Question 1
Material Price Variance = (Standard Rate - Actual Rate) * Actual Quantity of Material Used
Standard Rate = $ 2 per Metre
Actual Rate = $ 1.90 per Metre
Actual Quantity of Material Used = 500 Units * 4.1 Metre per Unit = 2,050 Metres
Material Price Variance = (2 - 1.90) * 2,050
Material Price Variance = $ 205 Favourable Variance
Question 2
Material Quantity Variance = (Standard Quantity of Material for Actual Output - Actual Quantity of Material Used) * Standard Rate
Standard Rate = $ 2 per Metre
Actual Quantity of Material Used = 2,050 Metres
Standard Quantity of Material for Actual Output = 500 Units * 4 Metre per Unit = 2,000 Metres
Material Quantity Variance = (2,000 - 2,050) * 2
Material Quantity Variance = ($ 100) Unfavorable Variance
Question 3
Direct Labour Rate Variance = (Standard Rate per Labour Hour - Actual Rate per Labour Hour) * Actual Hours paid
Standard Rate per Labour Hour = $ 7
Actual Date per Labour Hour = $ 6.50
Actual Hours Paid = 500 Units * 3.20 Hours per Unit = 1,600 Hours
Direct Labour Rate Variance = (7 - 6.50) * 1,600
Direct Labour Rate Variance = $ 800 Favourable Variance
Question 4
Direct Labour Efficiency Variance = (Standard Hours for Actual Output - Actual Hours Worked) * Standard Rate per Direct Labour Hour
Standard Rate per Labour Hour = $ 7
Actual Hours Worked = 1,600 Hours
Standard Hours for Actual Output = 500 Units * 3 Hours per Unit = 1,500 Hours
Direct Labour Efficiency Variance = (1500 - 1600) * 7
Direct Labour Efficiency Variance = ( $ 700) Unfavorable Variance
Question 5
Variable Overhead Rate Variance = (Standard Rate per Hour - Actual Rate per Hour) * Actual Hours Worked
Standard Rate per Hour = $ 3
Actual Rate per Hour = $ 3.10
Actual Hours Worked = 500 Units * 2.2 Hours per Unit = 1,100 Hours
Variable Overhead Rate Variance = (3 - 3.10) * 1,100
Variable Overhead Rate Variance = ($ 110) Unfavorable Variance
Question 6
Variable Overhead Efficiency Variance = (Standard Hours for Actual Output - Actual Hours Worked ) * Standard Variable Overhead Rate per Hour
Standard Variable Overhead Rate per Hour = $ 3
Actual Hours Worked = 1,100 Hours
Standard hours for Actual Output = 500 Units * 2 Hour per Unit = 1000 Hours
Variable Overhead Efficiency Variance = (1,000 - 1,100) * $ 3
Variable Overhead Efficiency Variance = ($ 300) Unfavorable Variance
Question 7
Company has performed very well in keeping it's material and labour variances under control but the Unfavorable Overhead Variances requires immediate attention to find out the gaps for the shortfall in the final results. The materials and labour variance sare under control becuase the deficiency in one is fulfilled by the other. for example increases in material usage and labour is compensated by the reduced prices but in the case it didn't happen. Actual Overhead Rate and Usage were more than that of the standard being setup by the company due to which it shows undesirable results. The need is to fix those gaps and set the standard according to the more realistic situation keeping in mind.
Triple Star Company's standard and actual costs per unit are provided below for the most recent...
Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost $8.00 Metres 4 4.1 Hours 3 3.2 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $21.00 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost I 3 $20.80 Hours Hourly Rate 2 2.2 $6.00 $3.00 $3.10 $6.82 $35.41 $35.00 Required: Given...
Triple Star Company's standard and actual costs per unit are provided below for the most recent per During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost Metres $8.00 4 4.1 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 Hours Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost $21.00 3 3.2 $20.80 Hours Hourly Rate $6.00 2 2.2 $3.00 $3.10 $6.82 $35.41 $35.00 Required: Given the information...
Header Question 1 Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced Product Product Standard Cont Actual Cost Materials Metres Unit Price Per Metre Standard 4 $2.00 $8.00 Actual $1.90 $7.79 Direct labour Hours Hourly Rate Standard $7.00 $21.00 Actual 3.2 $6.50 $20.80 Variable overhead Hours Hourly Rate Standard 2 $3.00 $6.00 Actual 2.2 $3.10 $6.82 Total unit cost $35.00 $35.41 Required: Given the...
i need answer of 4,5,6,7 Question 1: Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost $8.00 $7.79 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Metres 4 4.1 Hours 3 3.2 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $21.00 $20.80 Hours Hourly Rate $6.00 $3.00 $3.10 2.2 $6.82...
yandard and actual costs per unit are provided below for the most recent period Brod 500 units were acully produced Product Standard Cost Product Actual Cost $8.00 Metres 4 4.1 Hours 3 3.2 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $7.79 $21.00 3 $20.80 Hours Hourly Rate $6.00 $3.00 $3.10 2.2 $6.82 $35.41 $35.00 Required: Given the information above, compute the following variances....
Page Break Question 1: Triple Star Company's standard and actual costs per unit are provided below for the most recent period During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost Metres $8.00 4. 4.1 $7.79 Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 Hours Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost $21.00 3 3.2 $20.80 Hours Hourly Rate $6.00 2 19.2 $3.00 $3.10 $6.82 S35.41 $35.00...
А B I U ON A A A Question 1: rage or Triple Star Company's standard and actual costs per unit are provided below for the most recent period. During this period, 500 units were actually produced. Product Standard Cost Product Actual Cost $8.00 Metres 4 4.1 Hours 3 3.2 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Unit Price Per Metre $2.00 $1.90 Hourly Rate $7.00 $6.50 $7.79 $21.00 $20.80 Hours Hourly Rate...
Toronto Company's budget and actual costs per unit are provided below for the most recent period. During this period, 700 units were actually produced Product Budget Cost Product Actual Cost $22.00 $19.76 Materials Budget Actual Direct labour Budget Actual Variable overhead Budget Actual Total unit cost Metres 5.5 5.2 Hours 4 3.7 Unit Price Per Metre $4.00 $3.80 Hourly Rate $5.00 $5.50 $20.00 $20.35 Hours Hourly Rate 4 3.81 $14.00 $3.50 $3.10 $11.78 $51.89 $56.00 Required: Given the information above,...
Question 1: CNC Company's Budget and actual costs per unit are provided below for the most recent period. During this period, 600 units were actually produced. Product Product Standard Cost Actual Cost Materials Metres Unit Price Per Metre Standard 5 $2.00 $10.00 Actual 5.2 $2.20 $11.44 Direct labour Hours Hourly Rate Standard 3 $5.00 $15.00 Actual 3.2 $5.50 $17.60 Variable overhead Hours Hourly Rate Standard 4 $3.00 $12.00 Actual 4.2 $3.10 $13.02 Total unit cost $37.00 $42.06 Required: Given the...
Page Break Question 1: CNC Company's Budget and actual costs per unit are provided below for the most recent period. During this period, 600 units were actually produced. Product Standard Cost Product Actual Cost $10.00 Metres 5 5.2 Hours 3 $11.44 Materials Standard Actual Direct labour Standard Actual Variable overhead Standard Actual Total unit cost Unit Price Per Metre $2.00 $2.20 Hourly Rate $5.00 $5.50 $15.00 3.2 $17.60 Hours Hourly Rate 4 $12.00 $3.00 $3.10 4.2 $13.02 $42.06 $37.00 Required:...