Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours.
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Working Notes:
CACLULATION OF OVERHEAD APPLICATION RATE PER MACHINE HOURS
Overhead Application Rate = Budgeted Fixed Manufacturing Overhead Cost   "/" Budgeted Machine Hours "=" Estimated Overhead rate PER Machine Hrs
Overhead Application Rate = $                     2,19,800 "/"                        31,400 "=" $                       7.00
Solution:
CALCULATION OF SELLING PRICE OF JOB T 687
Direct Materials $                               580
Direct Labor Cost $                           1,160
Variable Manufacturing overhead (20 Hrs X $ 4) $                                 80
Fixed Manufacturing overhead (20 Hrs X $ 7) $                               140
Total Cost $                           1,960
Add: Markup @ 40% of $ 1,960 = $                               784
Sales Value $                           2,744
Divide By "/" By  
No. of Units in the Job                                      10
Selling Price for a Unit = ($ 2,744 / 10 Units) $                         274.40
Answer = $ 274.40 Per Unit
Add a comment
Know the answer?
Add Answer to:
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 31,400 $219,800 $ Recently, Job T687 was completed with the following characteristics: I 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 20 $ 580 $1,160 The amount of overhead...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 31,000 $310,000 $4.00 Recently, Job T687 was completed with the following characteristics: 10 30 Number of units in the job Total machine-hours Direct materials Direct labor cost $730 $1,460 The amount of overhead applied to Job...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 32,000 $352,000 $ 3.ee Recently, Job T687 was completed with the following characteristics: Number of units in the job Total nachine-hours Direct materials Direct labor cost 10 40 $ 675 $1,350 The unit product cost for...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 31,000 Total fixed manufacturing overhead cost $310,000 Variable manufacturing overhead per machine-hour $ 4.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 730 Direct labor cost $1,460 If the company marks up...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. TH company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 31,800 $159,090 Recently, Job T687 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost $ 660 $1,320 The unit product cost for Job T687 is...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 30,700 $337, 700 $ 4.00 Recently, Job T687 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 20 $ 575 $1,150 The amount of overhead...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 30,500 $610,000 $ 6.00 Recently, Job T687 was completed with the following characteristics: Number of units in the 10 job Total machine-hours Direct materials Direct labor cost 30 $ 690 $1,370 The unit product cost...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 31,000 $310,000 $ Recently, Job T687 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 30 $ 730 $1,460 The unit product cost for...

  • Lupo Corporation uses a job order costing system with a single plantwide predetermined overhead rate based...

    Lupo Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on machine hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 30,900 $154,500 $ 3.80 Recently, Job T687 was completed with the following characteristics Number of units in the job Total machine-hours Direct materials Direct labor cost 10 30 $ 740 $1,480 The amount of...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,000 Total fixed manufacturing overhead cost $ 252,000 Variable manufacturing overhead per machine-hour $ 2.10 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 675 Direct labor cost $ 1,050 The amount of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT