1. Materials price variance = (Actual quantity purchased * Actual price) - (Actual quantity purchased * Standard price)
= [(4.1 * $1.9) - (4.1 * $2)] * 500 units
= $205 Favorable
2. Materials quantity variance = (Actual quantity used * Standard price) - (Standard quantity * Standard price)
= [(4.1 * $2) - (4 * $2)] * 500 units
= $100 Unfavorable
3. Direct labour rate variance = (Actual hours * Actual rate) - (Actual hours * Standard rate)
= [(3.2 * $6.5) - (3.2 * $7)] * 500 units
= $800 Favorable
4. Direct labour efficiency variance = (Actual hours * Standard rate) - (Standard hours * Standard rate)
= [(3.2 * $7) - (3 * $7)] * 500 units
= $700 Unfavorable
5. Variable overhead rate variance = (Actual hours * Actual rate) - (Actual hours * Standard rate)
= [(2.2 * $3.1) - (2.2 * $3)] * 500 units
= $110 Unfavorable
6. Variable overhead efficiency variance = (Actual hours * Standard rate) - (Standard hours * Standard rate)
= [(2.2 * $3) - (2 * $3)] * 500 units
= $300 Unfavorable
yandard and actual costs per unit are provided below for the most recent period Brod 500...
Triple Star Company's standard and actual costs per unit are provided below for the most recent period During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost Metres 4 $8.00 4.1 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 Hours Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost $21.00 3.2 $20.80 Hours Hourly Rate $6.00 $3.00 $3.10 2.2 1 $6.82 $35.41 $35.00 Required: Given the information above,...
Triple Star Company's standard and actual costs per unit are provided below for the most recent per During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost Metres $8.00 4 4.1 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 Hours Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost $21.00 3 3.2 $20.80 Hours Hourly Rate $6.00 2 2.2 $3.00 $3.10 $6.82 $35.41 $35.00 Required: Given the information...
Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost $8.00 Metres 4 4.1 Hours 3 3.2 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $21.00 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost I 3 $20.80 Hours Hourly Rate 2 2.2 $6.00 $3.00 $3.10 $6.82 $35.41 $35.00 Required: Given...
Header Question 1 Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced Product Product Standard Cont Actual Cost Materials Metres Unit Price Per Metre Standard 4 $2.00 $8.00 Actual $1.90 $7.79 Direct labour Hours Hourly Rate Standard $7.00 $21.00 Actual 3.2 $6.50 $20.80 Variable overhead Hours Hourly Rate Standard 2 $3.00 $6.00 Actual 2.2 $3.10 $6.82 Total unit cost $35.00 $35.41 Required: Given the...
i need answer of 4,5,6,7 Question 1: Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost $8.00 $7.79 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Metres 4 4.1 Hours 3 3.2 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $21.00 $20.80 Hours Hourly Rate $6.00 $3.00 $3.10 2.2 $6.82...
Page Break Question 1: Triple Star Company's standard and actual costs per unit are provided below for the most recent period During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost Metres $8.00 4. 4.1 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 Hours Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost $21.00 3 3.2 $20.80 Hours Hourly Rate $6.00 2 19.2 $3.00 $3.10 $6.82 S35.41 $35.00...
А B I U ON A A A Question 1: rage or Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost $8.00 Metres 4 4.1 Hours 3 3.2 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $7.79 $21.00 $20.80 Hours Hourly Rate...
Toronto Company's budget and actual costs per unit are provided below for the most recent period. During this period, 700 units were actually produced Product Budget Cost Product Actual Cost $22.00 $19.76 Materials Budget Actual Direct labour Budget Actual Variable overhead Budget Actual Total unit cost Metres 5.5 5.2 Hours 4 3.7 Unit Price Per Metre $4.00 $3.80 Hourly Rate $5.00 $5.50 $20.00 $20.35 Hours Hourly Rate 4 3.81 $14.00 $3.50 $3.10 $11.78 $51.89 $56.00 Required: Given the information above,...
Page Break Question 1: CNC Company's Budget and actual costs per unit are provided below for the most recent period. During this period, 600 units were actually produced. Product Standard Cost Product Actual Cost $10.00 Metres 5 5.2 Hours 3 $11.44 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Unit Price Per Metre $2.00 $2.20 Hourly Rate $5.00 $5.50 $15.00 3.2 $17.60 Hours Hourly Rate 4 $12.00 $3.00 $3.10 4.2 $13.02 $42.06 $37.00 Required:...
Question 1: CNC Company's Budget and actual costs per unit are provided below for the most recent period. During this period, 600 units were actually produced. Product Product Standard Cost Actual Cost Materials Metres Unit Price Per Metre Standard 5 $2.00 $10.00 Actual 5.2 $2.20 $11.44 Direct labour Hours Hourly Rate Standard 3 $5.00 $15.00 Actual 3.2 $5.50 $17.60 Variable overhead Hours Hourly Rate Standard 4 $3.00 $12.00 Actual 4.2 $3.10 $13.02 Total unit cost $37.00 $42.06 Required: Given the...