Jeb uses a job costing system to charge out costs for jobs completed. Job number 49 was completed on 28 April with 1 500 units produced for a customer, M. Gidy.
Day 1: Material consumed per requisition 201A amounted to R400
Day 1: An artisan worked 4 hours
Day 2: Material consumed per requisition 201B amounted to R300
Day 5: An artisan worked 6 hours
Day 9: An artisan plus a labourer worked 3 hours
Day 11: An artisan plus a labourer worked 8 hours
Labour overheads of 35% are added to the total cost.
Material overheads of 25% are added to the total cost.
Artisan rate is R75 per hour.
Labourer rate is R25 per hour.
Required
Calculate the total job cost and the cost per unit. Present your answer in column form.
We need at least 10 more requests to produce the answer.
0 / 10 have requested this problem solution
The more requests, the faster the answer.
Jeb uses a job costing system to charge out costs for jobs completed. Job number 49 was completed on 28 April with 1 500 units produced for a customer, M. Gidy.
Jeb uses a job costing system to charge out costs for jobs completed. Job number 49 was completed on 28 April with 1 500 units produced for a customer, M. Gidy. Day 1: Material consumed per requisition 201A amounted to R400 Day 1: An artisan worked 4 hours Day 2: Material consumed per requisition 201B amounted to R300 Day 5: An artisan worked 6 hours Day 9: An artisan plus a labourer worked 3 hours Day 11: An artisan plus...
Question 1 Total 6 000 The following information relates to GC Company for the current year: Common Special R Units produced 2000 Direct material cost R60 000 R100 000 160 000 Direct labour hours 6 000 4 000 Direct labour costs R60 000 RBO 000 140 000 Number of set-ups 40 40 Number of design changes 12 8 Overhead cost Set up 80 000 Design changes 60 000 Other 140 000 Total manufacturing costs 530 000 Required Calculate the cost...
QUESTION 2 [25] Erundu Limited uses a job order costing system. Only three jobs were worked on during the past month. The data for these jobs were as follows: Details Job A10 Job B15 Job C20 Opening WIP R26 800 R42 790 RO Direct material added during the month R17 275 RO R18 500 Direct labour for the month R14 500 R3 500 R24 000 The manufacturing overheads applied to the three jobs for the month were R126 000 and...
1. Anderson Company uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. Manufacturing overhead and direct labor hours were estimated at $70,400 and 22,000 hours, respectively. In June, Job 11461 was completed. Ma. terials costs on the job totaled $4,815 and labor costs totaled $2,325 at $7.50 per hour (310 hours worked on this job). At the end of the year, it was determined that the company worked...
QUESTION 2 Citysites Sdn. Bhd. uses a job-order costing system. On Sept 1, Materials and Supplies Control account had a balance of $28.000, whilst the Finished Goods (Job X10) balance on the same date was $15,000. Work in process as at Sept 1 consists of 2 jobs. Details as follows: Job Materials ($) Labour (S) Overhead (S) XII 5.200 2,300 3,300 X12 8,700 3,200 5,775 Direct labour cost (S) incurred and machine hours for the month of Sept: Job Direct...
[25] QUESTION 1 Duvani Limited uses a job order costing system with a predetermined overhead absorption rate based on machine hours. The company keeps only one set of records for cost and financial transactions. At the beginning of 20x9 the company estimated its manufacturing overheads for the year at R100 000 and machine hours at 16 000. The following information on the jobs worked on during December 20X9 is available: Job 67 Job 69 Job 63 Work-in-process on 1 December...
Stellar Sound, Inc. which uses a job-order costing system, had two jobs in process at the start of 20x1: job no. 64 ($84,100) and job no. 65 ($53,500). The following information is available: a. The company applies manufacturing overhead on the basis of machine hours (based on practical capacity). Budgeted overhead and machine activity for the year were anticipated to be $792,000, and 16,000 hours, respectively. b. The company worked on four jobs during the first quarter. Direct materials used,...
Tech Solutions is a consulting firm that uses a job-order costing system. Its direct materials consist of hardware and software that it purchases and installs on behalf of its clients. The firm's direct labor Includes salaries of consultants that work at the client's job site, and its overhead consists of costs such as depreciation, utilities, and insurance related to the office headquarters as well as the office supplies that are consumed serving clients. Tech Solutions computes its predetermined overhead rate...
lech Solutions is a consulting firm that uses a job-order costing system. Its direct materials consist of hardware and software that it purchases and installs on behalf of its clients. The firm's direct labor includes salaries of consultants that work at the client's job site, and its overhead consists of costs such as depreciation, utilities, and insurance related to the office headquarters as well as the office supplies that are consumed serving clients. Tech Solutions computes its predetermined overhead rate...
i cannot figure this out
Tech Solutions is a consulting firm that uses a job-order costing system. Its direct materials consist of hardware and software that it purchases and installs on behalf of its clients. The firm's direct labor includes salaries of consultants that work at the client's job site, and its overhead consists of costs such as depreciation, utilities, and insurance related to the office headquarters as well as the office supplies that are consumed serving clients. Tech Solutions...