Question

Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Overhead rate = (310000/31000)+4 = 14 per hour

calculate unit product cost

Direct material 730
Direct labor 1460
Overhead (30*14) 420
Total product cost 2610
Unit 10
Unit product cost 261
Add a comment
Know the answer?
Add Answer to:
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 31,000 $310,000 $4.00 Recently, Job T687 was completed with the following characteristics: 10 30 Number of units in the job Total machine-hours Direct materials Direct labor cost $730 $1,460 The amount of overhead applied to Job...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 31,000 Total fixed manufacturing overhead cost $ 310,000 Variable manufacturing overhead per machine-hour $ 4 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 730 Direct labor cost $ 1,460 The amount of...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 31,000 Total fixed manufacturing overhead cost $310,000 Variable manufacturing overhead per machine-hour $ 4.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 730 Direct labor cost $1,460 If the company marks up...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 31,000 $310, $ Recently, Job T687 was completed with the following characteristics 10 Number of units in the job Total machine-hours Direct materials Direct labor cost $ 730 $1,460 The totaljob cost for Job T687 is...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,300 Total fixed manufacturing overhead cost $ 575,700 Variable manufacturing overhead per machine-hour $ 4 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 730 Direct labor cost $ 1,460 The total job...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,300 Total fixed manufacturing overhead cost $ 575,700 Variable manufacturing overhead per machine-hour $ 4 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 730 Direct labor cost $ 1,460 The amount of...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 30,300 $575,700 $ 4.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job Total machine-hours Direct materials Direct labor cost $ 730 $1,460 If the company marks up its...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 32,000 $352,000 $ 3.ee Recently, Job T687 was completed with the following characteristics: Number of units in the job Total nachine-hours Direct materials Direct labor cost 10 40 $ 675 $1,350 The unit product cost for...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 32,300 Total fixed manufacturing overhead cost $ 581,400 Variable manufacturing overhead per machine-hour $ 2.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 40 Direct materials $ 630 Direct labor cost $ 1,260 The amount of...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 32,000 $352,000 $ 3.00 Recently, Job T687 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 40 $ 675 $1,350 The amount of overhead...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT