Question

Vaughan Company had the following costs at two different levels of activity: MH Used 8,000 MH 15,000 MH October September $ 4

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Cost A

Variable cost per unit = $75,000 - $40,000 / 15,000 - 8,000

Variable cost per unit = $35,000 / 7,000 = $5 per unit

Fixed costs = $75,000 - (15,000*$5)

Fixed costs = $75,000 - $75,000 = $0

Hence Cost A is a variable costs

Cost B:

Variable cost per unit = $117,000 - 68,000 / 15,000 - 8,000

Variable cost per unit = $49,000 / 7,000 = $7

Fixed costs = $117,000 - (15,000*$7)

Fixed costs = $117,000 - $105,000 = $12,000

Total costs = $12,000 + $7 * Number of machine hour used

Cost C:

Cost C is a fixed costs.

Option 1:

Cost A is variable cost and Cost C is fixed costs.

Hence statement is not true.

Option 2:

Total estimated cost of Cost B = $12,000 + $7*10,000

Total estimated cost of Cost B = $12,000 + 70,000 = $82,000

Hence statement is not true.

Option 3:

Sales $300,000
Variable costs:
Cost A (12,000*$5) 60,000
Cost B (12,000*$7) 84,000
Contribution margin $156,000

Hence statement is True

Option 4:

Cost C is a Fixed cost.

The statement is True

Hence option Both the statement #3 and #4 is True

Add a comment
Know the answer?
Add Answer to:
Vaughan Company had the following costs at two different levels of activity: MH Used 8,000 MH...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Vaughan Company had the following costs at two different levels of activity: MH Used 9,000 MH...

    Vaughan Company had the following costs at two different levels of activity: MH Used 9,000 MH 15,000 MH Cost A September October $ 66,000$ 66,000 $36,000 $ 60,000 $ 55,000$ 85,000 Cost B Cost C If Vaughan Company expected to used 12,000 machine hours (MH) next month, what would they expect total costs (Cost A + Cost B + Cost C) to be?

  • Vaughan Company had the following costs at two different levels of activity: MH Used 10,000 MH...

    Vaughan Company had the following costs at two different levels of activity: MH Used 10,000 MH 15,000 MH September October Cost A $ 80,000 $120,000 Cost B $ 50,000 $ 65,000 Cost C $50,000 $50,000 If Vaughan Company expected to used 14,000 machine hours (MH) next month, what would they expect total costs (Cost A+ Cost B+ Cost C) to be?

  • Tableau DA 17-3: Mini-Case, Computing and assigning costs using ABC LO P3 Chrom Co. manufactures two...

    Tableau DA 17-3: Mini-Case, Computing and assigning costs using ABC LO P3 Chrom Co. manufactures two models, the XL and RD. It also has two departments, assembly and finishing. The company wants to assign overhead costs to its two different models to better understand the profitability of each model. The Tableau Dashboard provides data for our analysis. Estimated Overhead Costs by Department Estimated Direct Labor Hours & Machine Hours by Department 150,000 hrs 125,000 hrs 100,000 hrs Finishing 75,000 hrs...

  • Maintenance costs at Seaside Manufacturing over the past six months are listed in the following table....

    Maintenance costs at Seaside Manufacturing over the past six months are listed in the following table. Month January February March April Maintenance cost $13,600 $14,720 $13,000 $14,480 $17,000 $13,200 Machine hours 15,500 16,900 13,000 16,600 18,000 15,000 May June Using the high-low method, what would the total maintenance costs be if 17,500 machine hours were used? (Round any intermediary calculations to the nearest cent.) O A. $16,600 OB. $3,000 OC. $14,000 OD. $32,000 Maintenance costs at Seaside Manufacturing over the...

  • Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...

    Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 54,000    $188,180        May 44,000    $163,980        June 64,000    $212,380        July 74,000    $236,580   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 52,800     Supervisory salaries (fixed) 44,000   Maintenance (mixed) 67,180   Total overhead cost $ 163,980 The...

  • Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...

    Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 54,000    $188,180        May 44,000    $163,980        June 64,000    $212,380        July 74,000    $236,580   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 52,800     Supervisory salaries (fixed) 44,000   Maintenance (mixed) 67,180   Total overhead cost $ 163,980 The...

  • Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May...

    Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $204,360 $180,060 $228,660 $252,960 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 54,600 60,000 65,460 Total overhead cost $ 180,060 The company wants to...

  • Question 14 z Company uses the formula y-a + bX to predict and analyze overhead costs....

    Question 14 z Company uses the formula y-a + bX to predict and analyze overhead costs. In the previous year, XYZ used $1,750 per month for the a factor and $0.35 for the b factor in applying overhead. XYZ has used direct labour hours in the past, but is wondering whether overhead behaviour is more closely associated with machine hours. The following data have been generated for Month Machine Hours Overhead Costs 432 468 394 483 $2,646 3,089 2,476 $2,903...

  • Tableau DA 4-3: Mini-Case, Computing and assigning costs using ABC LOP3 wants to assign overhead costs...

    Tableau DA 4-3: Mini-Case, Computing and assigning costs using ABC LOP3 wants to assign overhead costs to its two different models to better understand the profitability of each model. The Tableau Dashboard provides data for our analysis Estimated Overhead Costs by Estimated Direct Labor Hours & Machine Hours by Department Estimated Overhead Costs by Estimated Direct Labor Hours & Department Machine Hours by Department 150,000 hrs 125,000 hrs 100,000 hrs Finishing o lo 75,000 hrs Assembly Assembly Department Finishing: $3,000,000...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT