Requirement 1:- Estimate how much of the $360,520 factory overhead cost at the high level of activity consists of maintenance cost.
Solution:-
Maintenance cost at high level of activity | $74,800 |
Calculation of Maintenace cost
Total factory overhead cost = Indirect material + Rent + Maintenance Cost
$360,520 = (90,400 * $1.80) + $123,000 + Maintenance Cost
Maintenance Cost = $74,800
Indirect material cost per direct labor hour = Total direct materials / Level of Activity
Indirect material cost per direct labor hour = $122,040 / 67,800 = $1.80 per direct labor
Requirement 2:- Using the high-low method, estimate a cost formula for maintenance.
Solution:-
Direct Lbaor hours | Maintenance cost | |
Low Level Activity | $67,800 | $63,500 |
High Level Activity | $90,400 | $74,800 |
Change | $22,600 | $15,700 |
(90,400 - 67,800) | (74,800 - 63,500) |
Compute variable element of cost as per given.
Variable element of cost = Change in maintenance cost / Change in direct labor hours
Variable element of cost = $15,700 / $22,600
Variable element of cost = 0.695 per direct labor hour
Compute Fixed Cost Element
Fixed cost Element = Semi variable cost - Variable cost per unit * labor hours
Fixed cost Element = $74,800 - (0.695.. * 90,400)
Fixed cost Element = $74,800 - $62,800
Fixed cost Element = $12,000
Formula for maintainance cost
Y = $12,000 + $0.695 * X
Requirement 3:- What total factory overhead costs would you expect the company to incur at an operating level of 74,580 direct labor-hours?
Solution:-
Calculation of Total overehead factory costs
Total factory overhead cost = Indirect material + Rent + Maintenance Cost
Total factory overhead cost = ($0.695 * 74,580) + $123,000 + {$12,000 + (0.695 * 74,580)}
Total factory overhead cost = $51,833 + $123,000 + $63,833
Total factory overhead cost = $238,666
Thank you!!!
Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably...
Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overthead costs fluctuate considerably from year to year according to increases and decreases in the number of direct labor-hours worked in the factory. Total factory overhead costs at high and low levels of activity for recent years are given below: Level of Activity Low High 90,400 351,900 Direct labor-hours 67,800 306,700 Total factory overhead costs The factory overhead costs above consist of indirect materials, rent, and maintenance. The...
Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably from year to year according to increases and decreases in the number of direct labor-hours worked in the factory. Total factory overhead costs at high and low levels of activity for recent years are given below: Level of Activity Low High Direct labor-hours 60,300 80,400 Total factory overhead costs $ 257,250 $ 287,400 The factory overhead costs above consist of indirect materials, rent, and...
Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably from year to year according to increases and decreases in the number of direct labor-hours worked in the factory. Total factory overhead costs at high and low levels of activity for recent years are given below: Level of Activ Low 51,000 High 68,000 Direct labor-hours Total factory overhead costs 267,200 $299,500 The factory overhead costs above consist of indirect materials, rent, and maintenance. The...
Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably from year to year according to increases and decreases in the number of direct labor-hours worked in the factory. Total factory overhead costs at high and low levels of activity for recent years are given below: Level of Activ Low 51,000 High 68,000 Direct labor-hours Total factory overhead costs 267,200 $299,500 The factory overhead costs above consist of indirect materials, rent, and maintenance. The...
Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably from year to year according to increases and decreases in the number of direct labor-hours worked in the factory. Total factory overhead costs at high and low levels of activity for recent years are given below: Level of Activity Low High 74,100 98,800 $278,760 $318,280 Direct labor-hours Total factory overhead costs The factory overhead costs above consist of indirect materials, rent, and maintenance. The...
Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably from year to year according to increases and decreases in the number of direct labor-hours worked in the factory. Total factory overhead costs at high and low levels of activity for recent years are given below: Level of Activity Low High Direct labor-hours 69,600 92,800 Total factory overhead costs $ 261,360 $ 298,480 The factory overhead costs above consist of indirect materials, rent, and...
Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably from year to year according to increases and decreases in the number of direct labor-hours worked in the factory. Total factory overhead costs at high and low levels of activity for recent years are given below: Level of Activity Low High Direct labor-hours 67,500 90,000 Total factory overhead costs $ 314,500 $ 364,000 The factory overhead costs above consist of indirect materials, rent, and...
Sawaya Co., ltd., of japan is a manufacuring company whose total factory overhead costs fluctuate value: 2.50 points Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably from year to year according to increases and decreases in the number of direct labor-hours worked in the factory. Total factory overhead costs at high and low levels of activity for recent years are given below: Level of Activity Low High 63,600 84,800 $ 300,620 $347,260...
Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably from year to year according to increases and decreases in the number of direct labor-hours worked in the factory. Total factory overhead costs at high and low levels of activity for recent years are given below: Level of Activity Low High Direct labor-hours 50,000 75,000 Total factory overhead costs $ 14,250,000 $ 17,625,000 The factory overhead costs above consist of indirect materials, rent, and...
THANK YOU ??? I'll remember to thumbs up! Sawaya Co., Ltd., of Japan is a manufacturing company whose total factory overhead costs fluctuate considerably from year to year according to increases and decreases in the number of direct labor-hours worked in the factory. Total factory overhead costs at high and low levels of activity for recent years are given below: Direct labor-hours Total factory overhead costs Level of Activity Low High 56,700 75,600 $292,770 $332,460 The factory overhead costs above...