Question

Vaughan Company had the following costs at two different levels of activity: MH Used 10,000 MH 15,000 MH September October Co
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Cost C is same at 10,000 machine hours and 15,000 machine hours. Hence, cost C is fixed cost. When machine hours are increased from 10,000 to 15,000, both cost A and Cost B change. Hence, Cost A and Cost B are either variable costs or mixed costs.

For Cost A

Variable cost per machine hour = Change in cost/ Change in machine hours

= (120,000-80,000)/(15,000-10,000)

= 40,000/5,000

= $8

for 10,000 machine hours, Cost A would be = 10,000 x 8

= $80,000

In the question, Cost A for 10,000 machine hours is given as $80,000, hence cost A is a variable cost.

for Cost B

Variable cost per machine hour = Change in cost/ Change in machine hours

= (65,000-50,000)/(15,000-10,000)

= 15,000/5,000

= $3

Total variable cost for 10,000 machine hours = 10,000 x 3

= $30,000

Total cost at 10,000 machine hours = $50,000

Hence, fixed cost portion in cost B = Total cost at 10,000 machine hours- Total variable cost for 10,000 machine hours

= 50,000-30,000

= $20,000

For 14,000 machine hours

Cost A= 14,000 x 8 = $112,000

Cost B = 20,000+14,000 x 3 = $62,000

Cost C = $50,000

Total cost = Cost A + Cost B + Cost C

= 112,000+62,000+50,000

= $224,000

Kindly comment if you need further assistance.

Thanks‼!

Add a comment
Know the answer?
Add Answer to:
Vaughan Company had the following costs at two different levels of activity: MH Used 10,000 MH...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Vaughan Company had the following costs at two different levels of activity: MH Used 9,000 MH...

    Vaughan Company had the following costs at two different levels of activity: MH Used 9,000 MH 15,000 MH Cost A September October $ 66,000$ 66,000 $36,000 $ 60,000 $ 55,000$ 85,000 Cost B Cost C If Vaughan Company expected to used 12,000 machine hours (MH) next month, what would they expect total costs (Cost A + Cost B + Cost C) to be?

  • Vaughan Company had the following costs at two different levels of activity: MH Used 8,000 MH...

    Vaughan Company had the following costs at two different levels of activity: MH Used 8,000 MH 15,000 MH October September $ 40,000 Cost A $ 75,000 Cost B $ 68,000 $ 117,000 Cost C $ 32,000 $ 32,000 Which of the following statements are true? 1. Cost A and Care variable costs 2. In a month where 10,000 machine hours (MH) are expected to be used, Cost B would be estimated to be $85,000 3. In a month where 12,000...

  • Brona Company makes treadmills. The company controller wants to calculate the fixed and variable costs associated...

    Brona Company makes treadmills. The company controller wants to calculate the fixed and variable costs associated with the janitorial costs incurred in the factory. Data for the past four months were as follows:    Month Janitorial costs Machine hours September JC:$12,500 mh:770 October JC:15,000 MH:800 November JC:12,000 MH:600 December JC:13,200 MH:630 MH: machine hours Options: A. $6,000 B. None of these C. $5,230 D. $3,000 JC:janitorial cost

  • Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May...

    Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 45,000 35,000 55,000 65,000 Total Overhead Cost $175,050 $ 151,550 $198,550 $ 222,050 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35,000-machine-hour level of activity in May is as follows: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 42,000 55,000 54,550 Total overhead cost $ 151,550 The company wants...

  • Exercise 2-37 Assigning Costs to a Cost Object, Direct and Indirect Costs Hummer Company uses manufacturing...

    Exercise 2-37 Assigning Costs to a Cost Object, Direct and Indirect Costs Hummer Company uses manufacturing cells to produce its products (a cell is a manufacturing unit dedicated to the production of subassemblies or products). One manufacturing cell pro- duces small motors for lawn mowers. Suppose that the motor manufacturing cell is the cost object. Assume that all or a portion of the following costs must be assigned to the cell. a. Salary of cell supervisor b. Power to heat...

  • Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for...

    Activity-Based Costing Slack Corporation has the following predicted indirect costs and cost drivers for 2019 for the given activity cost pools: Fabrication Department Finishing Department Maintenance. ... Materials handling Machine setups Inspections .. $ 20,000 30,000 70,000 $10,000 15,000 5,000 25,000 $55,000 Cost Driver Machine hours Material moves Machine setups Inspection hours $120,000 The following activity predictions were also made for the year: Fabrication Department Finishing Department Machine hours .. Materials moves.. Machine setups Inspection hours. 10,000 3,000 700 5,000...

  • Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...

    Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 54,000    $188,180        May 44,000    $163,980        June 64,000    $212,380        July 74,000    $236,580   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 52,800     Supervisory salaries (fixed) 44,000   Maintenance (mixed) 67,180   Total overhead cost $ 163,980 The...

  • Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...

    Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 54,000    $188,180        May 44,000    $163,980        June 64,000    $212,380        July 74,000    $236,580   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 52,800     Supervisory salaries (fixed) 44,000   Maintenance (mixed) 67,180   Total overhead cost $ 163,980 The...

  • Arid Company operates with two support and two production depts. Support Dept A costs are assigned...

    Arid Company operates with two support and two production depts. Support Dept A costs are assigned with maintenance hours as the cost driver, and Support Dept B costs are assigned with headcount as the cost driver. The cost driver in Depts C and D is direct labor hours. One of the products the company produces requires 4 direct labor hours per unit in Dept C and 5 direct labor hours in Dept D. Prime cost for the product cost $110.00...

  • Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month...

    Nova Company's total overhead cost at various levels of activity are presented below: Total Machine-Overhead Month April May June July Hours Cost 55,000 205,600 45,000179,600 65,000 75,000 ş 231,600 ş 257,600 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 45,000 machine-hour level of activity is Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $67,500 49,000 63,100 $179,600 Nova Company's management wants to break down the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT