Question

Triple Star Companys standard and actual costs per unit are provided below for the most recent period During this period, 50
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Question 1

Material Price Variance = (Standard Rate - Actual Rate) * Actual Quantity of Material Used

Standard Rate = $ 2 per Metre

Actual Rate = $ 1.90 per Metre

Actual Quantity of Material Used = 500 Units * 4.1 Metre per Unit = 2,050 Metres

Material Price Variance = (2 - 1.90) * 2,050

Material Price Variance = $ 205 Favourable Variance

Question 2

Material Quantity Variance = (Standard Quantity of Material for Actual Output - Actual Quantity of Material Used) * Standard Rate

Standard Rate = $ 2 per Metre

Actual Quantity of Material Used = 2,050 Metres

Standard Quantity of Material for Actual Output = 500 Units * 4 Metre per Unit = 2,000 Metres

Material Quantity Variance = (2,000 - 2,050) * 2

Material Quantity Variance = ($ 100) Unfavorable Variance

Question 3

Direct Labour Rate Variance = (Standard Rate per Labour Hour - Actual Rate per Labour Hour) * Actual Hours paid

Standard Rate per Labour Hour = $ 7

Actual Date per Labour Hour = $ 6.50

Actual Hours Paid = 500 Units * 3.20 Hours per Unit = 1,600 Hours

Direct Labour Rate Variance = (7 - 6.50) * 1,600

Direct Labour Rate Variance = $ 800 Favourable Variance

Question 4

Direct Labour Efficiency Variance = (Standard Hours for Actual Output - Actual Hours Worked) * Standard Rate per Direct Labour Hour

Standard Rate per Labour Hour = $ 7

Actual Hours Worked = 1,600 Hours

Standard Hours for Actual Output = 500 Units * 3 Hours per Unit = 1,500 Hours

Direct Labour Efficiency Variance = (1500 - 1600) * 7

Direct Labour Efficiency Variance = ( $ 700) Unfavorable Variance

Question 5

Variable Overhead Rate Variance = (Standard Rate per Hour - Actual Rate per Hour) * Actual Hours Worked

Standard Rate per Hour = $ 3

Actual Rate per Hour = $ 3.10

Actual Hours Worked = 500 Units * 2.2 Hours per Unit = 1,100 Hours

Variable Overhead Rate Variance = (3 - 3.10) * 1,100

Variable Overhead Rate Variance = ($ 110) Unfavorable Variance

Question 6

Variable Overhead Efficiency Variance = (Standard Hours for Actual Output - Actual Hours Worked ) * Standard Variable Overhead Rate per Hour

Standard Variable Overhead Rate per Hour = $ 3

Actual Hours Worked = 1,100 Hours

Standard hours for Actual Output = 500 Units * 2 Hour per Unit = 1000 Hours

Variable Overhead Efficiency Variance = (1,000 - 1,100) * $ 3

Variable Overhead Efficiency Variance = ($ 300) Unfavorable Variance

Question 7

Company has performed very well in keeping it's material and labour variances under control but the Unfavorable Overhead Variances requires immediate attention to find out the gaps for the shortfall in the final results. The materials and labour variance sare under control becuase the deficiency in one is fulfilled by the other. for example increases in material usage and labour is compensated by the reduced prices but in the case it didn't happen. Actual Overhead Rate and Usage were more than that of the standard being setup by the company due to which it shows undesirable results. The need is to fix those gaps and set the standard according to the more realistic situation keeping in mind.

Add a comment
Know the answer?
Add Answer to:
Triple Star Company's standard and actual costs per unit are provided below for the most recent...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Triple Star Company's standard and actual costs per unit are provided below for the most recent...

    Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost $8.00 Metres 4 4.1 Hours 3 3.2 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $21.00 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost I 3 $20.80 Hours Hourly Rate 2 2.2 $6.00 $3.00 $3.10 $6.82 $35.41 $35.00 Required: Given...

  • Triple Star Company's standard and actual costs per unit are provided below for the most recent...

    Triple Star Company's standard and actual costs per unit are provided below for the most recent per During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost Metres $8.00 4 4.1 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 Hours Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost $21.00 3 3.2 $20.80 Hours Hourly Rate $6.00 2 2.2 $3.00 $3.10 $6.82 $35.41 $35.00 Required: Given the information...

  • Header Question 1 Triple Star Company's standard and actual costs per unit are provided below for...

    Header Question 1 Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced Product Product Standard Cont Actual Cost Materials Metres Unit Price Per Metre Standard 4 $2.00 $8.00 Actual $1.90 $7.79 Direct labour Hours Hourly Rate Standard $7.00 $21.00 Actual 3.2 $6.50 $20.80 Variable overhead Hours Hourly Rate Standard 2 $3.00 $6.00 Actual 2.2 $3.10 $6.82 Total unit cost $35.00 $35.41 Required: Given the...

  • i need answer of 4,5,6,7 Question 1: Triple Star Company's standard and actual costs per unit...

    i need answer of 4,5,6,7 Question 1: Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost $8.00 $7.79 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Metres 4 4.1 Hours 3 3.2 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $21.00 $20.80 Hours Hourly Rate $6.00 $3.00 $3.10 2.2 $6.82...

  • yandard and actual costs per unit are provided below for the most recent period Brod 500...

    yandard and actual costs per unit are provided below for the most recent period Brod 500 units were acully produced Product Standard Cost Product Actual Cost $8.00 Metres 4 4.1 Hours 3 3.2 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $7.79 $21.00 3 $20.80 Hours Hourly Rate $6.00 $3.00 $3.10 2.2 $6.82 $35.41 $35.00 Required: Given the information above, compute the following variances....

  • Page Break Question 1: Triple Star Company's standard and actual costs per unit are provided below...

    Page Break Question 1: Triple Star Company's standard and actual costs per unit are provided below for the most recent period During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost Metres $8.00 4. 4.1 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 Hours Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost $21.00 3 3.2 $20.80 Hours Hourly Rate $6.00 2 19.2 $3.00 $3.10 $6.82 S35.41 $35.00...

  • А B I U ON A A A Question 1: rage or Triple Star Company's standard...

    А B I U ON A A A Question 1: rage or Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost $8.00 Metres 4 4.1 Hours 3 3.2 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $7.79 $21.00 $20.80 Hours Hourly Rate...

  • Toronto Company's budget and actual costs per unit are provided below for the most recent period....

    Toronto Company's budget and actual costs per unit are provided below for the most recent period. During this period, 700 units were actually produced Product Budget Cost Product Actual Cost $22.00 $19.76 Materials Budget Actual Direct labour Budget Actual Variable overhead Budget Actual Total unit cost Metres 5.5 5.2 Hours 4 3.7 Unit Price Per Metre $4.00 $3.80 Hourly Rate $5.00 $5.50 $20.00 $20.35 Hours Hourly Rate 4 3.81 $14.00 $3.50 $3.10 $11.78 $51.89 $56.00 Required: Given the information above,...

  • Question 1: CNC Company's Budget and actual costs per unit are provided below for the most...

    Question 1: CNC Company's Budget and actual costs per unit are provided below for the most recent period. During this period, 600 units were actually produced. Product Product Standard Cost Actual Cost Materials Metres Unit Price Per Metre Standard 5 $2.00 $10.00 Actual 5.2 $2.20 $11.44 Direct labour Hours Hourly Rate Standard 3 $5.00 $15.00 Actual 3.2 $5.50 $17.60 Variable overhead Hours Hourly Rate Standard 4 $3.00 $12.00 Actual 4.2 $3.10 $13.02 Total unit cost $37.00 $42.06 Required: Given the...

  • Page Break Question 1: CNC Company's Budget and actual costs per unit are provided below for...

    Page Break Question 1: CNC Company's Budget and actual costs per unit are provided below for the most recent period. During this period, 600 units were actually produced. Product Standard Cost Product Actual Cost $10.00 Metres 5 5.2 Hours 3 $11.44 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Unit Price Per Metre $2.00 $2.20 Hourly Rate $5.00 $5.50 $15.00 3.2 $17.60 Hours Hourly Rate 4 $12.00 $3.00 $3.10 4.2 $13.02 $42.06 $37.00 Required:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT