Overhead rate=Respective cost/Respective activity
Overhead rate for :
Setup costs=6350/575=$11.0434783(Approx)
Engineering costs=16800/1150=$14.6086957(Approx)
Maintenance costs=91550/4803=$19.0610035(Approx)
Hence overhead allocated for skateboard =(11.0434783*240)+(14.6086957*660)+(19.0610035*2228)
=$54760.0898
Hence overhead cost per skateboard=54760.0898/1750
=$31.29(Approx)
Vintage Fun reproduces old - fashioned style roller skates and skateboards. The annual production and sales...
Vintage Fun reproduces old−fashioned style roller skates and skateboards. The annual production and sales of roller skates is 1,000 units, while 1,780 skateboards are produced and sold. The company has traditionally used direct labor hours to allocate its overhead to products. Roller skates require 1.5 direct labor hours per unit, while skateboards require 2.25 direct labor hours per unit. The total estimated overhead for the period is $114,900. The company is looking at the possibility of changing to an activity−based...
Vintage Fun reproduces old-fashioned style roller skates and skateboards. The annual production and sales of roller skates is 900 units, while 1,750 skateboards are produced and sold. The company has traditionally used direct labor hours to allocate its overhead to products. Roller skates require 4.5 direct labor hours per unit, while skateboards require 3.25 direct labor hours per unit. The total estimated overhead for the period is $114,400. The company is looking at the possibility of changing to an activity...
Vintage Fun reproduces old - fashioned style roller skates and skateboards. The annual production and sales of roller skates is 900 units, while 1,700 skateboards are produced and sold. The company has traditionally used direct labor hours to allocate its overhead to products. Roller skates require 4.5 direct labor hours per unit, while skateboards require 3.25 direct labor hours per unit. The total estimated overhead for the period is $114,100. The company is looking at the possibility of changing to...
z Cont. Batch costs Number of batches Engineering changes Number of engineering hours Total estimated manufacturing overhead for the year $196,000 $188,950 $3,600,200 Total estimated direct labor hours for the company for the year are 100,250 hours. The company is evaluating whether it should use an activity-based costing system in place of its traditional costing system. Additional information about production needed for the activity-based costing system follows: Zips Dees Total Direct labor hours 61,250 39,000 100,250 Batches 2,350 400 2,750...
Vandalay Industries manufactures two products: toasters and blenders. The annual production and sales of toasters is 2,100 units, while 1,600 units of blenders are produced and sold. The company has traditionally used direct labor hours to allocate its overhead to products. Toasters require 1.25 direct labor hours per unit, while blenders require 1 direct labor hours per unit. The total estimated overhead for the period is $149,315. The company is looking at the possibility of changing to an activity−based costing...
Adelberg Company has two products: A and B. The annual production and sales of Product Ais 2.500 units and of Product Bis 2,000 units. The company has traditionally used direct labor-hours as the basis for applying all manufacturing overhead to products Product A requires 0.3 direct labor- hours per unit and Product requires 0.6 direct labor hours per unit. The total estimated overhead for next period is $108,775. The company is considering switching to an activity based costing system for...
Acton Company has two products: A and B. The annual production and sales of Product A is 800 units and of Product B is 500 units. The company has traditionally used direct labor-hours as the basis for applying all manufacturing overhead to products. Product A requires 0.3 direct labor-hours per unit and Product B requires 0.2 direct labor-hours per unit. The total estimated overhead for next period is $92,023. The company is considering switching to an activity-based costing system for...
Adelberg Company has two products: A and B. The annual production and sales of Product A is 2,250 units and of Product B is 1,650 units. The company has traditionally used direct labor- hours as the basis for applying all manufacturing overhead to products. Product A requires 0.5 direct labor-hours per unit and Product B requires 0.8 direct labor-hours per unit. The total estimated overhead for next period is $104,900. The company is considering switching to an activity-based costing system...
Adelberg Company has two products: A and B. The annual production and sales of Product A is 1,950 units and of Product B is 1,350 units. The company has traditionally used direct labor-hours as the basis for applying all manufacturing overhead to products. Product A requires 0.5 direct labor-hours per unit and Product B requires 0.8 direct labor-hours per unit. The total estimated overhead for next period is $101,600. The company is considering switching to an activity-based costing system for...
Adelberg Company has two products: A and B. The annual production and sales of Product A is 1,850 units and of Product B is 1,250 units. The company has traditionally used direct labor-hours as the basis for applying all manufacturing overhead to products. Product A requires 0.3 direct labor-hours per unit and Product B requires 0.6 direct labor-hours per unit. The total estimated overhead for next period is $ 100,500.The company is considering switching to an activity-based costing system for...