Support department cost allocation-direct method Becker Tabletops has two support departments (Janitorial and Cafeteria) and
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Allocation of Janitorial Deptt (basis of Sq. ft)
Total Sq. feet area of two production department = 600+2400 = 3000
% of Sq ft area occupied by Cutting =600/3000*100 = 20%
% of Sq ft area occupied by Assembly = 2400/3000*100 = 80%
Janitorial cost allocated:
Cutting department = 290,000*20% = 58,000
Assembly department = 290,000*80% = 2,32,000
Allocation of Cafeteria Department (basis of number of employees)
Total Number of employees = 16+4 = 20
% of employees in Cutting = 16/20 *100 = 80%
% of employees in Assembly = 4/20*100 = 20%
Cafeteria cost allocated
Cutting department = 180,000*80% = 1,44,000
Assembly department = 180,000*20% = 36,000
Final Answer:
Cutting Assembly
Janitorial department cost allocated 58,000 2,32,000
Cafeteria department cost allocated 1,44,000 36,000
Add a comment
Know the answer?
Add Answer to:
Support department cost allocation-direct method Becker Tabletops has two support departments (Janitorial and Cafeteria) and two...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Support department cost allocation—direct method Becker Tabletops has two support departments (Janitorial and Cafeteria) and two...

    Support department cost allocation—direct method Becker Tabletops has two support departments (Janitorial and Cafeteria) and two production departments (Cutting and Assembly). Relevant details for these departments are as follows: Support Department Cost Driver Janitorial Department Square footage to be serviced Cafeteria Department Number of employees Janitorial Department Cafeteria Department Cutting Department Assembly Department Department costs $280,000    $170,000 $1,480,000    $670,000 Square feet 48 5,200 1,200 1,800 Number of employees 12 2    14 6    Allocate the support department...

  • Support department cost allocation direct method Becker Tabletops has two support departments (anitorial and Cafeteria) and...

    Support department cost allocation direct method Becker Tabletops has two support departments (anitorial and Cafeteria) and two production departments (Cutting and Assembly). Relevant details for these departments are as follows: Support Department Cost Driver Janitorial Department Square footage to be serviced Cafeteria Department Number of employees Janitorial Cafeteria Cutting Assembly Department Department Department Department Department costs $310,000 $169,000 $1,504,000 $680,000 Sare feet 5.000 1,000 4,000 Number of employees 10 3 30 10 Allocate the support department costs to the production...

  • Support department cost allocation-sequential method Becker Tabletops has two support departments (Janitorial and Cafeteria) and two...

    Support department cost allocation-sequential method Becker Tabletops has two support departments (Janitorial and Cafeteria) and two production departments (Cutting and Assembly). Relevant details for these departments are as follows: Support Department Cost Driver Janitorial Department Square footage to be serviced Cafeteria Department Number of employees Janitorial Cafeteria Cutting Assembly Department Department Department Department Department costs $310,000 $169,000 $1,504,000 $680,000 Square feet 50 5,000 1,000 4,000 Number of employees 10 3 30 10 Allocate the support department costs to the production...

  • Support department cost allocation-reciprocal services method Becker Tabletops has two support departments ( Janitorial and Cafeteria)...

    Support department cost allocation-reciprocal services method Becker Tabletops has two support departments ( Janitorial and Cafeteria) and two production departments (Cutting and Assembly). Relevant details for these departments are as follows: Support Department Cost Driver Janitorial Department Square footage to be serviced Cafeteria Department Number of employees Janitorial Department $310,000 50 10 Department costs Square feet Number of employees Cafeteria Department $169,000 5,000 3 Cutting Department $1,504,000 1,000 30 Assembly Department $680,000 4,000 10 Allocate the support department costs to...

  • Support department cost allocation-direct method Becker Tabletops has two support departments (Janitorial and Cafeteria) and two...

    Support department cost allocation-direct method Becker Tabletops has two support departments (Janitorial and Cafeteria) and two production departments (Cutting and Assembly). Relevant details for these departments are as follows: Support Department Cost Driver Janitorial Department Square footage to be serviced Cafeteria Department Number of employees Janitorial Cafeteria Cutting Assembly Department Department Department Department Department costs $310,000 $169,000 $1,504,000 $680,000 Square feet 50 5,000 1,000 4,000 Number of employees 10 3 30 10 Allocate the support department costs to the production...

  • 1. Support department cost allocation—sequential method Becker Tabletops has two support departments (Janitorial and Cafeteria) and...

    1. Support department cost allocation—sequential method Becker Tabletops has two support departments (Janitorial and Cafeteria) and two production departments (Cutting and Assembly). Relevant details for these departments are as follows: Support Department Cost Driver Janitorial Department Square footage to be serviced Cafeteria Department Number of employees Janitorial Department Cafeteria Department Cutting Department Assembly Department Department costs $310,000    $169,000 $1,504,000    $680,000 Square feet 50 5,000 1,000 4,000 Number of employees 10 3    30 10    Allocate the support...

  • - Show Me How Calculator upport department cost allocation direct method Becker Tabletops has two support...

    - Show Me How Calculator upport department cost allocation direct method Becker Tabletops has two support departments (Janitorial and Cafeteria) and two production departments (Cutting and Assembly). Relevant details for these departments are as follows: Support Department Cost Driver Janitorial Department Square footage to be serviced Cafeteria Department Number of employees Janitorial Cafeteria Cutting Assembly Department Department Department Department Department costs $290,000 $190,000 $1,490,000 $700,000 Square feet 5,200 1,000 4,000 Number of employees 16 Allocate the support department costs to...

  • Support department cost allocation—comparison Becker Tabletops has two support departments ( Janitorial and Cafeteria) a...

    Support department cost allocation—comparison Becker Tabletops has two support departments ( Janitorial and Cafeteria) and two production departments (Cutting and Assembly). Relevant details for these departments are as follows: Support Department Cost Driver Janitorial Department Square footage to be serviced Cafeteria Department Number of employees Janitorial Department Cafeteria Department Cutting Department Assembly Department Department costs $310,000    $169,000 $1,504,000    $680,000 Square feet 50 5,000 1,000 4,000 Number of employees 10 3    30 10    Allocated the support department costs to the production...

  • Support department cost allocation—comparison Becker Tabletops has two support departments ( Janitorial and Cafeteria) and two...

    Support department cost allocation—comparison Becker Tabletops has two support departments ( Janitorial and Cafeteria) and two production departments (Cutting and Assembly). Relevant details for these departments are as follows: Support Department Cost Driver Janitorial Department Square footage to be serviced Cafeteria Department Number of employees Janitorial Department Cafeteria Department Cutting Department Assembly Department Department costs $310,000    $169,000 $1,504,000    $680,000 Square feet 50 5,000 1,000 4,000 Number of employees 10 3    30 10    Allocated the support department...

  • Becker Tabletops has two support departments (Janitorial and Cafeteria) and two production departments (Cutting and Assembly)....

    Becker Tabletops has two support departments (Janitorial and Cafeteria) and two production departments (Cutting and Assembly). Relevan details for these departments are as follows: Support Department Cost Driver Janitorial Department Square footage to be serviced Cafeteria Department Number of employees Janitorial Cafeteria Cutting Assembly Department Department Department Department Department costs $310,000 $169,000 $1,504,000 $680,000 Square feet 50 5,000 1,000 4,000 Number of employees Allocate the support department costs to the production departments using the sequential method. Allocate the support department...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT