For Setup Activity
Activity Base = 11,000
Budgeted activity cost = $54,200
Activity rate for Setups = Budgeted activity cost / Activity Base
= 54,200/11,000
= $4.93
Correct option is c.
Kindly give a positive rating if you are satisfied with this solution and please ask if you have any query.
Thanks
Given the following information, determine the activity rate for setups. Activity Total Activity-Base Usage Budgeted Activity...
Given the following information, determine the activity rate for setups. Activity Total Activity-Base Usage Budgeted Activity Cost Setups 11,000 $54,200 Inspections 25,600 $122,500 Assembly (dih) 78,400 $396,800 a. $5.06 b. $4.79 c. $4.93 d. $4.99
Given the following information, determine the activity rate for setups. Activity Total Activity-Base Usage Budgeted Activity Cost Setups 11,000 $54,200 Inspections 25,600 $122,500 Assembly (dih) 78,400 $396,800 a. $5.06 b. $4.79 c. $4.93 d. $4.99
Given the following information, determine the activity rate for setups. Activity Total Activity-Base Usage Budgeted Activity Cost Setups 11,000 $54,200 Inspections 25,600 $122,500 Assembly (dih) 78,400 $396,800 a. $5.06 b. $4.79 c. $4.93 d. $4.99
Given the following information, determine the activity rate for setups. Activity Total Activity-Base Usage Fudgeted Activity Cost Setups 11,000 $54,200 Inspections 25,600 $122,500 Assembly (dlh) 78,400 $396,800 a. $5.06 b. $4.79 c. $4.93 d. $4.99 <
Given the following information, determine the activity rate for setups. Total Activity-Base Budgeted Activity Activity Usage Cost Setups 9,100 $52,000 Inspections 23,000 $149,500 Assembly 74,700 (dih) $396,200 a. $6.50 b. $5.71 c. $5.60 d. $5.30 <
Given the following information, determine the activity rate for setups. Activity Total Activity-Base Usage Budgeted Activity Cost Setups 11,000 $55,500 Inspections 25,200 $120,300 Assembly (dlh) 76,100 $412,300 a.$4.77 b.$5.42 c.$5.05 d.$5.24
Given the following information, determine the activity rate for setups. Activity Total Activity-Base Usage Budgeted Activity Cost Setups 10,300 $52,300 Inspections 25,100 $127,900 Assembly (dlh) 75,400 $377,000 a.$5.10 b.$5.03 c.$5.08 d.$5.00
Given the following information, determine the activity rate for setups. Activity Setups Inspections Assembly (dih) Oa. $58.00 Total Activity-Base Usage 10,000 24,000 80,000 Budgeted Activity Cost $180,000 $120,000 $400,000 Ob. $0.75 Oc. $5.09 Od. $18.00
Given the following information, determine the activity rate for setups. Activity Pool Activity Base Budgeted Amount Setups 10,000 $60,000 Inspections 24,000 $120,000 Assembly (DLH) 80,000 $400,000 a) $58.00 b) $6.00 c) $0.75 d) $5.09
Given the following information, determine the activity rate for setups. Activity Pool Activity Base 10,100 23,500 Budgeted Amount $54,000 Setups Inspections Assembly (DLH) $144,700 $424,800 77,100 a. $5.35 b. $5.63 c. $6.16 d. $5.51