Estimated total direct labor hours = 48000
Total Estimated fixed manufacturing overhead = $307200
Variable overhead rate = 2.80
Predetermined overhead rate = Total Estimated fixed manufacturing overhead / Estimated direct labor hours + variable rate
Predetermined overhead rate =307200 / 48000 + 2.80 = 6.4 + 2.80 = $9.2 per hour
Calculation of Selling price |
|
Direct Material |
$600 |
Direct labor cost |
5500 |
Overhead cost (9.2 * 300 hrs ) |
2760 |
Total product cost |
8860 |
Mark up 20% (8860 * 20%) |
1772 |
Selling price |
$10632 |
Help Save 8 Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor- hours. The company based its predetermined overhead rate for the current year on 38,000 direct labor-hours, total fixed manufacturing overhead cost of $250,800, and a variable manufacturing overhead rate of $2.40 per direct labor-hour. Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data: Total direct labor-hours...
Mcewan Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on direct labor- hours. The company based its predetermined overhead rate for the current year on 35,000 direct labor hours, total fixed manufacturing overhead cost of $273.000, and a variable manufacturing overhead rate of $3.00 per direct labor hour. Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data....
Mcewan Corporation uses a Job-order costing system with a single plantwide predetermined overhead rate based on direct labor- hours. The company based its predetermined overhead rate for the current year on 23.000 direct labor-hours, total fixed manufacturing overhead cost of $170.200, and a variable manufacturing overhead rate of $5.00 per direct labor-hour. Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data: Total direct labor-hours...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor- hours. The company based its predetermined overhead rate for the current year on 21.000 direct labor-hours, total fixed manufacturing overhead cost of $163,800, and a variable manufacturing overhead rate of $3.30 per direct labor-hour Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data: Total direct labor-hours...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on 38,000 direct labor-hours, total fixed manufacturing overhead cost of $243,200, and a variable manufacturing overhead rate of $5.00 per direct labor-hour. Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data: Total direct labor hours:...
Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on 45,000 direct labor-hours, total fixed manufacturing overhead cost of $315,000, and a variable manufacturing overhead rate of $3.80 per direct labor-hour. Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data: Total direct labor-hours 300...
Item 6 Item 6 Mcewan Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on 21,000 direct labor-hours, total fixed manufacturing overhead cost of $163,800, and a variable manufacturing overhead rate of $3.30 per direct labor-hour. Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data:...
33 Mcewa Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on direct labor hours. The company based its predetermined overhead rate for the current year on 38.000 direct labor-hours, total fored manufacturing overhead cost of $250,800, and a variable manufacturing overhead rate of $2.40 per direct laber-hour Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data 1...
Cull Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $488,000, variable manufacturing overhead of $2.80 per machine-hour, and 61,000 machine-hours. The company has provided the following data concerning Job X455 which was recently completed: Number of units in the job 20 Total machine-hours 80 Direct materials $ 880 Direct labor cost $ 1,760 If...
Help Save & EX LUDO Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 38,500 $610, eee $ 6.00 Recently, Job T687 was completed with the following characteristics 1e Number of units in the job Total machine-hours Direct materials Direct labor cost 3e $ 69e...