A different manufacturing company began 2 new jobs during July. At the beginning of July, Job 227 was the only job in work in process inventory. There was no finished goods inventory. The cost of beginning work in process inventory for Job 227 consists of $1,500 in direct material cost, $2,000 in direct labor cost, and manufacturing overhead costs of $4,500. Total manufacturing overhead for the month was $16,054. The following information is available for costs added during the month of July:
job 227 | job 228 | job 229 | |
Direct Material | $935 | $2850 | $1300 |
Direct labor | $1840 | $3225 | $1975 |
direct labor hours | 184 | 310 | 204 |
Job 227 was completed and moved into finished goods inventory towards the beginning of the month. Later in the month, John 227 was sold. Job 228 was completed, but has yet to be sold. John 229 remains in production.
Required: Keep the following principles in mind as you follow the instructions below. First, costs for any job can only be in one place at the end of the month. Second, you will have to calculate the overhead rate for the month of July based upon the number of hours budgeted in production divided by the amount of manufacturing overhead budgeted. The annual budget for production was Budgeted Overhead of $180,000 and Budgeted Direct Labor Hours of 8,000. Third, the flow of funds is very important, but the detail on any job is only collected in the work in process inventory.
Calculate the cost of the ending work in process inventory as of the end of the month.
Calculate the cost of the finished goods inventory as of the end of the month.
Calculate the cost of goods sold for the month.
Budgeted Production Overhead | $ 180,000 |
Budgeted Direct Labor Hours | 8,000 |
Predetermined Production overhead rate/Direct Labor hour= | $ 22.50 |
Production Cost details for the Month of July | Job 227 | Job 228 | Job 229 | Total | |
Beginning WIP | |||||
Direct Materials | $ 1,500 | $ 1,500 | |||
Direct Labor | $ 2,000 | $ 2,000 | |||
Manufacturing overhead | $ 4,500 | $ 4,500 | |||
A | Total Beginning WIP | $ 8,000 | $ 8,000 | ||
Costs Added during July | |||||
a | Direct Materials | $ 935 | $ 2,850 | $ 1,300 | $ 5,085 |
b | Direct Labor | $ 1,840 | $ 3,225 | $ 1,975 | $ 7,040 |
c | Direct Labor Hrs | 184 | 310 | 204 | |
d | Manufacturing overhead @$22.5/Direct Labor Hr=c*22.5= | $ 4,140 | $ 6,975 | $ 4,590 | $ 15,705 |
B | Total Costs Added during July =a+b+d= | $ 6,915 | $ 13,050 | $ 7,865 | $ 27,830 |
Total Costs of Jobs at Month end=A+B | $ 14,915 | $ 13,050 | $ 7,865 | $ 35,830 | |
Job status | Sold | in FG | in WIP | ||
Cost of Ending WIP at the end of July (Job 229)= | $ 7,865 | ||||
Cost of FG Inventory at the end of July (Job 228)= | $ 13,050 | ||||
Cost of Goods Sold during July (Job 227)= | $ 14,915 |
A different manufacturing company began 2 new jobs during July. At the beginning of July, Job...
Ehrling Brothers Company makes jobs to customer order. During the month of July, the following occurred: Materials were purchased on account for $45,760. Materials totaling $40,980 were requisitioned for use in producing various jobs. Direct labor payroll for the month was $25,600 with an average wage of $16 per hour. Actual overhead of $8,860 was incurred and paid in cash. Manufacturing overhead is charged to production at the rate of $5.40 per direct labor hour. Completed jobs costing $60,000 were...
At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1,125 2,475 Balance, June 1 $7,875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...
2) A company began operations on the first of the month. During the month, two jobs were started. The following costs were incurred: Direct material Direct labor Job A $2,500 $7,000 Job B $5,000 $9,500 Factory overhead is applied at 120% of direct labor costs. During the month, Job A was completed but not sold. Job B has not been completed. Required: a. Calculate the cost of the ending work in process inventory as of the end of the month....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
1. The following selected ledger accounts of the Reynolds Manufacturing Company are for July. Materials Inventory July 1 balance …………………….. 150,000 July credits ……………………. 550,000 July debits ………………………….. 475,000 Manufacturing Overhead July debits ……………………...... 638,000 July 1 balance…………………… 50,000 July credits ……………………… 608,000 Work in Process Inventory July 1 balance …………………….. 100,000 July credits …………………… 1,650,000 July debits: Direct material …………………… 488,000 Direct labor ………………………… 675,000 Manufacturing overhead ………….. ? Wages Payable July debits …………………….. 850,000 July 1 balance……………………. 188,000...
Journal Entries, T-Accounts Ehrling Brothers Company makes jobs to customer order. During the month of July, the following occurred: Materials were purchased on account for $45,620. Materials totaling $40,880 were requisitioned for use in producing various jobs. Direct labor payroll for the month was $19,200 with an average wage of $12 per hour. Actual overhead of $8,870 was incurred and paid in cash. Manufacturing overhead is charged to production at the rate of $5.40 per direct labor hour. Completed jobs...
At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,200 $1,250 Direct labor 1,600 3,500 Applied overhead 1,120 2,450 Balance, June 1 $7,920 $7,200 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...
Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company had one job in process (Job 201) and one job completed but not yet sold (Job 200). Job 202 was started during January. Other select account balances follow (ignore any accounts that are not listed). Reyes Manufacturing Company uses a job order cost system. At the beginning of January, the company had one job in process (Job 201) and one job completed but not...
Instructions At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1.125 2,475 Balance, June 1 $7.875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 64 Job 45 Job 46...
Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow: Job 78 Job 79 Job 80 Units in each order 200 180 220 Units sold — 180 — Materials requisitioned $1,560 $990 $2,400 Direct labor hours 220 200 400 Direct labor cost $3,000 $3,000 $3,300 Overhead is assigned on the basis of direct labor hours at a rate of $8.40 per...