Rowan Company produces pipes for concert-quality organs. Each job is unique. In April 2016, it completed all outstanding orders, and then, in May 2016, it worked on only two jobs, M1 and M2:
Direct manufacturing labor is paid at the rate of
$25 per hour. Manufacturing overhead costs are allocated at a budgeted rate of $22 per direct manufacturing labor-hour. Only Job M1 was completed in May.
Read the requirements
Requirement 1. Compute the total cost for Job M1.
Job Costs May 2016 |
Job M1 |
---|---|
Total costs |
Rowan Company, May 2016
Job M1
Job M2
Direct materials
$75,000
$56,000
Direct manufacturing labor
275,000
209,000
.
Caluclation of Total cost of Jobs | ||||
Job M1 | Job M2 | |||
Direct materials | 75,000 | 56,000 | ||
Direct manufacturing labor | 275,000 | 209,000 | ||
Total Overhead allocated | 242,000 | 183,920 | (See Note 1 below) | |
Total Job Cost | 592,000 | 448,920 | ||
Note 1: OH Calculation | ||||
Job M1 | Job M2 | |||
Direct manufacturing labor | 275,000 | 209,000 | ||
Labor rate per hour | 25 | 25 | ||
No. of Hours used in Job | 11,000 | 8,360 | ||
Budgdted Overehad rate per hr | 22 | 22 | ||
Total Overhead allocated | 242,000 | 183,920 | ||
Rowan Company produces pipes for concert-quality organs. Each job is unique. In April 2016, it completed...
Rafael Company produces pipes for concert-quality organs. Each job is unique. In April 2016, it completed all outstanding orders, and then, in May 2016, it worked on only two jobs, M1 and M2: : (Click the icon to view the job information.) Direct manufacturing labor is paid at the rate of $30 per hour. Manufacturing overhead costs are allocated at a budgeted rate of $22 per direct manufacturing labor-hour. Only Job M1 was completed in May. Read the requirements. Requirement...
2. Post the journal entries to T-accounts for all of the inventories, Cost of Goods Sold, the Maruta cu would be used to authorized as backup for the entry. Overhead Control Account, and the Manufacturing Overhead Allocated 4-31 Job costing, journal entries. Donald Transport assembles prestige manufactured homes. Its job. indirect-cost pool (manufacturing overhead allocated at a budgeted $31 per machine-hour in 2017). The following data (in millions) show operation costs for 2017: Materials Control, beginning balance, January 1, 2017...
Job Costs At the end of April, Prichard Company had completed Jobs 50 and 51. Job 50 is for 1,000 units, and Job 51 is for 200 units The following data relate to these two jobs: Job at $20 per unit and 1,400 units for Job 51 On April 20, raw materials were requisitioned for production as follows: 500 units for at $22 per unit. During April, Prichard Company accumulated 700 hours of direct labor costs on Job 50 and...
Job Costs At the end of April, Kaye Company had completed Jobs 50 and 51. Job 50 is for 500 units, and lob 51 is for 200 units. The following data relate to these two jobs: On April 20, raw materials were requisitioned for production as follows: 500 units for Job 50 at $10 per unit and 1,400 units for Job 51 at $24 per unit. During April, Kaye Company accumulated 200 hours of direct labor costs on Job 50...
Job Costs At the end of April, Prichard Company had completed Jobs 50 and 51. Job 50 is for 200 units, and Job 51 is for 500 units. The following data relate to these two jobs: On April 20, raw materials were requisitioned for production as follows: 200 units for Job 50 at $12 per unit and 1,200 units for Job 51 at $12 per unit. During April, Prichard Company accumulated 500 hours of direct labor costs on Job 50...
Job Costs At the end of April, Kaye Company had completed Jobs 50 and 51. Job 50 is for 1,000 units, and Job 51 is for 500 units. The following data relate to these two jobs: On April 20, raw materials were requisitioned for production as follows: 300 units for Job 50 at $24 per unit and 1,100 units for Job 51 at $12 per unit. During April, Kaye Company accumulated 700 hours of direct labor costs on Job 50...
Job Costs At the end of April, Kaye Company had completed Jobs 50 and 51. Job 50 is for 500 units, and Job 51 is for 200 units. The following data relate to these two jobs: On April 20, raw materials were requisitioned for production as follows: 500 units for Job 50 at $10 per unit and 1,400 units for Job 51 at $24 per unit. During April, Kaye Company accumulated 200 hours of direct labor costs on Job 50...
Job Costs At the end of April, Kaye Company had completed Jobs 50 and 51. Job 50 is for 500 units, and Job 51 is for 200 units. The following data relate to these two jobs: On April 20, raw materials were requisitioned for production as follows: 500 units for Job 50 at $10 per unit and 1,400 units for Job 51 at $24 per unit. During April, Kaye Company accumulated 200 hours of direct labor costs on Job 50...
Job Costs At the end of April, Almerinda Company had completed Jobs 50 and 51. Job 50 is for 23,040 units, and Job 51 is for 26,000 units. The following data relate to these two jobs: On April 6, Almerinda Company purchased on account 60,000 units of raw materials at $12 per unit. On April 21, raw materials were requisitioned for production as follows: 25,000 units for Job 50 at $10 per unit and 27,000 units for Job 51 at...
Job Costs At the end of May, Bergan Company had completed Jobs 200 and 305. Job 200 is for 2,390 units, and Job 305 is for 2,053 units. The following data relate to these two jobs: On May 7, Bergan Company purchased on account 10,000 units of raw materials at $8 per unit. During May, raw materials were requisitioned for production as follows: 7,500 units for Job 200 at $8 per unit and 1,480 units for Job 305 at $5...