Learning curve problem:
A company was ordered to make 6 custom made parts. the labor costs of manufacturing all of the parts was $1000, and the manager's estimate an improvement coefficient of .6. what would be the labor costs of the next (identical) 3 part order.
Given That,
Improvement Coefficient = 0.6
Learning Rate = 1-0.6 = 0.4
New Labor cost for identical 3 part order = Labor Cost for 6 part order*(Learning Rate)^(ln3/ln2)
New Labor cost for identical 3 part order = 1000*(0.4)^(ln3/ln2)
New Labor cost for identical 3 part order = 1000*0.2340346 = 234.03
Learning curve problem: A company was ordered to make 6 custom made parts. the labor costs...
AbC Company is a Contracting Company that builds custom- made boats. It received from MVB an order to build 5 custom-made boats. The boats are to be delivered in 6 months with the first two to be delivered in the next two months. The following costs are incurred for the two boats to be delivered in two months: Direct Materials $ 80,000 Direct Labor $120,000 Manufacturing Overhead is applied at 150% of Direct Labor. Required: How Much...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,800,000 in manufacturing overhead cost at an activity level of 240,000 machine hours. The company spent the entire month of January working on a large order for 16,000 custom-made machined parts. The company had...
Shelf-It Ltd. incurs the following costs to make each custom-made shelf: materials of $14, labour of $14, variable overhead of $4, and fixed overhead of $6. Each shelf normally sells for $45. A customer is offering to buy 1,550 units at $37 each. Shelf-It will incur additional costs of $3 per shelf to imprint a logo and to pay for shipping. (a) Prepare an incremental analysis for the special order. Reject Order Accept Order Incremental Revenue and Costs Revenues Costs...
Question 5 Shelf-It Ltd. incurs the following costs to make each custom-made shelf: materials of $14, labour of $14, variable overhead of $4, and fixed overhead of $6. Each shelf normally sells for $45. A customer is offering to buy 1,550 units at $37 each. Shelf-It will incur additional costs of $3 per shelf to imprint a logo and to pay for shipping. (a) Prepare an incremental analysis for the special order. Reject Order Accept Order Incremental Revenue and Costs...
Gordon Company produces custom-made machine parts. A setup activity is required for the batches of parts that it produces. Activity output is measured using setup hours. The value-added standard (SQ) for this activity is zero. On July 1, at the beginning of the fiscal year, 15 setup hours were allowed and used per batch. The standard wage rate for setup labor is $24 per setup hour. During the first quarter of the new fiscal year, the company is planning to...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,262,400 in manufacturing overhead cost at an activity level of 576,000 machine-hours. The company spent the entire month of January working on a large order for 12,100 custom-made machined parts. The company had no work...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,247,600 in manufacturing overhead cost at an activity level of 574,000 machine-hours. The company spent the entire month of January working on a large order for 12,000 custom-made machined parts. The company had no work...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,192,500 in manufacturing overhead cost at an activity level of 559,000 machine-hours. The company spent the entire month of January working on a large order for 12,200 custom-made machined parts. The company had no work...
Check m Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,230,000 in manufacturing overhead cost at an activity level of 564,000 machine-hours. The company spent the entire month of January working on a large order for 12,500 custom-made machined parts. The company had...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,245,000 in manufacturing overhead cost at an activity level of 566,000 machine-hours. The company spent the entire month of January working on a large order for 12,600 custom-made machined parts. The company had no work...