Answer #1

1. Manufacturing overhead= Total direct labour hoursX overhead rate= (18+28+10) hours*$16= $896

2. TOTAL COST OF JOB 1478= DIrect material+direct labout+manufacturing overhead

  • Direct material    = 985
  • Direct labour = 1118
  • Manufacturing o/h = 896
  • Total cost = $2999
Add a comment
Know the answer?
Add Answer to:
help asap Description: Cherry kitchen nuructing 13. 3. Green cabinets is a coston cabinet builder. they...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Green Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job...

    Green Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job Number 1478), as summarized below: Job Number: 1478 Date Started: 4/07/20x8 Date Completed: 4/22/20x8 Description: Cherry kitchen cabinets Applied Manufacturing Overhead Hours Rate Amount Direct Materials Direct Labor Reg. No Amount Ticket Hours Amount 385 $ 360 128 14 $ 280 391 300 130 28 574 395 155 133 10 240 401 230 Total $1,045 Total 52 $1,094 Cost Summary Direct Material Cost $1,045...

  • Green Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job...

    Green Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job Number 1478), as summarized below: Job Number: 1478 Date Started: 4/07/20x8 Date Completed: 4/22/20x8 Description: Cherry kitchen cabinets Applied Direct Materials Direct Labor Manufacturing Overhead Reg. No Amount Ticket Hours Amount Hours Rate Amount 385 $ 390 128 16 $ 400 391 275 130 688 395 120 133 290 401 265 Total $1,050 Total 53 $1,378 Cost Summary Direct Material Cost $ 1.050 Direct...

  • Green Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job...

    Green Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job Number 1478), as summarized below: Job Number: 1478 Date Started: 4/07/20x8 Date Completed: 4/22/20x8 Description: Cherry kitchen cabinets Applied Manufacturing Overhead Hours Rate Amount Req. No Direct Materials Direct Labor Amount Ticket Hours Amount 385 $ 380 128 17 $ 374 391 230 130 28 630 395 120 133 10 260 401 250 Total $ 980 Total 55 $1,264 Cost Summary Direct Material Cost...

  • Green Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job...

    Green Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job Number 1478), as summarized below: Job Number: 1478 Date Started: 4/07/20x8 Date Completed: 4/22/20x8 Description: Cherry kitchen cabinets Applied Manufacturing Overhead Hours Rate Amount Direct Materials Req. NO Amount 385 $ 300 391 225 395 150 401 215 Direct Labor Ticket Hours Amount 128 16 $ 288 130 23 426 133 12 264 Total 5890 Total 51 $ 978 $ 890 Cost Summary Direct...

  • Geller Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job...

    Geller Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job Number 12478), as summarized below: Job Number:12478 Date Started: 8/05/20x8 Date Completed: 8/25/20x8 Description: Butternut kitchen cabinets Applied Manufacturing Overhead Hours Rate Amount Direct Materials Direct Labor Reg. No Amount Ticket Hours Amount 385 $ 375 128 18 $ 360 391 300 130 27 567 395 135 133 8 156 401 410 141 13 338 Total $1,220 Total 66 $1,421 Cost Summary Direct Material...

  • Help Geller Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets...

    Help Geller Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job Number 12478), as summarized below: Job Number :12478 Date Started: 8/05/20x8 Date Completed: 8/25/20x8 Description: Butternut kitchen cabinets Applied Manufacturing Overhead Hours Rate Amount 4 Direct Materials Direct Labor Reg. No Amount Ticket Hours Amount 385 $ 390 128 16 $ 336 391 305 130 23 506 395 105 133 8 164 401 385 141 14 378 Total $1,185 Total 61 $1,384 Cost...

  • The Modern Company builds kitchen cabinets. On January 1, 2019, one job (D42) was in progress....

    The Modern Company builds kitchen cabinets. On January 1, 2019, one job (D42) was in progress. The order is from Dallas Apartment Corporation and was begun on December 21, 2018. Costs accumulated to date on that job are materials, $1,874; labor, $1,200; and overhead, $480. During January, the following costs were incurred in production work on Job D42 and on Jobs J01 and J02, which were started on January 5, 2019: Materials Labor Overhead Quantity Job D42 $ 540 $...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT