Question

8 600 QUESTION 2 a. The following costs were incurred by Barak Klever Ltd in 2020 in the design and construction of a new off
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Feasibility Study:- 8

Add:- Architect's Fees:- 100

Add:- Site Clearance:- 80

Add:- Construction materials:- 600

Add:- Cost of own inventories :- 30

Add:- Internal construction staff salaries:-360

Add:- ExternaL Contractor cost:- 2400

Total:- 3578

Add a comment
Know the answer?
Add Answer to:
8 600 QUESTION 2 a. The following costs were incurred by Barak Klever Ltd in 2020...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT