Question

Saved Help Whitley Construction Company is in the home remodeling business. Whitley has three teams of highly skilled employe
Budgeted direct materials cost and direct labor cost for the year are estimated at $450,000 and $600,000, respectively. Direc
0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1
OH rate per DLH:
Budgeted Overheads 4,95,000
Divide: Budgeted DLH 22,500
OH rate per DLH: 22 per DLH
Req 1.
Total cost of Jobs:
Harrison Barnes Tyler
Material cost 6753 13229 42338
Labour cost 15367 22184 49654
Overheads applied @ 22 per DLH 990 1936 2926
Total cost 23110 37349 94918
Req 2.
Direct labour hours used 23,800
Multiply: Oh rate per DLH 22
Overheads applied 523600
Actual overheads incurred 525000
Under-applied overheads 1400
Add a comment
Know the answer?
Add Answer to:
Saved Help Whitley Construction Company is in the home remodeling business. Whitley has three teams of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Homework Saved Help Set Serial Problem Business Solutions LO P1, P2, P3 The computer workstation furniture...

    Homework Saved Help Set Serial Problem Business Solutions LO P1, P2, P3 The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June, Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs. Direct materials Direct labor Overhead Job 602 $1,500 800 400 Job 603 $3,300 1,420 710 Job 604 $2,700 2,100 1,050 Job 602 was started in production in May, and these costs were assigned...

  • Davis & Company is an architectural firm specializing in home remodeling for private clients and new...

    Davis & Company is an architectural firm specializing in home remodeling for private clients and new office buildings for corporate clients. Davis charges customers at a billing rate equal to 134% of the client's total job cost. A client's total job cost is a combination of (1) professional time spent on the client ($63 per hour cost of employing each professional) and (2) operating overhead allocated to the client's job. Davis allocates operating overhead to jobs based on professional hours...

  • Grenier & Company is an architectural firm specializing in home remodeling for private clients and new...

    Grenier & Company is an architectural firm specializing in home remodeling for private clients and new office buildings for Annika Lawson hired Grenier to design her kitchen remodeling. A total of 30 professional hours were incurred on this job. corporate clients. Grenier charges customers at a billing rate equal to 126% of the client's total job cost. A client's total job In addition, Lawson's remodeling job required one of the professionals to travel back and forth to her house for...

  • Saved Help Save & Exit Submit 10 Check my work 2 Mason Company has two manufacturing...

    Saved Help Save & Exit Submit 10 Check my work 2 Mason Company has two manufacturing departments-Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B Estimated Data Kanufacturing overhead Direct labor hours Machine hours points Machining Assembly Total $12,500,000 625,000 $13, 125,000 525,000 520,000 25,000 500,000 500,000 20,000 eBook...

  • Farris & Company is an architectural firm specializing in home remodeling for private clients and new...

    Farris & Company is an architectural firm specializing in home remodeling for private clients and new office Abagal Lahired and to design her lachen remodeling A total of 25 professional hours were incurred on this buildings for corporate dients Farris charges customers at a biling rate equal to 1281 of the diens otaljob b . In addition Laws remodeling abrogured one of the professionals to travel back and forth to her house for a A dient cost is a combination...

  • 1.Consider a single job at Company B: Direct Materials costs were : 7,882 Direct labor was...

    1.Consider a single job at Company B: Direct Materials costs were : 7,882 Direct labor was 64 hours at a rate of $16/HR MOH is allocated to jobs based on labor hours Budgeted MOH cost is 23,428 Budgeted dl labor hours is 4,622 actual MOH was 28,730 actual direct labor hours was 5,422 If actual costing is used, what is the actual overhead rate? 2. Consider a single job at Company B: Direct Materials costs were : 6,845 Direct labor...

  • Bramble Company uses a job order cost system in each of its three manufacturing departments. Manufacturing...

    Bramble Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2020, the following estimates were made for the year. D E K Manufacturing overhead $1,089,000 $1,500,000 $960,000 Direct labor costs $1,361,250 $1,375,000 $495,000 Direct labor hours 110,000 125,000 44,000 Machine...

  • Tyler Tooling Company uses a job order cost system with overhead applied to products on the...

    Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $213,520 and total machine hours at 62,800. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job:     Job 101 Job 102 Job 103 Total Direct materials used $...

  • Tyler Tooling Company uses a job order cost system with overhead applied to products on the...

    Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $234,840 and total machine hours at 61,800. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job:     Job 101 Job 102 Job 103 Total Direct materials used $...

  • ter 2 Saved Help Save & Exit Submit Exercise 2-7 Job-Order Costing; Working Backwards [LO2 1,...

    ter 2 Saved Help Save & Exit Submit Exercise 2-7 Job-Order Costing; Working Backwards [LO2 1, LO2-2, LO2-3] Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $15 per hour . During the year, the company started and completed only two jobs-Job Alpha, which used 54,500 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT