Answer :
(a) Activity rate for design = Total cost of Design / Total Engineering hour
= $ 164406 / 208 + 309
= $ 318 per hour
(b) Activity rate for machining = Total cost of machining / Total machine hour
= $ 583800 / 1130+ 3040
= $ 140 per hour
(c) Activity Rate for Inspection = Total cost / Number of Batch
= $ 25650 / 38 +16
= $ 475 per Batch
(d) Indirect Cost for product - A
Indirect cost | |
Design 208*$ 318 | $ 66144 |
Machining 1130* $ 140 | $ 158200 |
Inspection 38* $ 475 | $ 18050 |
Total Indirect cost | $ 242394 |
Number of Unit | 10800 |
Indirect cost per unit | $ 22.44 |
(e)
Indirect Cost for product - B
Indirect cost | |
Design 309*$ 318 | $ 98262 |
Machining 3040* $ 140 | $ 425600 |
Inspection 16* $ 475 | $ 7600 |
Total Indirect cost | $ 531462 |
Number of Unit | 6600 |
Indirect cost per unit | $ 80.52 |
(f) Manufacturing cost for product - A
10800 unit | |
Direct Material 10800* $ 48 | $ 518400 |
Direct Labor 10800* $ 20 | $ 216000 |
Indirect cost | $ 242394 |
Total manufacturing cost | $ 976794 |
Number of unit sold | 10800 |
Manufacturing cost per unit | $ 90.44 |
(g)
Manufacturing cost for product - B
6600 unit | |
Direct Material 6600* $ 65 | $ 429000 |
Direct Labor 6600*$ 26 | $ 171600 |
Indirect cost | $ 531462 |
Total manufacturing cost | $ 1132062 |
Number of unit sold | 6600 |
Manufacturing cost per unit | $ 171.52 |
(h) and (I) Gross profit for A and Gross profit for B
A | B | |
Number of unit | 10800 | 6600 |
Selling price | $ 140 | $ 198 |
Sales | $ 1512000 | $ 1306800 |
Less - Manufacturing cost | $ 976794 | $ 1132062 |
Gross profit | $ 535206 | $ 174738 |
Gross profit per unit | $ 49.56 | $ 26.48 |
rate for design rate for machining rate for inspection indirect cost for product a indirect cost...
drivers are as follows: Design Engineering Hours) Machining Machine Hours) Inspection (Batches) Cost $164,406 $583,800 $ 25,650 Usage by Product A 208 1,130 38 Usage by Product B 309 3,040 16 49 Walnut manufactures 10,800 units of Product A and 6,600 units of Product B per month. Each unit of Product A uses $48 of direct materials and $20 of direct lobor, while each unit of Product Buses $65 of direct materials and $26 of direct labor. Required: a. Calculate...
2.000 = $so 22. Walnut Systems produces two different products, Product A, which sells for $120 per unit. and Product B, which sells for $180 per unit, using three different activities: Design, which uses Engineering Hours as an activity driver; Machining, which uses machine hours as an activity driver; and Inspection, which uses number of batches as an activity driver. The cost of each activity and usage of the activity drivers are as follows: Cost Usage by Product A Usage...
Walnut Systems produces two different products, Product A, which sells for $120 per unit, and Product B, which sells for $180 per unit, using three different activities: Design, which uses Engineering Hours as an activity driver; Machining, which uses machine hours as an activity driver; and Inspection, which uses number of batches as an activity driver. The cost of each activity and usage of the activity drivers are as follows: Usage by Cost Product A Usage by Product B Design...
Walnut Systems produces two different products, Product A, which sells for $220 per unit, and Product B, which sells for $280 per unit, using three different activities: Design, which uses Engineering Hours as an activity driver; Machining, which uses machine hours as an activity driver; and Inspection, which uses number of batches as an activity driver. The cost of each activity and usage of the activity drivers are as follows: Cost Usage by Product A Usage by Product B Design...
Walnut Systems produces two different products, Product A, which sells for $128 per unit, and Product B, which sells for $208 per unit, using three different activities: Design, which uses Engineering Hours as an activity driver; Machining, which uses machine hours as an activity driver; and Inspection, which uses number of batches as an activity driver. The cost of each activity and usage of the activity drivers are as follows: Cost Usage by Product A Usage by Product B Design...
Instant Thumbs Up For Help Thank You! Have 40 minutes soon as
answered thumb up!
Walnut Systems produces two different products, Product A, which sells for $190 per unit, and Product B, which sells for $250 per unit, using three different activities: Design, which uses Engineering Hours as an activity driver; Machining, which uses machine hours as an activity driver, and Inspection, which uses number of batches as an activity driver. The cost of each activity and usage of the...
Wainut Systems produces two different products, Product A, which sols for $120 per unt, and Product B, which sals for $180 per unit, using throe difarent activitios: Design, which uses Enginearing Hours as an activty driver, Machining, which uses machine hours an an activity driver and Inspection, which uses number of batches as an activity driver The cost of each activity and usage of the acthvity drivers are as foillows Usage by Product A 200 1000 45 Usage by Product...
Lynwood, Inc. produces two different products (Product A and Product X) using two different activities: Machining, which uses machine hours as an activity driver, E and Inspection, which uses number of batches as an activity driver. The activity rate for Machining is $140 per machine hour, and the activity rate for Inspection is $560 per batch. The activity drivers are used as follows: Machining, which uses machine hours as an activity driver, Product A 1,400 54 Product X 3,200 E...
Lynwood, Inc. produces two different products (Product A and Product X) using two different activities: Machining, which uses machine hours as an activity driver, and Inspection, which uses number of batches as an activity driver. The activity rate for Machining is $220 per machine hour, and the activity rate for Inspection is $500 per batch. The activity drivers are used as follows: Product A Product X 1,400 3,500 53 16 Total 4,900 Machine hours Number of batches What is the...
Lynwood, Inc. produces two different products (Product A and Product X) using two different activities: Machining, which uses machine hours as an activity driver, and Inspection, which uses number of batches as an activity driver. The activity rate for Machining is $140 per machine hour, and the activity rate for Inspection is $500 per batch. The activity drivers are used as follows: Machine hours Number of batches Product A Product X 1,100 3,500 5321 Total 4,600 74 What is the...