Question

Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours.
Multiple Choice $2610 $2.990 O $150 0 $1880
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Calculation of predetermined overhead rate
Predetermined overhead rate Fixed manufacturing costs/Total machine hours
Predetermined overhead rate 310000/31000
Predetermined overhead rate $10 per machine hour
Calculation of total cost of job
Direct materials $730
Direct labor cost $1,460
Variable manufacturing cost $120 4*30
Fixed manufacturing cost $300 10*30
Total cost of job $2,610
Thus, total cost of job is $2,610
Add a comment
Know the answer?
Add Answer to:
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 31,000 $310,000 $ Recently, Job T687 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 30 $ 730 $1,460 The unit product cost for...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 31,000 $310,000 $4.00 Recently, Job T687 was completed with the following characteristics: 10 30 Number of units in the job Total machine-hours Direct materials Direct labor cost $730 $1,460 The amount of overhead applied to Job...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 31,000 Total fixed manufacturing overhead cost $ 310,000 Variable manufacturing overhead per machine-hour $ 4 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 730 Direct labor cost $ 1,460 The amount of...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 31,000 Total fixed manufacturing overhead cost $310,000 Variable manufacturing overhead per machine-hour $ 4.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 730 Direct labor cost $1,460 If the company marks up...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,300 Total fixed manufacturing overhead cost $ 575,700 Variable manufacturing overhead per machine-hour $ 4 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 730 Direct labor cost $ 1,460 The total job...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,300 Total fixed manufacturing overhead cost $ 575,700 Variable manufacturing overhead per machine-hour $ 4 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 730 Direct labor cost $ 1,460 The amount of...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 30,300 $575,700 $ 4.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job Total machine-hours Direct materials Direct labor cost $ 730 $1,460 If the company marks up its...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 32,300 $581,400 $ 2.00 Recently, Job T687 was completed with the following characteristics: 10 40 Number of units in the job Total machine-hours Direct materials Direct labor cost $ 630 $1,260 The unit product cost for...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 32,300 Total fixed manufacturing overhead cost $ 581,400 Variable manufacturing overhead per machine-hour $ 2.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 40 Direct materials $ 630 Direct labor cost $ 1,260 The amount of...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 32,000 $352,000 $ 3.00 Recently, Job T687 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 40 $ 675 $1,350 The amount of overhead...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT