Question

Question 2. (25 marks) Levie Company uses standard costing. The company prepared its static budget for 2018 at 2,500,000 mach
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer :

For the Fixed overhead

1 (a) Budgeted amount = Total overhead budgeted - Variable overhead budgeted

= $ 31250000 - 2500000 hour * $ 11

= $ 3750000

1 (b) Budgeted cost per machine hour = Budgeted Fixed overhead / Budgeted Machine hour

= $ 3750000/ 2500000 hour

= $ 1.50 per hour

1 (c) Computation of Actual cost of Fixed oh

Fixed overhead rate variance = Budgeted fixed overhead - Actual Fixed oh

- $ 1500000 = $ 3750000 - Actual Fixed oh

Actual Fixed oh = $ 5250000

1 (d) Production volume variance = Absorbed fixed overhead - Budgeted Fixed overhead

= $ 3735000 - $ 3750000

= $ 15000 U

Working note -1

Absorbed Fixed overhead = Standard rate per hour * Standard hour for actual output

= $ 1.50*2490000hour = $ 3735000

Standard hour for actual Output = 1245000unit* 2 hour = 2490000 hour

Standard hour per unit required = $ 22/ $11 = 2 hour per unit


2 .Variable overhead rate variance

= ( Standard rate - Actual Rate ) * Actual hour   

= Standard rate * Actual hour - Actual rate * Actual hour

= $ 11*2400000 hour - $ 25200000

= $ 1200000 F

Variable overhead efficiency variance

=Standard rate ( Standard hour - Actual hour )

= $ 11 ( 2490000 hour - 2400000 hour )

   = $ 990000 F

Note -1

F = Favorable

U = Un favorable

  

Add a comment
Know the answer?
Add Answer to:
Question 2. (25 marks) Levie Company uses standard costing. The company prepared its static budget for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • marks) Levie Company uses standard costing. The company prepared its static budget for 2018 at 2,500,000...

    marks) Levie Company uses standard costing. The company prepared its static budget for 2018 at 2,500,000 machine-hours for the year. Total budgeted overhead cost is $31,250,000. The variable overhead rate is $11 per machine-hour ($22 per unit). Actual results for 2018 follow: Machine-hours Output Variable overhead Fixed overhead rate variance 2,400,000 hours 1,245,000 units 25200000 $ 1,500,000 Required I 1. Calculate for the fixed overhead: a. Budgeted amount b. Budgeted cost per machine-hour. c. Actual cost. d. Production-volume variance. 2....

  • Company uses standard costing. The company prepared its static budget for 2018 at 2,500,000 machine hours...

    Company uses standard costing. The company prepared its static budget for 2018 at 2,500,000 machine hours for the year. Total budgeted overhead cost is $33,500,000. The variable overhead rate is $11 per machine hour ($22 per unit). Actual result for 2018 as follow: Machine-hours 2,400,000 hours Output 1,230,000 units Variable overhead $27,600,000 Fixed overhead rate variance $1,350,000 U 1. Calculate for the fixed​ overhead: a. Budgeted amount. b. Budgeted cost per​ machine-hour. c. Actual cost. d. ​Production-volume variance. 2. Calculate...

  • Standard machine hours per unit of output 4 hours Standard variable-overhead rate per machine hour 8.00...

    Standard machine hours per unit of output 4 hours Standard variable-overhead rate per machine hour 8.00 Actual variable-overhead rate per machine hour Actual machine hours per unit of output Budgeted fixed overhead |Actual fixed overhead Budgeted production in units Actual production in units Variable-overhead spending variance Variable-overhead efficiency variance Fixed-overhead budget variance Fixed-overhead volume variance Total actual overhead Total budgeted overhead (flexible budget) Total budgeted overhead (static budget) Total applied overhead 9.00 3 S 50,000 25,000 24,000 72,000 Unfavorable 192,000...

  • Walkenhorst Company's machining department prepared its 2019 budget based on the following data: Practical capacity Standard...

    Walkenhorst Company's machining department prepared its 2019 budget based on the following data: Practical capacity Standard machine hours per unit Standard variable factory overhead Budgeted fixed factory overhead 40,000 units 2 $3.00 per machine hour $352,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 87,000 machine hours and incurred $619,000 in total manufacturing overhead cost to manufacture 42,190 units. Actual fixed overhead cost for the year was $371,000. Required: Determine for the...

  • The Taravez Company uses standard costing in its manufacturing plant for auto parts. The standard cost...

    The Taravez Company uses standard costing in its manufacturing plant for auto parts. The standard cost of a particular auto​ part, based on a denominator level of 3,900 output units per​ year, included 5 ​machine-hours of variable manufacturing overhead at $7 per hour and 5 ​machine-hours of fixed manufacturing overhead at $16 per hour. Actual output produced was 4,300 units. Variable manufacturing overhead incurred was $260,000. Fixed manufacturing overhead incurred was $265,000. Actual ​machine-hours were 30,000. Requirements 1. Prepare an...

  • Walkenhorst Company's machining department prepared its 2019 budget based on the following data: 40,000 units 2...

    Walkenhorst Company's machining department prepared its 2019 budget based on the following data: 40,000 units 2 Practical capacity Standard machine hours per unit Standard variable factory overhead Budgeted fixed factory overhead $3.00 per machine hour $424,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 85,800 machine hours and incurred $689,000 in total manufacturing overhead cost to manufacture 42,070 units. Actual fixed overhead cost for the year was $437,000. Required: Determine for the...

  • The MartinezMartinez Company uses standard costing in its manufacturing plant for auto parts. The standard cost...

    The MartinezMartinez Company uses standard costing in its manufacturing plant for auto parts. The standard cost of a particular auto​ part, based on a denominator level of 4,500 output units per​ year, included 5 ​machine-hours of variable manufacturing overhead at $7 per hour and 5 ​machine-hours of fixed manufacturing overhead at $15 per hour. Actual output produced was 4,800 units. Variable manufacturing overhead incurred was $ 240,000. Fixed manufacturing overhead incurred was $ 385,000. Actual​ machine-hours were 29,000. Variable OH...

  • Walkenhorst Company’s machining department prepared its 2019 budget based on the following data: Practical capacity 40,000...

    Walkenhorst Company’s machining department prepared its 2019 budget based on the following data: Practical capacity 40,000 units Standard machine hours per unit 2 Standard variable factory overhead $3.00 per machine hour Budgeted fixed factory overhead $ 376,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 85,200 machine hours and incurred $637,000 in total manufacturing overhead cost to manufacture 42,010 units. Actual fixed overhead cost for the year was $386,000. Required: Determine for...

  • The Tavarez Company uses standard costing in its manufacturing plant for auto parts. The standard cost...

    The Tavarez Company uses standard costing in its manufacturing plant for auto parts. The standard cost of a particular auto part, based on a denominator level of 3.700 output units per year, included 6 machine-hours of variable manufacturing overhead at $0 per hour and machine-hours of fixed manufacturing overhead at $14 per hour. Actual output produced was 4,000 units. Variable manufacturing overhead incurred was $255,000. Fixed manufacturing overhead incurred was $373.000 Actual machine-hours were 26,500 Read the requirements Requirement 1....

  • Walkenhorst Company's machining department prepared its 2019 budget based on the following data: 40,000 units Practical...

    Walkenhorst Company's machining department prepared its 2019 budget based on the following data: 40,000 units Practical capacity Standard machine hours per unit Standard variable factory overhead Budgeted fixed factory overhead $3.00 per machine hour $368,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 88,000 machine hours and incurred $636,000 in total manufacturing overhead cost to manufacture 43,000 units. Actual fixed overhead cost for the year was $380,000. Required: Determine for the year:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT