Answer:
1)
Setup standard 15 hours per batch
Expected cost
(15 x $ 24)
$ 360 per batch
Kaizen standard
( 15 (-) 50% )
7.5 hours per batch
Expected cost
( 7.5 x $ 24 )
$ 180 per batch
2)
Setup standard 7.5 hours per batch
Expected cost $ 180 per batch
3)
Maintenance standard
( 15 (-) 40% )
9 hours per batch
Standard batch cost
( 9 x $ 24 )
$ 216
Add a comment
Know the answer?
Add Answer to:
Gordon Company produces custom-made machine parts. A setup activity is required for the batches of parts...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Variances Maquina Company produces custom-made...

    Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Variances Maquina Company produces custom-made machine parts. Maquina recently has implemented an activity-based management (ABM) system with the objective of reducing costs. Maquina has begun analyzing each activity to determine ways to increase its efficiency. Setting up equipment was among the first group of activities to be carefully studied. The study revealed that setup hours was a good driver for the activity. During the last year, the company incurred...

  • Total Budgeted Manufacturing Overhead Cost Allocation Base Activity Materials handling $ Number of parts Machine setup...

    Total Budgeted Manufacturing Overhead Cost Allocation Base Activity Materials handling $ Number of parts Machine setup 13,200 5,200 49,500 86,100 Number of setups Number of parts Insertion of parts Finishing Finishing direct labor hours $ 154,000 Total Print Done * Requirements 1. Compute the cost allocation rate for each activity. 2. Compute the manufacturing overhead cost that should be assigned to Job 420. 3. Compute the manufacturing overhead cost that should be assigned to Job 510 Print Done Farragut Company...

  • 8.Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing...

    8.Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. Costs...

  • eBook Calculator Unit-Based Versus Activity-Based Costing Fisico Company produces exercise bikes. One of its plants produces...

    eBook Calculator Unit-Based Versus Activity-Based Costing Fisico Company produces exercise bikes. One of its plants produces two versions: a standard model and a deluxe model. The deluxe model has a wider and sturdier base and a variety of electronic gadgets to help the exerciser monitor heartbeat, calories burned, distance traveled, etc. At the beginning of the year, the following data were prepared for this plant: Standard Model Deluxe Model Expected quantity 30,000 15,000 Selling price $370 $700 Prime costs $4.5...

  • Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing...

    Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. Costs...

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $ 250,680 Number of machine hours 61,600 Number of design hours 66,482 Number of batches Estimated Cost Driver 71,600 7.ee 465 Required: 1. Compute the activity rate for each activity 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $171,100 Number of machine hours 45,100 Number of design hours 66,123 Number of batches Estimated Cost Driver 59,000 5,500 465 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...

  • Please show working and answer in order Unit-Based Versus Activity-Based Costing Fisico Company produces exercise bikes....

    Please show working and answer in order Unit-Based Versus Activity-Based Costing Fisico Company produces exercise bikes. One of its plants produces two versions: a standard model and a deluxe model. The deluxe model has a wider and sturdier base and a variety of electronic gadgets to help the exerdser monitor heartbeat, calories burned, distance traveled, etc. At the beginning of the year, the following data were prepared for this plant Standard Model 30,000 $370 Deluxe Model 15,000 $700 Expected quantity...

  • Company used to consider a traditional costing system based on machine hours; however, they are currently...

    Company used to consider a traditional costing system based on machine hours; however, they are currently considering an activity-based costing (ABC) approach. The company estimates the usage of 50,000 direct labor hours (DLH) and 30,000 machine hours (MH) for the current year. The following data show the budgeted manufacturing overhead (OH): Activity center Cost driver Activity driver Cost Material handling # of parts handled 6,000,000 $720,000 Setup costs # of setups 750 $315,000 Machining costs # of machine hours 30,000...

  • Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Variances Maquina Company pro...

    Calculation of Value-Added and Non-Value-Added Costs, Activity Volume and Unused Capacity Variances Maquina Company produces custom-made machine parts. Maquina recently has implemented an activity-based management (ABM) system with the objective of reducing costs. Maquina has begun analyzing each activity to determine ways to increase its efficiency. Setting up equipment was among the first group of activities to be carefully studied. The study revealed that setup hours was a good driver for the activity. During the last year, the company incurred...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT