Question

La Mia’s Casas builds replicas of residences of famous and infamous people. The company is highly...

La Mia’s Casas builds replicas of residences of famous and infamous people. The company is highly automated, and the new accountant-owner has decided to use machine hours as the basis for predicting maintenance costs. The following data are available from the company’s most recent eight months of operations:

Machine Hours Maintenance Costs
4,000 $1,470
7,000 1,200
3,500 1,680
6,000 1,100
3,000 1,960
9,000 880
8,000 1,020
5,500 1,200

a. Using the high-low method, determine the cost formula for maintenance costs with machine hours as the basis for estimation.

Total cost = $Answer + $Answer X

b. Indicate whether each of the following statements is true or false based on the results of part (a).

(1) Results indicate that as machine hours increase, maintenance cost decreases. TrueFalse
(2) The components of fixed and variable costs are unclear. TrueFalse
(3) Based on the data provided, the equation in part (a) functions correctly. TrueFalse

Tom’s Shoe Repair provides a variety of shoe repair services. Analysis of monthly costs revealed the following cost formulas when direct labor hours are used as the basis of cost determination:

Supplies y = $0 + $4.00X
Production supervision and direct labor y = $500 + $7.00X
Utilities y = $350 + $5.40X
Rent y = $450 + $0.00X
Advertising y = $75 + $0.00X

a. Prepare a flexible budget at 250, 300, 350, and 400 direct labor hours.

250 300 350 400
Variable costs:
Supplies @ $4.00 per DLH
Direct labor @ $7.00 per DLH
Utilities @ $5.40 per DLH
Fixed costs:
Direct labor
Utilities
Rent
Advertising
Total cost

b. Calculate a total cost per direct labor hour at each level of activity. Round amounts to two decimal places.

250 300 350 400
Cost per DLH

c. Tom’s employees usually work 350 direct labor hours per month. The average shoe repair requires 1.25 labor hours to complete. Tom wants to earn a 40 percent margin on his cost. What should be the average charge per customer, rounded to the nearest dollar to achieve Tom’s profit objective?
$Answer

0 0
Add a comment Improve this question Transcribed image text
Answer #1

La Mia's Casas

Machine-hours Maintenance Costs
High level 9000 880
Low level 3000 1960
Change 6000 -1080

Variable cost per machine hour = $-1080/6000 = $-0.18

Fixed cost (at high level) = $880 - (9000 x $-0.18) = $880 + $1620 = $2500

Fixed cost (at low level) = $1960 - (3000 x $-0.18) = $1960 + $540 = $2500

a. Total cost = $2500 - $0.18x

b.

(1) Results indicate that as machine hours increase, maintenance cost decreases. TRUE
(2) The components of fixed and variable costs are unclear. FALSE
(3) Based on the data provided, the equation in part (a) functions correctly. TRUE

Per HOMEWORKLIB RULES the first question has been answered. Please post the remaining independent question separately. Thank you.

Add a comment
Know the answer?
Add Answer to:
La Mia’s Casas builds replicas of residences of famous and infamous people. The company is highly...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • QUESTION 2) Hannover Manufacturing Company has three service departments and three production departments. The company budgeted...

    QUESTION 2) Hannover Manufacturing Company has three service departments and three production departments. The company budgeted its manufacturing overhead (MOH) cost for the upcoming year of 2020 as follows: Service Departments Production Departments Factory Repair and Management Cafeteria Maintenance Cutting Molding Finishing 425,000 375,000 95,000 700,000 920,000 485,000 I. Allocation in USD). Space occupied (m²) Number of employees Maintenance hours 500 1,000 200 3,000 4,500 4,000 125 55 22 680 150 720 80 50 0 250 400 300 Machine hours...

  • Nile Corp. has identified three cost pools to allocate overhead costs. The following estimates are provided...

    Nile Corp. has identified three cost pools to allocate overhead costs. The following estimates are provided for the coming year: Cost Pool Overhead Costs Cost driver Activity level Supervision of direct labor $234,000 Direct labor-hours 780,000 Machine maintenance $128,800 Machine-hours 920,000 Facility rent $266,000 Square feet of area 140,000 Total overhead costs $628,800 The accounting records show the Mossman Job consumed the following resources: Cost driver Actual level Direct labor-hours 300 Machine - hours 1,700 O A. $0.30 per dih;...

  • Hotchkiss Company has two support departments, Maintenance Department (MD) and Personnel Department (PD), and two producing...

    Hotchkiss Company has two support departments, Maintenance Department (MD) and Personnel Department (PD), and two producing departments, P1 and P2. The Maintenance Department costs of $90,000 are allocated on the basis of standard service hours used. The Personnel Department costs of $9,000 are allocated on the basis of number of employees. The direct costs of Departments P1 and P2 are $36,000 and $60,000, respectively. Data on standard service hours and number of employees are as follows: Maint. Dept. Person. Dept....

  • 2. The Galaxy Company has two service departments (Power and maintenance) and two production departments (Machinery...

    2. The Galaxy Company has two service departments (Power and maintenance) and two production departments (Machinery and Assembly). Additional information is given below: Kilowatt Maintenance Cost Hours Hours Machinery 450,000 39,000 1,600 Assembly 210.000 15,000 2,400 Power 135,000 5,500 1,000 Maintenance 90,000 6,000 600 Costs of Power department are allocated on the basis of Kilowatt Hours. The Costs of Maintenance department are allocated on the basis of Maintenance Hours. Total machine hours worked in Machinery Department is 2,500 and total...

  • 2. The Galaxy Company has two service departments (Power and maintenance) and two production departments (Machinery...

    2. The Galaxy Company has two service departments (Power and maintenance) and two production departments (Machinery and Assembly). Additional information is given below: Kilowatt Maintenance Cost Hours Hours Machinery 450,000 39,000 1,600 Assembly 210.000 15,000 2,400 Power 135,000 5,500 1,000 Maintenance 90,000 6,000 600 Costs of Power department are allocated on the basis of Kilowatt Hours. The Costs of Maintenance department are allocated on the basis of Maintenance Hours. Total machine hours worked in Machinery Department is 2,500 and total...

  • Shaker Stairs Co.designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles,...

    Shaker Stairs Co.designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted overhead costs Amount $75,000 82,000 220,000 105,000 108,000 126,000 270,000...

  • please show fomulas Given the following information for Dorttmund Corporation: Advertising costs = 320,000 Office rent...

    please show fomulas Given the following information for Dorttmund Corporation: Advertising costs = 320,000 Office rent = 240,000 Direct materials = 800,000 Delivery vehicle depreciation = 90,000 Factory repair and maintenance = 420,000 Sales salary = 510,000 Indirect labor = 220,000 Manufacturing equipment depreciation = 180,000 Administrative salaries = 360,000 President's salary = 700,000 Sales revenue = 5,200,000 Indirect materials = 190,000 Direct labor = 1,500,000 Machine hours = 2,000 Direct Labor hours = 10,000 Machine hours per unit =...

  • Clampit Company hour are as follows: uses a flexible budget for manufacturing overhead based on machine...

    Clampit Company hour are as follows: uses a flexible budget for manufacturing overhead based on machine hours. Variable manufacturing overhead costs per machine Indirect labor $5.00 Indirect materials $2.10 Maintenance $0.50 Utilities $0.40 Fixed overhead costs per month are Supervision $1,200 Insurance $400 Property taxes $600 Depreciation $1,800 The company believes it will normally operate in a range of 4,000 to 8,000 machine hours per month. During the month of June 2020, the company incurs the following manufacturing overhead costs:...

  • M u ie unveis Tor its production activities follows Grinding Polishing Product modification Providing power System...

    M u ie unveis Tor its production activities follows Grinding Polishing Product modification Providing power System calibration 11,000 machine hours 11,000 machine hours 1,600 engineering hours 15,000 direct labor hours 400 batches Job 3175 130 units 250 MH Job 4286 1,625 units 2,500 MH Number of units Machine hours Engineering hours Batches Direct labor hours 34 eng. 22 eng. hours 25 batches 450 DLH hours 75 batches 4,050 DLH 5. If the company uses a plantwide overhead rate based on...

  • Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components...

    Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted overhead costs Amount $75,000 82,000 220,000 100,000 120,000 126,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT