100 3,544,200 Determine Fuller Manufacturing's cost of goods manufactured for the month ended October 31. Fuller Manufacturing Company Statement of Cost of Goods Manufactured For the Month Ended October 31 Work in process inventory, October 1 Manufacturing costs incurred during October: Cost of direct materials used in production Direct labor Factory overhead Total...
Average Cost per Unit Direct Materials $12 Direct Labor Indirect Materials Fixed manufacturing overhead Variable manufacturing overhead Fixed selling and administrative expenses Variable sales commissions E. IF 19,000 units are produced, what are the total manufacturing overhead costs incurred? Total manufacturing overhead costs $ F. If 24,000 units are produced, what are the total manufacturing overhead costs incurred? Total manufacturing overhead costs $ G. If 19,000 units are produced, what are the per unit manufacturing overhead costs incurred? If required,...
The following costs were incurred in April: Direct materials Direct labor Manufacturing overhead Selling expenses Administrative expenses $57.000 $48.000 $40,000 $36.0po $51,000 Conversion costs during the month totaled: O $97.000 O $88.000 O $232.000 O $124.000
r cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 24,000, direct labor $ 14,400, and manufacturing overhead $ 19,200. As of January 1, Job 49 had been completed at a cost of $ 108,000 and was part of finished goods inventory. There was a $ 18,000...
Labels
Actual factory overhead
Depreciation of equipment
Direct labor used
Direct materials used
Factory overhead applied
Factory rent
Factory utilities
Indirect labor
Indirect materials
Required information (The following information applies to the questions displayed below. Marcelino Co.'s March 31 inventory of raw materials is $84,000. Raw materials purchases in April are $550,000, and factory payroll cost in April is $382,000. Overhead costs incurred in April are: indirect materials, $58,000; indirect labor, $27,000; factory rent, $39,000; factory utilities, $24,000; and factory...
The following costs were incurred in May: Direct materials $ 45,100 Direct labor $ 32,300 Manufacturing overhead $ 26,700 Selling expenses $ 17,900 Administrative expense $ 34,100 Prime costs during the month totaled:
The following costs were incurred in May: Direct materials $ 41,000 Direct labor $ 13,000 Manufacturing overhead $ 46,000 Selling expenses $ 18,000 Administrative expenses $ 15,000 Product costs during the month totaled:
1 Data Table Direct materials used Direct labor Manufacturing overhead allocated to the department . $ .. $ $ 106,000 20,000 158,000 Print Done Done wer Mac Trane Company's Work in Process Inventory account had a $63.000 beginning balance on December 1 (536.000 of this related to dired materials used during November, while $27.000 related to convers costs incurred during November Duning December, the following costs were incurred in the department 113 Click the icon to view the data from...
The following costs were incurred in May. Direct materials Direct labor Manufacturing overhead Selling expenses Administrative expense $39,100 $30,400 $18,000 $14,500 $34,700 01:03:56 Prime costs during the month totaled: Multiple Choice 0 O $69.500 0 $48.400 0 $36.700 0 $27500
Garcia Manufacturing uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2008, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job No. 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was...