CALCULATION OF PREDETERMINED OVERHEAD RATE: | ||
Variable mfg overhead per machine hour | $ 4.00 | Per MH |
Fixed manufacturing overhead per hour = 575700/30300 = | $ 19.00 | Per MH |
Predetermined overhead rate = 4+19 = | $ 23.00 | Per MH |
WORKINGS FOR COST OF PRODUCTION: | ||
The price would be: | ||
Direct material cost | $ 730 | |
Direct labor cost | $ 1,460 | |
Manufacturing overhead assigned = 30*23 = | $ 690 | |
Total cost of production | $ 2,880 | |
Mark up 40% = 2880*40% = | $ 1,152 | |
Total selling price | $ 4,032 | |
Number of units | 10 | Units |
Price per unit = 4032/10 = | $ 403.20 |
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,300 Total fixed manufacturing overhead cost $ 575,700 Variable manufacturing overhead per machine-hour $ 4 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 730 Direct labor cost $ 1,460 The total job...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,300 Total fixed manufacturing overhead cost $ 575,700 Variable manufacturing overhead per machine-hour $ 4 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 730 Direct labor cost $ 1,460 The amount of...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 31,000 Total fixed manufacturing overhead cost $310,000 Variable manufacturing overhead per machine-hour $ 4.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 730 Direct labor cost $1,460 If the company marks up...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 31,000 $310,000 $ Recently, Job T687 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 30 $ 730 $1,460 The unit product cost for...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 31,000 Total fixed manufacturing overhead cost $ 310,000 Variable manufacturing overhead per machine-hour $ 4 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 730 Direct labor cost $ 1,460 The amount of...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 31,000 $310, $ Recently, Job T687 was completed with the following characteristics 10 Number of units in the job Total machine-hours Direct materials Direct labor cost $ 730 $1,460 The totaljob cost for Job T687 is...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 31,000 $310,000 $4.00 Recently, Job T687 was completed with the following characteristics: 10 30 Number of units in the job Total machine-hours Direct materials Direct labor cost $730 $1,460 The amount of overhead applied to Job...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 31,500 $ 220,500 $ 6.00 Recently, Job T687 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 40 $ 685 $1,370 If the company...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour Recently , Job T687 was completed with the following characteristics: 31,400 $219,800 $ 4.00 Number of units in the job Total machine-hours Direct materials Direct labor cost 10 20 $ 580 $1,160 If the company marks...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 32,000 $352,000 $ 3.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job Total machine-hours Direct materials Direct labor cost 10 40 $ 675 $1,350 If the company marks up...