A)

Capacity cost rate per hour

= Total cost / Total capacity

= 86,000/6,000

=$14.33

B)

Purchasing Activity rate = Hours*Cost per hour

= 8*14.33

=$114.64

Delivery activity rate

= 15*14.33

= $214.95

Add a comment
Know the answer?
Add Answer to:
Assume the same employees perform the purchasing and receiving activities, and these employees provide practical capacity...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • TDABC Bob Randall, cost accounting manager for Hemple Products, was asked to determine the costs of...

    TDABC Bob Randall, cost accounting manager for Hemple Products, was asked to determine the costs of the activities performed within the company's Manufacturing Engineering Department. The department has the following activities: creating bills of materials (BOMS), studying manufacturing capabilities, improving manufacturing processes, training employees, and designing tools. The resource costs (from the general ledger) and the times to perform one unit of each activity are provided below. Activities Resource Costs Unit Time Driver 0.7 hr. No. of BOMS Salaries Creating...

  • TDABC Bob Randall, cost accounting manager for Hemple Products, was asked to determine the costs of...

    TDABC Bob Randall, cost accounting manager for Hemple Products, was asked to determine the costs of the activities performed within the company's Manufacturing Engineering Department. The department has the following activities: Creating bills of materials (BOMs), studying manufacturing capabilities, improving manufacturing processes, training employees, and designing tools. The resource costs (from the general ledger) and the times to perform one unit of each activity are provided below. Resource Costs Activities Unit Time Driver Salaries Equipment $500,000 100,000 Creating BOMS Designing...

  • Simplifying the ABC System: TDABC Golding Bank provided the following data about its resources and activities...

    Simplifying the ABC System: TDABC Golding Bank provided the following data about its resources and activities for its checking account process: Resources Activities Time per Unit Activity Driver Supervision Phone and supplies $70,000 90,000 Processing accounts Issuing statements 0.20 hr. No. of accounts 0.10 hr No. of statements Salaries 275,000 Processing transactions 0.05 hr. No. of transactions Computer 25,000 Answering customer inquiries 0.15 hr. No. of inquiries Total $460,000 Total check processing hours 25,000 (practical capacity) Required: 1. Calculate the...

  • Houston Company produces two products. Standard and Jumbo, and currently uses a costing system that accumulates...

    Houston Company produces two products. Standard and Jumbo, and currently uses a costing system that accumulates all overhead costs in a single cost pool and assigns it to products based on direct labor dollars. After completing a study that showed overhead costs were driven by factors other than volume, Houston's management has decided to implement an activity based costing (ABC) system. The study showed that manufacturing overhead costs could be associated with three activities: (1) purchasing. (2) receiving, and (3)...

  • Woodruff Company is currently producing a snowmobile that uses five specialized parts. Engineerin...

    Woodruff Company is currently producing a snowmobile that uses five specialized parts. Engineering has proposed replacing these specialized parts with commodity parts, which will cost less and can be purchased in larger order quantities. Crt activity capacity and demand (with specialized parts required) and expected activity demand (with only commodity parts required) are provided. Activites Activity Driver Actvity Curent Activity Expected Activity Capacity Demand Demand Material usage Installing parts Purchasing parts Number of orders Additionally, the following activity cost data...

  • $21.000 Number of employees Average salary per employee Weeks of enployment per year Hours worked per...

    $21.000 Number of employees Average salary per employee Weeks of enployment per year Hours worked per week Practical capacity percentage Line-Iten Picking Packaging Loading Deliveries Minute per unit of the activity Customer L Customer 195 Customer N 145 Number of line itens picked Rumber of boxes packaged Number of deliveries loaded All Customers 405.000 50, 400 15. 700 Required: 1. Using the customer cost analysis as demonstrated in Exhibit 7A-2 in your textbook, compute the following: a. The cost per...

  • $ 24,500 Number of employees Average salary per employee Veeks of employment per year Hours worked...

    $ 24,500 Number of employees Average salary per employee Veeks of employment per year Hours worked per week Practical capacity percentage 40 85% Requisition Bid Processing Evaluation 45 Minutes per unit of the activity Inspection 30 Job Y 8 Number of requisitions processed Sunber of bid evaluations Number of inspections Job z 5 Now assume that Saratoga Company would like to answer the following "what if question using its time-driven activity-based costing system: Assuming our estimated activity demands for all...

  • Saratoga Company manufactures jobs to customer specifications. The company is conducting a time-driven activity-based costing study in its Purchasing Department to better understand how Purchasing Dep...

    Saratoga Company manufactures jobs to customer specifications. The company is conducting a time-driven activity-based costing study in its Purchasing Department to better understand how Purchasing Department labor costs are consumed by individual jobs. To aid the study, the company provided the following data regarding its Purchasing Department and three of its many jobs: Number of employees 19 Average salary per employee $ 23,500 Weeks of employment per year 52 Hours worked per week 40 Practical capacity percentage 85 % Requisition...

  • Stahl Company is conducting a time-driven activity based costing study In Its Shipping Department. To old...

    Stahl Company is conducting a time-driven activity based costing study In Its Shipping Department. To old the study, the company provided the following data regarding Its Shipping Department and the customers served by the department: $31,000 Number of employees Average salary per employee Weeks of employment per year Hours worked per week Practical capacity percentage 808 Line-Item Picking Loading Deliveries Packaging Minutes per unit of the activity Customer L Customer X Customer 95 21 Number of line items picked Number...

  • Activity Availability, Capacity Used, Unused Capacity Corazon Manufacturing Company has a purchasing department staffed by five...

    Activity Availability, Capacity Used, Unused Capacity Corazon Manufacturing Company has a purchasing department staffed by five purchasing agents. Each agent is paid $64,000 per year and is able to process 8,000 purchase orders. Last year, 35,600 purchase orders were processed by the five agents. Required: 1. Calculate the activity rate per purchase order. per purchase order 2. Calculate, in terms of purchase orders, the: a. Total activity availability purchase orders b. Unused capacity purchase orders 3. Calculate the dollar cost...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT