1)
Ensign Landscape Design | |||||
Job-Order Cost Sheets | |||||
For the month of April | |||||
Job 39 | Job 40 | Job 41 | Job 42 | Job 43 | |
Begining Balance | $540 | $3,400 | $2,990 | 0 | 0 |
Direct Materials | 700 | 560 | 375 | 3,500 | 6,900 |
Direct Labors (a) | 500 | 600 | 490 | 2,500 | 3,000 |
Applied Overhead [a * 110%] | 550 | 660 | 539 | 2,750 | 3,300 |
Total Cost | 2,290 | 5,220 | 4,394 | 8,750 | 13,200 |
Applied Overhead =(Direct Labor Cost * 110%)
2)
Ending Balance in Work In Process (as of April 30) = Total Cost of (Job 39 + Job 42)
Job 39 = $2,290
Job 42 = $8,750
TOTAL = $11,040
Cost of Goods Sold for April = Total Cost of (Job 40 + Job 41 + Job 43)
Job 40 = $5,220
Job 41 = $4,394
Job 43 = $13,200
TOTAL = $22,814
3) Ensign Landscape Design
Income Statement
For the month ended April 30
Sales | $29,658 |
Cost of Goods Sold | 22,814 |
Gross Margin | 6,844 |
Less: | |
Selling and administrative expenses | 4,575 |
Operating Income | $2,269 |
Sales = Cost of goods sold + (30% of cost of goods sold)
= $22,814 + (30% * $22,814)
= $22,814 + $6,844.2
= $29,658.2 OR $29,658
Instructions Ensign Landscape Design design landscape plans and plants the material for clients. On April 1,...
Ensign Landscape Design designs landscape plans and plants the material for clients. On April 1, there were three jobs in process, Jobs 39, 40, and 41. During April, two more jobs were started, Jobs 42 and 43. By April 30, Jobs 40, 41, and 43 were completed and sold. The following data were gathered: Job 39 Job 40 Job 41 Job 42 Job 43 Balance, April 1 $500 $3,370 $3,010 — — Direct materials 650 530 350 $3,450 $6,890 Direct...
Ensign Landscape Design designs landscape plans and plants the material for clients. On April 1, there were three jobs in process, Jobs 39, 40, and 41. During April, two more jobs were started, Jobs 42 and 43. By April 30, Jobs 40, 41, and 43 were completed and sold. The following data were gathered: Job 39 Job 40 Job 41 Job 42 Job 43 Balance, April 1 $570 $3,450 $3,000 - Direct materials 690 600 410 520 $3,520 $6,880 2,550...
Ensign Landscape Design designs landscape plans and plants the material for clients. On April 1, there were three jobs in process, Jobs 39, 40, and 41. During April, two more jobs were started, Jobs 42 and 43. By April 30, Jobs 40, 41, and 43 were completed and sold. The following data were gathered: Job 39 Job 40 Job 41 Job 42 Job 43 Balance, April 1 $570 $3,380 $3,010 — — Direct materials 740 610 370 $3,450 $6,880 Direct...
Ensign Landscape Design designs landscape plans and plants the material for clients. On April 1, there were three jobs in process, Jobs 39, 40, and 41. During April, two more jobs were started, Jobs 42 and 43. By April 30, Jobs 40, 41, and 43 were completed and sold. The following data were gathered: Job 39 Job 40 Job 41 Job 42 Job 43 Balance, April 1 $570 $3,430 $2,990 — — Direct materials 750 520 350 $3,540 $6,870 Direct...
Ensign Landscape Dosign designs landscape plans and plants the material for more jobs were started, Jobs 42 and 43. By April 30. Ihsan and w o mpleted and sold. The following data word game monts. On April 1, there were throo jobs in process, Jobs 39, 40, and 41. During April, two Job 39 Job 40 Job 41 Job 42 Job 43 Balance, April 1 $570 $3,450 $3,000 Direct materials 690 600 410 $3,520 $6,880 Direct labor 520 590 520...
Instructions Ensign Landscape Design designs landscape plans and plants the material for clients. On April 1, there were three jobs in prodals, Jobs 39, 40, and 41. During April, two more jobs were started, Jobs 42 and 43. By April 30, Jobs 40, 41, and 43 were completed and sold. The following data were gathered: Job 39 Job 40 Job 41 Job 42 Job 43 Balance, April 1 $520 $3,350 $2,990 Direct materials 730 530 370 $3,510 2,470 $6,850 3,000...
Ensign Landscape Design designs landscape plans and plants the materials for clients. On April 1, there were three jobs in process - Job 39, 40 and 41. During April, two more jobs were started 42 and 43. By April 30, Jobs 39 and 40 were completed and sold; Jobs 41 and 42 were completed and not sold; and Job 43 was not completed. Direct labor is $10/hour. Overhead is applied at the rate of $32 per direct labor hour. Jobs...
Exercise 4-49: Assume Direct Labor workers make $20 per hour, so with the given labor cost per job, you can determine the number of hours worked. CHANGE the Exercise to say that Overhead is applied at the rate of $32 per direct labor hour. ALSO CHANGE to say that Job #39 and Job #40 were completed and sold, while Job #41 and Job #42 are complete but not sold, and Job #43 is not completed yet. Ensign Landscape Design designs...
Instructions At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $5,250 $1,600 Direct labor 1,500 3,300 Applied overhead 1.125 2,475 Balance, June 1 $7.875 $7,375 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 64 Job 45 Job 46...
Calculator Instructions Labels and Amount Descriptions Income Statement Instructions The following accounts were taken from the Adjusted Trial Balance columns of the end-of-period spreadsheet for April 30, for Finnegan Co.: Amount $32,000 78,000 7.250 Accounts Accumulated Depreciation Fees Earned Depreciation Expense Rent Expense Prepaid Insurance Supplies Supplies Expense 34,000 6,000 400 1.800 Required: Prepare an income statement. Be sure to complete the statement heading. Refer to the lists of Accounts in the information given, Labels, and Amount Descriptions for the...