Command Generators is in the process of preparing a production
cost budget for August. Actual costs in July for the production of
60 generators were:
Materials cost | $ | 5,200 | |
Labor cost | 2,600 | ||
Rent | 1,200 | ||
Depreciation | 1,700 | ||
Other fixed costs | 4,600 | ||
Total | $ | 15,300 | |
Materials and labor are the only variable costs. If production and
sales are budgeted to increase to 70 generators in August, how much
is the expected total cost on the August budget?
Multiple Choice
$17,850
$16,600
$9,100
$15,300
None of these answer choices is correct.
In Question Given material and labor are ONLY variable costs that means other costs and expenses (Rent, Depreciation,Other fixed cost ) are fixed i.e remains same irrespective of production
Please refer Below attachment for Answer
Command Generators is in the process of preparing a production cost budget for August. Actual costs...
Brawny Generators is in the process of preparing a production cost budget for August. Actual costs in July for the production of 60 generators were: Materials cost $ 5,200 Labor cost 2,600 Rent 1,200 Depreciation 1,700 Other fixed costs 4,600 Total $ 15,300 Materials and labor are the only variable costs. If production and sales are budgeted to increase to 70 generators in August, how much is the fixed cost per unit on the August budget? Multiple Choice $107.14 $125.00...
Santiago’s Salsa is in the process of preparing a production
cost budget for May. Actual costs in April were:
Santiago’s Salsa
Production Costs
April 2017
24,000
Production
Jars of Salsa
Ingredient cost (variable)
$19,200
Labor cost (variable)
11,520
Rent (fixed)
5,000
Depreciation (fixed)
6,000
Other (fixed)
1,000
Total
$42,720
Using this information, prepare a budget for May. Assume that
production will increase to 28,800 jars of salsa, reflecting an
anticipated sales increase related to a new marketing
campaign.
Santiago's Salsa...
Acme Company’s production budget for August is 18,000 units and includes the following component unit costs: direct materials, $8.00; direct labor, $11.20; variable overhead, $6.00. Budgeted fixed overhead is $44,000. Actual production in August was 18,400 units. Required: Prepare a flexible budget that would be used to compare against actual production costs for August. (Round "Cost per unit" to 2 decimal places.) Original Budget Flexed Budget Cost Formula (18,000 units) (18,400 units) Direct materials Direct labor Variable overhead Fixed overhead...
Acme Company’s production budget for August is 18,300 units and
includes the following component unit costs: direct materials,
$6.30; direct labor, $10.80; variable overhead, $6.50. Budgeted
fixed overhead is $40,000. Actual production in August was 19,110
units. Actual unit component costs incurred during August include
direct materials, $9.00; direct labor, $10.20; variable overhead,
$7.60. Actual fixed overhead was $42,300.
Required:
Prepare a performance report, including each cost component.
(Indicate the effect of each variance by selecting "F" for
favorable, "U"...
Acme Company's production budget for August is 19,000 units and includes the following component unit costs: direct materials, $8.00; direct labor, $11.60; variable overhead, $5.60. Budgeted fixed overhead is $47,000. Actual production in August was 20,445 units. Actual unit component costs incurred during August include direct materials, $9.80; direct labor, $10.00; variable overhead, $6.40. Actual fixed overhead was $50,000. Required: Prepare a performance report, including each cost component. (Indicate the effect of each variance by selecting "F" for favorable, "U"...
Acme Company's production budget for August is 18,000 units and includes the following component unit costs: direct materials, $8.00; direct labor, $11.20; variable overhead, $6.00. Budgeted fixed overhead is $44,000. Actual production in August was 18,400 units. Actual unit component costs incurred during August include direct materials, $9.40; direct labor, $10.00; variable overhead, $6.60. Actual fixed overhead was $46,700 Required: Prepare a performance report, including each cost component. (Indicate the effect of each variance by selecting "F" for favorable, "U"...
Assume that The AM Bakery is preparing a budget for the month ending October 31. Management prepares the budget by starting with the actual results for August 31. Next, management considers what the differences in costs will be between August and October. Management expects revenue in October to be 10 percent more than in August, and it expects all ingredient costs (e.g., flour, butter, and so on) to be 10 percent higher in October than in August. Management expects “other”...
Pronghorn Company uses budgets in controlling costs. The August
2017 budget report for the company’s Assembling Department is as
follows.
PRONGHORN COMPANY
Budget Report
Assembling Department
For the Month Ended August 31, 2017
Difference
Manufacturing Costs
Budget
Actual
Favorable
Unfavorable
Variable costs
Direct materials
$50,740
$49,740
$1,000
Favorable
Direct labor
54,280
51,480
2,800
Favorable
Indirect materials
25,960
26,260
300
Unfavorable
Indirect labor
22,420
21,940
480
Favorable
Utilities
14,750
14,580
170
Favorable
Maintenance
5,900
6,120
220
Unfavorable
Total variable
174,050
170,120...
Pronghorn Company uses budgets in controlling costs. The August 2017 budget report for the company's Assembling Department is as follow: PRONGHORN COMPANY Budget Report Assembling Department For the Month Ended August 31, 2017 Difference Budget Actual Favorable Unfavorable Manufacturing Costs Variable costs Direct materials Direct labor Indirect materials Indirect labor Utilities $50,740 54,280 25,960 22,420 14,750 5,900 174,050 $49,740 51,480 26,260 21,940 14,580 6,120 170,120 $1,000 Favorable 2,800 Favorable 300 Unfavorable 480 Favorable 170 Favorable 220 Unfavorable 3,930 Favorable Maintenance...
Acme Company’s production budget for August is 19,300 units and
includes the following component unit costs: direct materials,
$9.00; direct labor, $11.80; variable overhead, $5.80. Budgeted
fixed overhead is $50,000. Actual production in August was 21,870
units. Actual unit component costs incurred during August include
direct materials, $10.00; direct labor, $11.20; variable overhead,
$7.00. Actual fixed overhead was $53,300. The standard direct labor
cost per unit consists of 0.5 hour of labor time at $23.6 per hour.
During August, $244,944...