Activity | Cost | Activity Driver | Prod. 1 | Prod. 2 | Activity Rate | Activity Cost: Prod. 1 | Activity Cost: Prod. 2 | ||
Design | $65,250 | Design Time | 880 | 1,370 | hours | $29 | /hour | $25,520 | $39,730 |
Preparation | $56,880 | Labour Hours | 3,130 | 3,190 | hours | $9 | /hour | $28,170 | $28,710 |
Machining | $137,700 | Machine Hours | 1,550 | 3,550 | hours | $27 | /hour | $41,850 | $95,850 |
Finishing | $23,310 | Batches | 218 | 300 | batches | $45 | /batch | $9,810 | $13,500 |
Inspection | $17,200 | Units | 660 | 1,060 | units | $10 | /unit | $6,600 | $10,600 |
Packaging | $29,682 | Orders | 40 | 57 | orders | $306 | /order | $12,240 | $17,442 |
Shipping | $12,852 | Packages | 70 | 38 | packages | $119 | /package | $8,330 | $4,522 |
1. Design:
Activity Rate = Total Cost / Total Driver Usage = $65,250 / (880 Hrs + 1,370 Hrs) = $65,250 / 2,250 hrs = $29 Per Hour
Activity Cost = Driver Usage Hours * Activity Rate Per Hour
Product 1: 880 Hours * $29 Per Hour = $25,520
Product 2: 1,370 Hours * $29 Per Hour = $39,730
2. Preparation:
Activity Cost for Product 2 = Total Activity Cost – Activity Cost for Product 1 = $56,880 - $28,170 = $28,710
Activity Rate = Activity Cost for Product 1 / Product 1 Driver Usage = $28,170 / 3,130 Hrs = $9 Per Hour
Product 2 Driver Usage = Activity Cost for Product 2 / Activity Rate Per Hour = $28,710 / $9 Per Hour = 3,190 Hrs
3. Machining:
Activity Cost for Product 2 = Total Activity Cost – Activity Cost for Product 1 = $137,700 - $41,850 = $95,850
Product 1 Driver Usage= Activity Cost for Product 1 / Activity Rate Per Hour = $41,850 / $27 Per Hour = 1,550 Hours
Product 2 Driver Usage= Activity Cost for Product 2 / Activity Rate Per Hour = $95,850 / $27 Per Hour = 3,550 Hours
4. Finishing:
Activity Cost for Product 1 = Product 1 Driver Usage * Activity Rate = 218 Batches * $45 Per Batch = $9,810
Activity Cost for Product 2 = Product 2 Driver Usage * Activity Rate = 300 Batches * $45 Per Batch = $13,500
Total Activity Cost = Activity Cost for Product 1 + Activity Cost for Product 2 = $9,810 + $13,500 = $23,310
5. Inspection:
Total Activity Cost = Activity Cost for Product 1 + Activity Cost for Product 2 = $6,600 + $10,600 = $17,200
Product 1 Driver Usage = Activity Cost for Product 1 / Activity Rate = $6,600 / $10 Per Unit = 660 Units
Product 2 Driver Usage = Activity Cost for Product 2 / Activity Rate = $10,600 / $10 Per Unit = 1,060 Units
6. Packaging:
Product 1 Driver Uasge = Activity Cost for Product 1 / Activity Rate = $12,240 / $306 Per Order = 40 Orders
Activity Cost for Product 2 = Product 2 Driver Usage * Activity Rate = 57 Orders * $306 Per Order = $17,442
Total Activity Cost = Activity Cost for Product 1 + Activity Cost for Product 2 = $12,240 + $17,442 = $29,682
7. Shipping:
Activity Cost for Product 1 = Total Activity Cost – Activity Cost for Product 2 = $12,852 - $4,522 = $8,330
Activity Rate = Activity Cost for Product 1 / Product 1 Driver Usage = $8,330 / 70 Packages = $119 Per Package
Product 2 Driver Usage = Activity Cost for Product 2 / Activity Rate = $4,522 / $119 Per Package = 38 Packages
Magnolia Company has identified seven activities as part of its manufacturing process and chosen corresponding activity...
Magnolia Company has identified seven activities as part of its manufacturing process and chosen corresponding activity drivers for each activity. The chart below lists the total cost of each activity, the amount of activity driver used for each of Magnolia's two products, the activity rate, and the activity cost assigned to each product. Fill in the blanks below: Cost Activity Driver Activity Rate Driver Usage Prod. 1 Prod. 2 850 1,200 hours 3,090 hours Activity Cost:Prod. 1 Activity Cost:Prod. 2...
Elmwood Company has identified seven activities as part of its manufacturing process and chosen corresponding activity drivers for each activity. The chart below lists the total cost of each activity, the amount of activity driver used for each of Elmwood's two products, the activity rate, and the activity cost assigned to each product. Fill in the blanks below: Activity Cost: Activity Cost: Prod. 1 Prod. 2 Driver Usage Prod. 1 Prod. 2 1,600 2,400 hours 5,400 hours $ $ $...
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $480,850 Number of setups 590 Ordering costs 425,500 Number of orders 18,500 Machine costs 700,400 Machine hours 41,200 Receiving 298,800 Receiving hours 8,300 Deoro produces two models of dishwashers with the following expected prime costs and activity demands: Model A Model B Direct materials $570,000 $821,000 Direct labor $462,000 $472,000 Units completed 16,500 8,800...
! Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $416,700 Number of machine hours 93,100 Number of design hours 73,338 Number of batches Estimated Cost Driver 92,600 9,500 510 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...
Morgana Company identifies three activities in its manufacturing
process: machine setups, machining, and inspections. Estimated
annual overhead cost for each activity is $205,900, $411,200, and
$58,500, respectively. The cost driver for each activity and the
expected annual usage are number of setups 2,900, machine hours
25,700, and number of inspections 1,300.
Compute the overhead rate for each activity.
Machine setups
$
per setup
Machining
$
per machine hour
Inspections
$
per inspection
Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $129,000 Number of setups 120 Ordering materials 15,300 Number of orders 900 Machining 92,400 Machine hours 11,550 Receiving 16,800 Receiving hours 1,050 Silven produces two models of cell phones with the following expected activity demands: Model X Model Y 5,900 11,800 80 40 300 Units completed Number of setups Number of orders Machine hours...
Morgana Company identifies three activities in its manufacturing process: machine setups, machining, and inspections. Estimated annual overhead cost for each activity is $201,600, $413,100, and $84,600, respectively. The cost driver for each activity and the estimated annual usage are number of setups 2,800, machine hours 24,300, and number of inspections 1,800. Compute the overhead rate for each activity. Machine setups $ per setup Machining $ per machine hour Inspections $ per inspection
Approximately Relevant ABC Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $129,000 Number of setups 120 Ordering materials 15,300 Number of orders 900 Machining 92,400 Machine hours 11,550 Receiving 16,800 Receiving hours 1,050 Silven produces two models of cell phones with the following expected activity demands: Model X Model Y Units completed 5,900 11,800 Number of setups 80 40 Number of orders...
CALCULATOR PAINTER VERSION BACK NEXT Question 1 Morgana Company identifies three activities in its manufacturing process: machine setups, machining, and inspections. Estimated annual overhead cost for each activity is $205,900, $265,100, and $78,400, respectively. The cost driver for each activity and the estimated annual usage are number of setups 2,900, machine hours 24,100, and number of inspections 1,600 Compute the overhead rate for each activity. Machine setups $ per setup Machining $ per machine hour Inspections per inspection